Presentation is loading. Please wait.

Presentation is loading. Please wait.

Turnaround: from LHC to FCC?

Similar presentations


Presentation on theme: "Turnaround: from LHC to FCC?"— Presentation transcript:

1

2 Turnaround: from LHC to FCC?
David Nisbet, with input from K. Fuchsberger

3 Outline LHC turnaround in 2016 LHC v FCC Conclusions

4 Efficiency: turnaround and beam cycle
Turnaround Time Beam Cycle Time Turnaround time Stable beams to Stable Beams A total of 157 fills in 2016 Beam cycle time Only physics fills that arrived to Stable Beams A total of 179 fills in 2016 General Only proton fills are considered Beam mode declaration time is used (from logging DB) CRS to 3m Squeeze to 40cm TOTEM bump Standard, BCMS RB.A12 RQ5.L1

5 Turnaround See Evian presentation for more details 2015 2016 Min 2.5 h
p-p physics, ignoring faults > 24 h Fills following accelerator mode change have no associated turnaround Following the Restart, Technical Stops, Special Physics Commissioning, Machine Development 2015 2016 >4h = faults & measurements 2016 2015 Min 2.5 h 2.2 h Median 5.2 h 6.3 h Mean 7.1 h 6.6 h K. Fuchsberger, M. Solfaroli + AWG (CERN-ACC-NOTE )

6 Clean turnarounds 14 Turnarounds No gap in Fill-number No fault
No Precycle No EOF MD 14 Turnarounds 2016 Min 2.50 h Median 2.67 h Mean 2.74 h

7 Injection (physics beams)
Injection in 2016 limited to 96b/injection 46 injections for 2076b Nominal (t_fill_min = ~26mins) 48 injections for 2220b BCMS (t_fill_min = ~28mins) For fills reaching STABLE BEAMS In 2015: 122 fills, with an average of 761b up to 144b/inj In 2016: 179 fills, with an average of 1688b up to 96b/inj 127 fills with >2000b 2016 (>2000b) 2015 Beam Quality Dumped while injecting average for 2016 (<2000b) = 32min/579b Aug-16 21:08: SPS RF cavity Aug-16 15:13: ADT adjustments Aug-16 19:30: Normal 16-Aug-16 09:53: min SPS no beam then normal fill Several factors impact the injection process: Train length, TL steering, SPS super cycle length, BQM setup, Injector beam quality + availability, intensity (vac, cryo, etc) Faults and machine setup 2016 >2000b 2016 2015 Median 37.8 min 37.0 min 44.1 min Mean 42.1 min 39.2 min 48.2 min

8 Adjust ADJUST in 2016 = TOTEM dispersion bump, collide IPs 1+5, collide IPs 2+8 Optimisation after finding collisions requires operator interaction 2015 2016 15x EoF MDs removed from data Checks and problem solving Totem bump played at end of squeeze. 20 – 25 mins = regeneration, alternative check (ADT, BSRT, etc) 25 – 30 = mixed. Some long adjusts. Regeneration + lumi publication. 53min (fill 5370) = CMS lumi very difficult to find. MD but normal collisions (6 Oct) – effect of bump in 5R. 78min (fill 5330) = BPM faults prevent declaring SB. 2016 2015 Min 9.2 min 4.9 min Median 14.1 min 12.5 min Mean 16.2 min 13.7 min

9 Turnaround in one go Beam Mode LHC Theory 2015 LHC Median
2017 LHC Median (estimate) 2016 FCC Theory (estimate) 2017 FCC Median (estimate) SETUP 10 min 222.7 min 158.5 min 147.0 min 10 + ? min INJECTION 38 min 58.1 min 51.6 min 40 min 40 + ? min PRERAMP 4 min 5.4 min 4.2 min 3 min 5 min RAMP 20 min 20.4 min 19 min FLATTOP 4.8 min 0 min SQUEEZE 18 min 13.1 min 18.0 min 11 min ADJUST 12.5 min 14.1 min 5min RAMP DOWN 31 min 41.0 min 40.0 min TURN-AROUND 2.2 hrs 6.3 hrs 5.2 hrs 4.5 hrs 1.8 hrs 1.8 + ? hrs

10 Observations Clearly the greater the size of the machine the more systems are required One must ensure design for availability Otherwise it is unreasonable to use the LHC figures directly without mitigation In my limited experience, the median value is a useful indicator of efficiency The large outliers tend to push the average up disproportionately Turnaround estimates for a realistic machine should include both ‘theoretical minimum’ and ‘realistic forecast’ Method for realistic forecast? Turnaround (min) + t_fault (median) = 1.8hrs + 2 hrs? The FCC relies heavily on the availability and injection time being close to forecast In the LHC scenario, can it really cycle 4x in ~40 mins? In my opinion, more data should be provided to justify why this is achievable

11 Conclusions The LHC does a little more in a little less time in 2016 compared to 2015 Ratio of median / theory was 2.8 in 2015, 2.3 in 2016 Could trend to 2.0 in 2017 (if fault statistics remain similar) BUT Data from 2015 and 2016 shows long tails As clearly stated in 2016 paper, must assume some distribution in estimate Mitigating arguments should be provided if the theoretical value is retained as baseline (applies both for LHC and FCC) , for example design for availability The estimate made in 2016 is a reasonable ‘theoretical minimum’ Theoretical minimum for FCC = 1.8 hrs Assumes circuits are designed to ramp down inside time of main dipole ramp (not the case in the LHC today) However turnaround estimates for a realistic machine should include both ‘theoretical minimum’ and ‘realistic forecast’ Method for determining realistic forecast needs to be evaluated and agreed… In particular the times for ‘setup’ and ‘injection’ Apply same methods to both and FCC…

12 References FCC-hh turn-around cycle, R Alemany Fernandez et al, CERN-ACC Concepts for magnet circuit powering and protection, M. Prioli, FCC Week Rome 2016


Download ppt "Turnaround: from LHC to FCC?"

Similar presentations


Ads by Google