Limpopo Provincial Government
Department of Roads and Transport Infrastructure Conditional Grant EPWP Expenditure Presenter M.M Makibelo HOD
2
Introduction The Province has a challenge of linking the economic hubs to stimulate Economic growth. Being rural Province the provincial plan is to make sure that motorists does not drive more than 10 km before they can reach tar road. The Department utilized 100% of the Conditional Grant on projects during the previous financial year. EPWP fencing projects: Fence is being stolen along the roads by community members, thus stray animals still impose danger to the road users. EPWP road construction and maintenance project: (i) Emerging contractors do not have finance to sustain their businesses which compel some of the projects abandoned. (ii) Lack of management skills.
3
ALLOCATION OF GRANTS AND EPWP BUDGET, TO 2006/07 TO 2010
2006/07. 2007/08 2008/09 2009/10 Budget Expenditure Expenditure Item R'000 Conditional Grant 291,786 377,096 380,950 415,748 EPWP- Gundo Lashu 41,000 39,743 31,243 35,180 84,244 EPWP – Fencing Project 10,000 9,151 32,122 32,382 68,762 TOTAL 342,786 340,680 440,461 53,461 448,512 568,754
4
Infrastructure Conditional Grant 2006/07
RAL NO. ROAD NO. DESCRIPTION ACTIVITY LOCAL MUNICIPALITY DISTRICT BUDGET R'000 YEAR END EXPEND R'000 BALANCE R'000 % COMPL 341 D19 Polokwane-Matlala-Tibane Upgrading(gravel to tar) Polokwane Capricorn 26,434 26,184 250 100 346 D3840/D3187/D3981/D3260 Giyani to Phalaborwa Giyani/ Ba-Phalaborwa Mopani 26,222 26,159 63 100 347 D4100/D4250/ D4191/D4190 Flag Boshielo Dam (Serageng) to Veeplaats to Apel and Apel to Mmabulela Makhuduthamaga Sekhukhune 350 D3500,D4380, D3505,D3561, D192 GaKgabudi to Mapela to Bakenberg to Mogalakwena to Marulaneng to Segole to Rapadi to Marken Mogalakwena Waterberg 26,088 25,798 290 351 D3110 Ga-Seleka to Shongoane 23,534 22,842 692 352 D1589, D217 Schiermonikoog to Kromhoek Blouberg 33,775 32,348 1,427 353 P277/1 Makonde to Masisi Thulamela/ Mutale Vhembe 30,418 30,417 1 375 D21 Sekororo to The Oaks Maruleng 18,137 16,876 1,261 376 D4285/D4373/ D4300,D4300 Maseremole/Nebo-Mabitwane-Ragaphela-GaMatlala-Madiilo - Mamphokgo. Makhudutamaga/ Marble Hall 36,051 35,953 98 313,163 305,117 8,046
5
PROJECTS FOR 2007/2008 - CONDITIONAL GRANTS UPGRADING
RAL NO. ROAD NO. DESCRIPTION ACTIVITY LOCAL MUNICIPALITY DISTRICT 2006/2007 BUDGET 2007/2008 BUDGET 355B D3810/D3981/ D3811 Thomo/Altein (Shangoni KNP gate) to Khakhala to Gawula to Mahlathi to Ndindani to Hlomela to Phalaubeni to Mbaula to Phalaborwa Upgrading (gravel to tar) and bridges Construction Giyani Mopani 15.211 369 D3708 Mukula to Mhinga Upgrading(gravel to tar) Thulamela Vhembe 18.000 46.800 386 D3246,D3186, D3849,D3847, D3982 Mamitwa to Xihoko to GaMokgwathi to Makhuva Tzaneen/ Giyani 12.000 38.500 387 D3398/D3332 Ceres WF Knobel Hosp. to Rapitsi Bochum Aganang/ Molemole Capricorn 9.000 38.400 389 D1897 Radium Road (P1/3 to NW/ Cyferskuil) Bela Bela Waterberg 7.127 17.000 390 D3180 Modjadji-Mokwakwaila-Bambeni-Nkomo. Letaba/Giyani 43.000 459 D3600 Elandskraal to Magatle Marble Hall Sekhukhune 0.000 20.000 460 D3231 Thakgalani Maintenance: Bridge reconstruction Letaba 6.500 461 D979, D1350 Tzaneen to Deerpark and Deerpark to Mokwakwaila Mainenance: Bridge 1933 repairs and Bridge UNL02 Tzaneen 8.900 464 D2219/D4295/ D1547 Jane Furse to Motetema to Groblersdal Maintenance Fetakgomo/ Tubatse 8.000 455 P62/2 P51/3 to Groblersdal/ N-Province Greater Groblersdal
6
PROJECTS FOR 2007/2008 -CONDITIONAL GRANTS MAINTENANCE, cont…
484 D1296, D1261 P169/2 to Lydenburg/Lebowa and road P169/2 to road D212 Maintenance Greater Tubatse Sekhukhune 0.000 7.500 485 D1458, D4100 D1547/ Groblersdal to D1547/ Marble Hall Greater Marble Hall 27.000 486 P116/1, P170/1 Lydenberg and road P116/1 to Mpumalanga border 12.000 487 P169/2, D737 P169/1 & D212 to P33/2 and road P169/2 to Mpumalanga 38.000 488 P169/3 P33/2 to P116/1 12.300 490 P51/3 End subs. Groblersdal to P62/2 Greater Groblersdal 9.100 491 P95/1, D198 Moutse 3 to Groblersdal and road P51/3 to end paved 9.700 492 P278/1 Sibasa to Nzhelele to Musekwaspoort Thulamela/Musina Vhembe 13.550 499 P19/1 Mokopane -Kloof Pass- Marken Mogalakwena Waterberg 7.000 20.000 TOTALS FOR UPGRADING (from gravel to sealed) TOTALS FOR MAINTENANCE (Preventative maintenance done by RAL) GRAND TOTAL BUDGET
7
Infrastructure Conditional Grant 2007/08
The cost of Roads construction in the province is higher than those of other provinces. The Province is conducting an investigation to establish why is the cost higher than other provinces. Overloading problems: heavy trucks damage the provincial roads as they prefer to use them other than the National Road Provincial Treasury did not transfer all money for conditional grants for 2005/06,R16 million is still outstanding and the department has committed the funds.
