Presentation is loading. Please wait.

Presentation is loading. Please wait.

Z26 Project Management The Effectiveness of Workshops Graham Collins University College London (UCL) graham.collins@ucl.ac.uk.

Similar presentations


Presentation on theme: "Z26 Project Management The Effectiveness of Workshops Graham Collins University College London (UCL) graham.collins@ucl.ac.uk."— Presentation transcript:

1 Z26 Project Management The Effectiveness of Workshops Graham Collins University College London (UCL)

2 Objectives Outline the scoping and process modelling of a blueprint ‘strategic project’ Problems encountered Lessons learnt

3 The Challenge of Programme Management
Large scale complex change Final result often unpredictable Varied interpretations of transition path

4 Initial objective Ensure alignment of objectives
Provide sound basis for transition without this the programme is likely to veer off course

5 MSP ‘The Blueprint should be maintained and refined throughout the programme’ Managing Successful Programmes, 1999, OGC

6 Blueprint How the organisation will operate when the programme has been completed Blueprint should be refined throughout the programme Expression of the future, encompassing processes operations etc linked to operational performance to ensure desired effects are realised

7 Use of blueprint Focus for where programme is heading
Basis for evaluation Basis for impact of change

8 Need to create a vision to work towards
Programme Identification Programme Definition Consensus on scope concept model i.e. future state Communication tool learning tool

9 Invitation Programme had been running 7 months
High level of frustration with consultancy already under contract No programme definition

10 Initial presentation Our approach to programme and project management
including iterative and incremental approaches in real-time workshops

11 The Usage Pattern Mission Objectives Task Object Model
Class Object Model Code Consistency

12 Follow up meeting It was clear that a lack of progress was causing concern Political issues were hindering progress The ‘strategic project’ had become centred on definitions of BPR, Business Improvement etc.

13 Proposal Get the strategic project on track
Ascertain whether approach to project management including workshops would be useful Create ‘buy-in’ from all stakeholders including consultancy already under contract

14 Project far too complex
BPR projects Information systems Strategic communications

15 Initial workshops Two dates were set First workshop covered scope
Second workshop business modelling

16 Scoping workshop Day 1 Iterative and incremental approach
‘Buy-in’ created by careful selection of staff and using dialogue in workshop Mission statements were broken down into objectives

17 Modelling workshop Day 2
Objective was to create the optimal strategic communications model The new structure was modelled real-time using software developed for the workshop and consensus reached Software included a metrics suite and Work Breakdown Structure (WBS) that could be viewed from different perspectives

18 Schedule Initial consultancy under contract Workshops Blueprint
Target date abandoned Oct 1998 original target date Initial consultancy under contract Workshops Blueprint Programme identification Programme definition Mar 1998 Nov Consultancy B contacted Feb 1999 Mar 1999 Blueprint completed

19 Benefits Realisation Strategic goals Programme identification
Process view conceptual models process /organisation cross reference At programme definition the future state is finalised and the tranches for programme delivery. Initial blueprint a major deliverable in this second phase.

20 Benefits - Communication
Creation of natural owners Communication tool Focus, risk management, and evaluation of alternative ideas

21 Benefits - Consensus Moved away from discussions of BPR v Business Improvement Blueprint model created and agreed on ‘Strategic project’ achieved within original timescale set

22 Champions Champions were created which helped the programme spread more rapidly ‘Most often, the champion is intrigued by the technology ‘silver bullet’…. …and may have even suggested that the project manager use it.. Edward Yourdon, Death March - the complete software developer’s guide to mission impossible projects, Prentice Hall 1997

23 Learning Points 1 Here it was essential to gain commitment ie ‘buy-in’ from all parties Workshops were the only way forward There were too many stakeholders with differing objectives to have chosen any other approach

24 Learning Points 2 The lack of clearly defined goals were hindering progress The scope i.e. what is in and what is outside the project as well as the goals of the ‘strategic project’ needed to be defined

25 Learning Points 3 The lack of tranching of the ‘strategic project’ caused confusion The WBS was agreed with senior staff and further refined in the workshops that followed This had a three fold effect, clarity of objectives, instilling confidence in programme staff, and being able to readily identify staff to manage individual projects

26 Learning Points 4 Project managers must frame the challenge
The teams must be designed for learning There must be an environment of psychological safety Harvard Business Review October 2001, Best Practice, Speeding up team learning Amy Edmondson et al.


Download ppt "Z26 Project Management The Effectiveness of Workshops Graham Collins University College London (UCL) graham.collins@ucl.ac.uk."

Similar presentations


Ads by Google