Presentation is loading. Please wait.

Presentation is loading. Please wait.

SF6 Leak Repair Case Study ConEd West 49th Street GIS Jonathan Brengel, ConEd Liisa Colby, The Colt Group.

Similar presentations


Presentation on theme: "SF6 Leak Repair Case Study ConEd West 49th Street GIS Jonathan Brengel, ConEd Liisa Colby, The Colt Group."— Presentation transcript:

1 SF6 Leak Repair Case Study ConEd West 49th Street GIS Jonathan Brengel, ConEd Liisa Colby, The Colt Group

2 Agenda Station Overview SF6 Emissions Summary Leak Identification
Repair History Alternative Solutions Repair Cost Issues Moving Forward The Leak Repair Process Other SF6 Repair Examples

3 Station Overview

4

5

6 Station Overview West 49th Street Substation reduces voltage from 345 kV to 138 kV Five 345 kV feeders Two from Sprain Brook Substation Two from East 13th Street Substation One inter-utility feeder from Public Service Electric and Gas Company Eleven 138 kV feeders from the station supply W 42nd St., W 50th St., W 65th St. and Astor Substations Gas Insulated Switchgear (GIS) at the station was put into service in 1978 No design requirements to control leakage were in place in 1978 Fifteen SF6 insulated 345 kV and 138 kV bus sections Five autotransformers Ten 345 kV circuit breakers

7

8

9 SF6 Historical Emissions
2,049 lbs. of SF6 Emissions from West 49th Street in Accounts for ~17% of total SF6 emitted for entire company in 2015 *Gas call data improvements were implemented during 2014 resulting in enhanced data accuracy during the 2nd half of 2014 onward Areas of greatest concern Transformer 3 secondary bus, Bus Section 3, Transformer 5 secondary bus 49th Street Substation SF6 Annual Emissions Summary 2014 2015 YTD Total SSO SF6 Emissions (lbs) 15,901 12,682 Total 49th Street (lbs) *1,576 2,049 % of Total SSO Emissions 9.91% 16.20%

10 SF6 Historical Emissions
Transformer 3 Secondary Bus Section 24 gas calls in 2014 For each gas call a mechanic attempted to find a leak Average leak identification time of 4 hours x $85/man-hour x 24 gas calls = $8,160 366 lbs. SF6 emitted 2015 27 clamps, 8 bypasses and 9 patches on bus work currently *Gas call data improvements were implemented during 2014 resulting in enhanced data accuracy during the 2nd half of 2014 onward TR3 SF6 Annual Emissions Summary *2014 2015 Total TR3 Secondary Bus (lbs) 421 366 Total Bus Section 3 (lbs) 263 217 Total TR5 Secondary Bus Section (lbs) 88 249

11  Leak Identification & Sampling Techniques Minimize number of samples
ZERO Purge SF6 Analysis Previously emitted 2 lbs per sample lbs released per year New DILO SF6 gas analyzers Improved tool for leak detection FLIR GF306 SF6 Camera 11

12 49th Street Substation SF6 Repair Summary
SF6 Leak Repair Status 94 100 35 49th Street Substation SF6 Repair Summary Total clamps installed (including on bypasses) Total bypasses Total patches Total Active leaks Clamp on leaking bypass in Transformer 3 Secondary Bus Clamp on leaking flange in Bus Section 7 Welded patch on secondary CCPD

13 Colt Clamp Temporary Repairs
$263,000 in O&M spent in 2014 on clamps $324,000 spent in O&M already through September of 2015 Estimating $162,000 to be spent on clamps/repairs during remainder of year ~$4,000 to $15,000 per clamp Concern with added weight, structural integrity, bus failure, etc. Aluminum clamps may also be used - Lighter weight but more expensive Moving forward, all clamps require supports 2 year Warranty

14 Examples: Colt Clamp Repairs

15

16 Permanent Repairs Eliminate centralized gas fill system
Remove clamps on leaking welds and re-weld/repair (outage required) Currently planning to remove 5 clamps and repair welds on TR5 secondary during fall outage NDE testing on patches/welds that aren’t clamped to identify possible future leak areas Replace temporary bypass piping clamps with stainless tubing and DILO self-sealing fittings

