FOUO B-1 Recovery
2
69 Hours from Mishap to Resumption of Full Runway Operations
Timeline FOUO 8 May 2220L – Mishap 9 May 1300L – CAT Plan & Engineering Analysis 10 May 1000L – Pre-lift Brief 10 May 1700L – Staging 11 May 0700L – Safety Brief 11 May 0800L – Resurrection 11 May 1800L – Towed to Parking 11 May 2000L – Resume Full Runway Ops 69 Hours from Mishap to Resumption of Full Runway Operations
3
FOUO Lift Day
4
Forward Fuselage Crane / Strap Placement
FOUO Forward Fuselage Crane / Strap Placement
5
Shoring & Lift Bags to Stabilize Wings During Lift
FOUO Shoring & Lift Bags to Stabilize Wings During Lift
6
Placement of Front Jacks
FOUO Placement of Front Jacks
7
Four (4) 21K Blocks as Mooring to stabilize Front Jacks
FOUO Four (4) 21K Blocks as Mooring to stabilize Front Jacks
8
Aft Fuselage Crane / Strap Placement
FOUO Aft Fuselage Crane / Strap Placement
9
Lift Bags Inflated to Stabilize Wings During Rear Lift
FOUO Lift Bags Inflated to Stabilize Wings During Rear Lift
10
Placement of Rear Jacks
FOUO Placement of Rear Jacks
11
FOUO Alternate Gear Extend
12
On her Three (3) feet … Ready to Tow
FOUO On her Three (3) feet … Ready to Tow
13
FOUO On the home stretch
14
The coalition team that made it happen!
FOUO TSgt Epps Lift Supervisor Chief John Lift Director Lt Col Foster Team Director Maj Barack Team Lead The coalition team that made it happen!