Download presentation
Presentation is loading. Please wait.
Published byTanner Gimbert Modified over 10 years ago
1
© Copyright, 2009, S. Leigh Geiger & Associates, Inc. Using MsProject for Earned Value Calculations Advanced MsProject Course Dr. Leigh Geiger
2
© Copyright, 2009, S. Leigh Geiger & Associates, Inc. Set Up Process 1. Create Project Plan 2. Baseline the Plan 3. Track progress/actuals & update the plan 4. Set the Status Date 5. Select the Earned Value method 6. Use MsProject EV Views & Reports
3
© Copyright, 2009, S. Leigh Geiger & Associates, Inc. Set Up Process Create Project Plan Baseline the Plan Track progress/actuals & update the plan 4. Set the Status Date 5. Select the Earned Value method 6. Use MsProject EV Views & Reports
4
© Copyright, 2009, S. Leigh Geiger & Associates, Inc. Earned Value Methods % Complete Calculated for each task: [Act Dur/Dur]*100 If you enter it directly -Project calculates Act. & Rem. Duration Use if actual work is entered Physical % Complete Not calculated, must be entered directly Use if Actuals aren’t accurate Possible to use up 90% of total task duration and still be only 10% Physical Complete, e.g., when most work is planned for the last minute.
5
© Copyright, 2009, S. Leigh Geiger & Associates, Inc. EV Terms in Project Old TermNew Term BCWSPV BCWPEV ACWPAC
6
© Copyright, 2009, S. Leigh Geiger & Associates, Inc. EV Views & Reports Table Views Earned Value Earned Value Cost Indicators Earned Value Schedule Indicators Cost Reports Earned Value Visual Reports EV Over Time
Similar presentations
© 2024 SlidePlayer.com Inc.
All rights reserved.