17 Equipment Replacement
Install a circuit breaker on each 138 kV feeder leg (2 circuit breakers, disconnect switches, all buswork) Estimated at $2.3 million per each 138 kV section (equipment cost only) Maintain reliability advantages Replace a 345 kV Bus Section (circuit breaker, potential transformer, disconnect/ground switches, bus, LCC, adapter flanges and structures) Estimated at $1.75 million per bus section (equipment cost only) ~14 to 16 month delivery and installation

18 West 49th Street 2015 Annual SF6 O&M Costs
Additional Costs West 49th Street 2015 Annual SF6 O&M Costs Item Total Cost Clamp Installation $486,000 SF6 Gas Added ($8.50/lb) $19,920 Daily Leak Locating/Repairs $180,000 Split TR Secondary Alarm Points $74,000 Install Supports on Existing Clamps $42,000 Fall Outage Leak Repairs $173,000 Chem Lab - Gas Sampling/Outage Support $29,400 TOTAL PROJECTED COST $1,004,320 *Project annual costs based on actual spent YTD

19 Issues Lack of O&M funding
No long range plans to replace equipment and no plan for added capacity Limited availability for outages

20 Moving Forward How do we help meet future goals?
15,000 lbs. – 2015 (equivalent to 7% of nameplate) 14,000 lbs. – 2016 proposed goal 13,000 lbs. – 2017 proposed goal Continue to leverage capital programs Circuit Breaker Reliability Program SF6 GIS Bus Overhauls AGS Retirements SF6 Peer Management Team SSO/EH&S-Air/Chem Lab/Engineering/TLC Monthly meetings to keep lines of communication open Maintain focus, identify and work through issues together

21 The Leak Repair Process

22

23 Options for dealing with leaks:
Let it leak If oil is getting out, air and moisture are getting in Re-gasket or replace Cost, outage time, resources required In-house Repair (Epoxy) Not always effective Use Outside Repair Specialists An alternative worth considering

24 No need to drain the oil or gas or depressurize
Benefits of Online Leak Repair for HV App No need to drain the oil or gas or depressurize Many repairs can be made under pressure – energized The sealant is not an epoxy – it’s flexible and easily removed

25 Epoxy – can’t be easily removed Do-it-yourself Kit
Common Misconceptions of Leak Repair It’s a band-aid What is temporary? Epoxy – can’t be easily removed Do-it-yourself Kit Concerns about the sealant

26 A Proven Process 15,323 jobs completed since 2002 6,286 Flanges
5,691 Valve packings 1,045 Custom clamps & enclosures 875 Drain plugs 287 Cover plates 91 Miscellaneous Tap changer flanges 24 CTs 987 re-pumps over twelve years or 6.4%. A 93.6 success rate

27 The History of Online Leak Repair

28 Leak Sealing Today Pressures up to 7,500 psig Temperatures from Cryogenic to 1800 F

29 After 20+ Years of Experience

30 Oil Leak Flange Repair using “Drill & Tap” injection

31 About The Sealant Independent Lab Report Results:
Dissolved Gas in Oil (DGA) Dielectric strength Minus 40 degrees C/F – 40 degrees C/F Sealant is NOT an epoxy - It’s flexible and easily removed.

32 Manufacturer Warranty TC Flange Repair
Sealant injected via Injectable Bolts Repair made with unit in service

33 Custom Clamps & Enclosures Thread Leak on Valve (Bar Clamp)
33

34 Alliant Energy Eddyville Substation 69 kv SF6 Breaker Eddyville, Iowa
SF6 Leak Repair Example Alliant Energy Eddyville Substation 69 kv SF6 Breaker Eddyville, Iowa

35

36

37

38 Client options Let it leak. Not an option, environmental concern
Re-gasket. Time to take the breaker out of service was the primary issue. Would require 5 days of down time, loss of transmission and $20, in costs Leak Repair – Installing custom enclosure and injecting sealant. Determined the optimal solution Justification: Reduced downtime for critical apparatus. Just 1 day of down time and $20, to fix all leaking components Savings = 4 days of transmission

39

40

41

42

43

44

45 SF6 Circuit Breaker - Casting Leak
.

46 SF6 Circuit Breaker - Casting Leak
SF6 Leaks SF6 Circuit Breaker - Casting Leak

47

48 Ongoing Research….

49 Clamp Removal

50 Sealant Removal

51 Thank you


Download ppt "SF6 Leak Repair Case Study ConEd West 49th Street GIS Jonathan Brengel, ConEd Liisa Colby, The Colt Group."

Similar presentations


Ads by Google