Variation and Control Charts A Leadership Perspective

Similar presentations


Presentation on theme: "Variation and Control Charts A Leadership Perspective"— Presentation transcript:

1 Variation and Control Charts A Leadership Perspective
Please give credit to when using this presentation.

2 How Do We Look at Data? Sales (000) in Jan-10: $11,229
A number by itself has little meaning. So, we naturally want to compare it to something. But to what? Budget for Jan-10: $10,000 Sales in Jan-09: $7,997 Typical comparisons include: This month’s result to last year’s result This month’s result to budget YTD result to last year’s YTD YTD result to budget

3 Financial Reports First Quarter Sales: 1Q 2010 Budget Variance 2Q 209
30,148 30,000 148 23,823 6,325 Second Quarter Sales: 2Q 2010 Budget Variance 2Q 2009 Sales $ 27,460 30,000 (2,540) 33,545 (6,085) YTD Sales: 2010 YTD Budget Variance 2009 YTD Sales $ 57,608 60,000 (2,392) 57,368 240

4 Variation in Metrics Sales in Jan-10: $11,229 Sales in Feb $10,016 Are these two numbers the same? The measurements we take reflect the variation in the process. The problem with measurement systems that compare one time frame to another (like the financial report) is that the actual performance (variation) of the process is hidden – we don’t know if there are special causes or just common causes.

5 Measurements and the Underlying Process
Let’s return to the financial report from before – things did not look too good – especially in the second quarter. Let’s explore another method of examining the data that reveals the “voice of the process” – the true performance. 2010 YTD Budget Variance 2009 YTD Sales $ 57,608 60,000 (2,392) 57,368 240

6 Measurements and the Underlying Process
The table below shows the monthly data used to make the earlier tables. What does this data tell you? Often, it is difficult to understand the process by looking at a table of numbers. Month Sales Jan-09 7997 Jul-09 8133 Jan-10 11229 Feb-09 9132 Aug-09 7215 Feb-10 10016 Mar-09 6694 Sep-09 8278 Mar-10 8903 Apr-09 10005 Oct-09 11117 Apr-10 9617 May-09 12055 Nov-09 6481 May-10 8190 Jun-09 11485 Dec-09 6897 Jun-10 9653

7 It is often better to examine the data as a time series chart.
No major change in monthly sales - some months better than others Financial report indicated a problem (2Q 2004) Time series tells a different story There is a problem though – sales aren’t increasing

8 Adding the average line helps with interpreting the process behavior
Nine points above, nine points below Monthly sales fairly predictable Range from about $600,000 to about $1,200,000 Can provide an early warning of problems

9 Control Limits The time series charts can be further enhanced by adding control limits These limits define the boundaries for common causes of variation With common cause of variation: The upper control limit (UCL) is the largest value you can expect The lower control limit (LCL) is the smallest value you can expect As long as the all the points are within the limits and there are no patterns, only common cause of variation is present The process is said to be “in control” To improve it, you must fundamentally change the process UCL LCL

10 Sales chart with control limits
Process is “in control” Can predict what will happen in the future It is not the limits, but the story that the chart tells Provides feedback on whether the process is changing or staying the same

11 Interpreting Time Series Charts
Points beyond the limits UCL Avg LCL Special cause

12 Zones Test The zone tests are valuable tests for enhancing the ability of control charts to detect small shifts quickly. The first step in using these tests is to divide the control chart into zones. The chart is divided into six equal zones: three above the average and three below the average. UCL LCL Avg A B C

13 Test for Zone A X= Out of Control Point UCL LCL Avg A B C X A special cause of variation exists if there are two out of three consecutive points in zone A or beyond (on one side of the average).

14 Test for Zone B X= Out of Control Point UCL LCL Avg A B C X A special cause of variation exists if there are four out of five consecutive points in zone B or beyond (on one side of the average).

15 Test for Zone C X = Out of Control Point UCL LCL Avg A B C X A special cause of variation exists if there are seven or more consecutive points in zone C or beyond (on one side of the average).

16 Rule of Seven Tests UCL Avg LCL
Seven Points in a Row Above the Average Seven Points in a Row Below the Average Seven Points in a Row Trending Down Seven Points in a Row Trending Up

17 In Control or Out of Control?

18 Summary Special or Common?