8
Application of 2006/07 budget
The Province is responsible for 6,514 kms of gravel and 21,996 kms of paved roads. Progress on Provincial roads infrastructure. Type of job Amount R’000 Units Comments Tarring R737m 165km and 8 bridges Total km’s Preventative maintanance R143m 105 km Gundo Lashu EPWP Project R35.7m 25,3KM 998 people employed Roads Designed at Sekhukhune District R7.6m 14 Projects Roads shifted from Mpumalanga as a results of Cross Boundary 2007/8 Roads Designs: R10,2m Plans All designs ready for implementation
9
EPWP NEW CONSTRUCTION PROJECTS – GUNDO LASHU
2007 / 2008 RAL No. ROAD No. DESCRIPTION CONSULTANT DETAILS Comments RAL budget Add budget Km Estimate 515 D4036/D4037/ D4013/D4016/ D4017 Mankweng cluster SEMENYA FURUMELE 2.70 5.00 New Construction 516 D3899 Tickyline to Sofaya INFRABURO 3.50 4.00 517 D3234 Shimange - Tar NHLENGANI 3.00 518 D4200 Mphanama - Apel BKS 519 D3676, D5003 Muraleni - Schoemansdal (P98/2) T2Tech 5.30 520 D192 Kgopong - Makekeng AFRICAN EPA 422 D2231 Nakampe - Sekhiming G & C 6.00 Compl portion to D9 423 D3911, D3912 Mulalene - Crossing - Mabins MOSOMO Compl 2nd/3rd phase to end 4.80 1.60 425 V & V 2.00 2.40 To reach Kgopong 0.80 428 Maebane - Makhita T2-TECH 4,5km / 3.55km repectively 4.28 1.00 429 Jokong - Shimange VELA VKE 7.20 Link D3180 to Shimange 430 2.30 2.76 To link Shimage 2.88 0.90 432 D3700 Shakadza - Tshirunzini 0.40 0.48 To link Shakadza to GL gravel rd 1.90 433 D3969 Muraluwe - Muswodi SMV Link Muswodi to D3697 434 2.20 4.40 Compl loop to D4016 378A D3211 KWEZI V3 4.25 6.50 380A D3769 Mafarana Gabaza 3.30 4.46 Compl Mafarana Gabaza 4.44 382A TSHEDZA To reach T at D4203 3.58 0.72 384B D3200 Mokwakwaila - Lebaka (D9 tar) km 5.90 Compl link 5.20 382B D3521 D192 - Mabuladihlare 3.60 4.50 Finish original- to Masebe Hosp 13.22 10.12
10
EPWP NEW CONSTRUCTION PROJECTS
km Estimate D3836 Sikhunyane - Mpephule 8.50 Upgrade grav to tar: R1m/km D4252 Mphanama - D4045 12.00 20.40 Intended to link (Est on R1.6m /km) D4200 Madibong - Mphanama 4.00 2.50 Complete terminated 323 3.00 D3009 London - P18/1 5.00 6.75 To close the link D3724 Tshifulanani - Tshivhumbe B 4.50 6.08 To complete balance D4263 Ga-Phaahla - Ga-Marishane Loop 24.00 28.80 Est R 1.2 /km D4070,77,86 Ga Mphahlele Cluster/Loop 26.00 31.20 0.00 GL Upgrading Totals 62.26 25.32
11
MAINTENANCE AND REPAIR PROJECTS(GL0)
2007 / 2008 Ga Marishane (1st standard) 7.00 0.30 2.2 1st STANDARD PROJECTS Prev. Contractor Length (Km) Cost/km GL/T269 D3211 Nakampe - Sekhiming MVKS Civils 5.50 0.20 Repair and fog-spray GL/T270 Sekhiming - Bembula Rola Consultants 9.00 GL/T271 D3180 Shimange - Jokong Mmabatho Construction 10.00 0.06 Drainage GL/T272 D3983 Bambeni & Sekunyane - Sekiming Lulama Women Investment GL/T274 D3853/D3854 Xikhumba - Guwela & Xikhumba - Xawela Tshidaho Construction 7.60 0.03 Drainage (sidefill protection) GL/T275 D3767/D3769 Mafarana - Gabaza & Burgersdorp - Myakayaka Rea Soma Correspondace 6.00 0.25 GL/T276 D4413/D3932 Crossing - Mulelane & London Worcester Henque 3645 cc 7.20 0.35 Repair, reseal and drainage (50%) 1.70 GL/T277 D3909 Madeira Loop & Tickyline - Sofaya Dawning Business Enterprise 6.60 GL/T282 D3901 Bismark Haulking Repair and slurry (20%) 0.00 5.55
