Presentation is loading. Please wait.

Presentation is loading. Please wait.

ISOLDE Technical report for INTC 21/5/2007

Similar presentations


Presentation on theme: "ISOLDE Technical report for INTC 21/5/2007"— Presentation transcript:

1 ISOLDE Technical report for INTC 21/5/2007
Mats Lindroos Mats Lindroos

2 Outline Change of responsibilities at ISOLDE Shutdown work
Off-line upgrade REX status Technical R&D at ISOLDE Mats Lindroos

3 New responsibilities at ISOLDE
Technical coordinator Richard Catherall REX ISOLDE superintendent Fredrik Wenander ISOLDE hall superintendent Erwin Siesling New projects and INTC matters Mats Lindroos Mats Lindroos

4 Major 2006/7 Shutdown tasks Yearly facility maintenance: water and power (HT) Instrumentation: migration to linux of scanners & wiregrids Front-Ends: repair of the boris-tubes insulators (R. Catherall) Mini-move: mini-ball into the extension 170 (D. Voulot) REX maintenance: upgrades and repair (F. Wenander) RFQ installation: prim pumps into HRS zone (E. Siesling) Various work: laser windows, PLC update, ADC replace,etc. Mats Lindroos

5 Improvement on the shutdown
Dedicated and responsible person appointed for each major task Weekly technical shutdown meeting Close follow-up and adaptation of the planning Daily start-up meeting at beginning of the run Mats Lindroos

6 Results 2007 smooth start-up No hardware failures or over-run of work
Expected software debugging (i.e. scanner & wiregrids applications) BUT.. Unexpected (minor) controls problems (PS wide, AB/CO addressed) Mats Lindroos

7 Off-line separator upgrade
New magnet coils to replace old faulty coils Survey points for the alignment of the offline separator installed and documented New beam diagnostic chamber with mechanical slit system and “ISOLDE type” scanner installed Special thanks to Jerome Sarret, Erik Asen, Antony Newborough, Michel Duraffourg Mats Lindroos

8 Automatic mass program
Labview based control system communicating directly to PLC’s via RPC server Response time: CCV to PLC <900ms Refresh rate 100ms Automatic mass program 15 minutes for masses with 0.1 mass unit resolution Mats Lindroos

9 REX low energy stage Trap EBIS
Operational and in standby mode. Minor improvements during shutdown. Have delivered some stable beam to Witch. EBIS The general power cut in March partly vented the machine preventing us from doing further electron beam tests with the post anode. The newly inserted cathode did not perform as expected and had to be exchanged.  The machine is up running with a new cathode. Beam has been injected and extracted through the separator The old control system has been exchanged to a AB supported system. Still running with a temporary application programme Mats Lindroos

10 The constant “quest” for efficiency
7Li 238U 27Al 116Cd Efficiencies for beams 2006 Tot. eff. = Trap × BTS × EBIS × Sep  REX low energy stage now covers A=7 to >200 with total efficiencies of at least 5%  High current beams can now be charge breed with some efficiency (e.g. 1.8% for a 3nA 7Li+ beam into 7Li3+)  Light ions still difficult to breed ≤5% -> Charge breeder : generally aiming for 10% total efficiency! -> Linac efficiency 70-85% (aim for >80% in 2007) Mats Lindroos

11 Isotopes and elements run at REX so far…
8Li3+,9,11Li2+ 10,11,12Be3+,4+ 17F5+ 24-29Na7+ 29,31Mg9+, 28,30,32Mg8+ 68Ni19+ 67-71,73Cu19+,20+,20+,19+ 80Zn21+, 74,76,78Zn18+ 70Se19+ 88,92Kr21+,22+ 108In30+ 108,110Sn27+,30+ 122,124,126Cd30+,31+ 138,140,142,144Xe34+ 148Pm30+ 153Sm28+ 156Eu28+ Mats Lindroos

12 * Phase 1 = First phase of a full installation
Minimove - Phase 1 Installation in progress! * Phase 1 = First phase of a full installation (linac upgrade, recoil separator, HIE-Isolde…) * Goals : 1. create space (linac upgrade, space around experiments) 2. improve shielding from X-ray background at Miniball 3. improve beam properties -> more focussing -> more beam diagnostics -> realignment of beamlines New section Mats Lindroos

13 Beam optics calculation 9-GP to MB target * 3MeV/u A/q3.5
* 0.6π.mm.mrad normalised * ±1% energy spread Diploma Thesis by T. Arronsson Mats Lindroos

14 Linac emittance measurements
Results * Normalised transverse emittance (2σ RMS) = 0.21±0.07 π.mm.mrad at 2.2MeV/u * Low intensity few 100pA (no space charge effect in EBIS!) * Horizontal emittance larger than vertical after the bender (energy spread) * Emittance increased when going from 1.2 to 2.2 MeV/u (mismatch between IHS and 7gaps?) * Emittance increased with stripper foils Y direction after 2.5m drift MeV/u Energy spread = ±0.03MeV/u @ 2.97MeV/u (±1%) Continuation 2007 * Verify results with uninterrupted measurement series * Verify influence of EBIS operation conditions on the emittance * Measure at 3MeV/u and 300keV/u Mats Lindroos

15 Technical R&D at ISOLDE
Dual transfer lines Merging of neutral beams Mono ECR Tendering for new solid state laser for RILIS Progress on LARIS installation ECR PHOENIX charge breeder development RFQ cooler off-line commissioning Mats Lindroos

16 Background >5nA 2<A/q<7
Results CW Pulsed 86Kr13+ 86Kr % 132Xe18+ 1% Preliminary Afterglow 4<A/q<8 h=2-7% CW DV tuning Stable background Background >5nA 2<A/q<7 P. Delahaye et al., RSI 77 03B105 (2006)

17 ~5p·mm·mrad 90% emittance ~30p·mm·mrad 90% emittance as input
RFQ cooler “ISCOOL” Continuous mode Emittance meter ~5p·mm·mrad 90% emittance ~30p·mm·mrad 90% emittance as input Ongoing tests with the bunching mode Last off-line tests with a FEBIAD source delivering noble gas ions RFQ cooler Ion transmission Li+ 17% Na+ 27% K+ 60% Cs+ 70% E. Mané, H. Frånberg, P. Delahaye Alkali ion source


Download ppt "ISOLDE Technical report for INTC 21/5/2007"

Similar presentations


Ads by Google