12
2nd STANDARD PROJECTS GL/T313 D5002 Tshikororo - Dovhoni Liore Road Construction 2 0.25 Repair and slurry 0.50 0.38 GL/T314 D3724 Tshifulanani - Tshivhumbe Fishoff 4 0.30 1.20 GL/T315 D3695 Tshandama - Tshikwadza Bagma Roads 6.25 Repair and fog-spray 1.56 GL/T316 ES-EM-ES GL/T317 D3700 Tshirunzina - Shakadza KCA 6.5 0.06 Drainage GL/T318 D3969 Muraluwe - Muswodi Risimati Professional Civils and Construction 2.40 10.80 GL/T319 D3812 Lulekani/Homo South - Mapayeni/Homo South Maraka Pula 5.06 0.45 Repair, reseal and drainage GL/T320 D4264 Mapayeni - Mahlathini River North Trading 6.2 GL/T321 D192 P19/1 (Tar) - Kgopung A re Ageng 1.63 0.81 GL/T322 Kgopung - Makekeng Lekatana Mabore Business Enterprise GL/T323 D4200 Madibeng - Mphanama Constructability II cc 9.1 0.35 3.19 GL/T324 D4312/3/4 Ga Phahla - Marishane Silver Solutions 142 cc 7.1 0.40 Repair, reseal and drainage (4.5km) 1.80 GL/T337 D D4264 Sekhukhune Loop Lulama GL/T338 Ga Maseshlaneng Loop GL/T339 Mankweng cluster Nenis Construction 0.00 9.94 6.33
13
05/06 PROJECTS GL/T378b D4200 Madibong - Mphanama Lekatana Mabore Business Enterprise 5.30 0.15 Repair and fog-spray(50%, 50%) 0.40 GL/T379b D4214/ D4264 Mphanama-Petseng/GaMar/GaPha Maraka Pula 4.50 0.34 GL/T379c D3701 Access Road to Madimbo Matshakatini KCA 5.80 0.44 GL/T380b D3378 Ga-Ngwetsana - Ga-Setshaba Nenis Construction 4.80 0.36 GL/T380c D3377 D19 - Kgorosi - Ga-Setshaba A re Ageng 5.50 0.41 GL/T381 D3911 Crossing - Mulalene 5.20 0.39 GL/T382b D3521 D192 - Mabuladihlare Lulama Women Investment GL/T383b D5003 Muraleni - Madabani Bagma Roads 5.10 0.38 GL/T384a D3200 Mokwakwaila - Lebaka Risimati Professional Civils and Construction 5.00 0.00 3.43 GL Maintenance Totals 15.49 2.40 13.04 10.80 4.93 CONSTRUCTION AND MAINTENANCE: LABOUR INTENSIVE R 62.26 R 40.81 R 25.95 R 43.43 R 15.60 R 53.45 CONSTRUCTION AND MAINTENANCE: CONVENTIONAL R 0.00 R 4.13 R 17.75 R 19.40 R 88.06 TOTAL 40.81 30.08 61.18 35.00 141.51 TARGET (RAL, PIG Conditional Grant): R R R R R R
14
EPWP Fencing Project: - people to be employed , 2007/08
DISTRICT ADULTS YOUTH TOTALS TOTAL MALE FEMALE (M + F) CAPRICORN 76 88 79 87 155 175 330 MOPANI 82 132 84 92 166 224 390 VHEMBE 98 144 68 212 394 SEKHUKHUNE 103 90 95 198 180 378 WATERBERG 150 274 229 364 593 509 728 405 427 914 1,155 2,069
15
SUMMARY FOR 2007/8 Type of job Amount R’000 Units Comments
EPWP Project Gundo Lashu 31,243 31KM 1,000 to be employed EPWP Project Tsela Chueu 32,122 5,000km 2,000 to be employed Development of emerging contractors 20,0000 Training Programme Mainly forecast on youth and women.
16
PROGRESS ON EPWP PROJECTS, 2007/8
2007/8 plans for road construction, road maintenance and fencing projects are in place and being implemented. Process of appointing contractors is being finalised for new projects. Department intends to empower local people, especially rural women. Department is negotiating with the ESKOM Foundation and Waterberg District Municipality to join hands for the implementation of regravelling programme which will be more labour intensive.
17