1
Release Management – Ship It!
Phyllis Kaiden Release Infrastructure Manager The Cobalt Group, Inc. December 6, 2004
2
Outline What is Release Management? Why does it matter?
How does it work? Would you ship it? What did we learn? December 6, 2004
3
What is Release Management?
Release Management Definition Release Management Responsibilities What is Configuration Management? Product and Project Management December 6, 2004
4
Release Management Definition
The process by which a product is made ready for distribution to customers. Release management is the coordination of all the activities leading to and including product release to customers. The purpose of release management is to ensure products are ready when promised. Focus on software release management but basics apply to all product releases. December 6, 2004
5
It’s Like Baking Recipe – the set of activities in order
Ingredients – quality components Variations – Icing? Nuts? Mixing – executing the recipe steps Baking time – varies based on desired outcome Is it done? – knowing when it’s just right Final product – presentation, consumption December 6, 2004
6
Baking & Releasing Recipe – the set of activities in order (the plan)
Ingredients – quality components (content, schedule, resources) Variations – Icing? Nuts? (special considerations) Mixing – executing the recipe steps (do the plan) Baking time – varies based on desired outcome (priority of time to market, features, quality) Is it done? – knowing when it’s just right (assess readiness against measurable criteria) Final product – presentation, consumption (packaging and distribution) December 6, 2004
7
What is a release? Delivery of a “system” from a supplier to a customer. The “system” consists of a set of authorized and integrated components. The supplier is usually the development organization. The customer is the internal or external recipient of the system. December 6, 2004
8
Key Practices Release Planning: Manage and publish release schedule
Define deliverables included in a release Build and Version the integrated release package Manage dependencies across components Coordinate activities across company Control changes that would impact the release schedule Establish release criteria Assess release readiness December 6, 2004
9
Key Principle: Define “Done”
Deliverables Dependencies Avoid scope creep but allow change Release criteria Objective Quantifiable Cross-functional December 6, 2004
10
Components of a release
Golden Build (software): CD-ROM, files Documentation and Help Training materials Marketing collateral Internal documents Customer Notification Release Notes December 6, 2004
11
Types of Products Consumer: shrink-wrapped, commercial off-the-shelf (COTS), e.g. MS Word Open-source: download as needed, e.g. MySQL Hosted: Application Service Provider (ASP), e.g. Yahoo mail Corporate: Enterprise Resource Planning (ERP), e.g. Oracle Financials Corporate desktop: enterprise distribution of desktop applications, e.g. MS Office Operating system: core tools for IT, e.g. Sun Solaris December 6, 2004
12
Attributes by Product Type
Consumer Open-Source Hosted Corporate Corporate Desktop Operating System Installed by Self Self or IT Vendor IT Distribution Pull Push Cost $ $$ $$$ Training No Maybe Yes Support Multiple supported versions December 6, 2004
13
What is Configuration Management?
The process of building the product, tracking its components, and managing change. The purpose of configuration management is to guarantee reproducibility of the product and traceability of all changes. Release Management and Configuration Management are often the same group. December 6, 2004
14
Common Responsibilities of CM
Source Code and Version Control Reproducible – components of the release Traceable – what changed in this release Definitive Software Library: Baseline + delta baseline delta delta Version 1.0 1.1 1.2 branch baseline merge Version 2.0 December 6, 2004
15
Product and Project Management
“ABCs of Release Management” by Mario Moreira. CM Crossroads, Aug December 6, 2004
16
Why does Release Management matter?
Common Release Problems Benefits of Release Management Who Cares? December 6, 2004
17
A Story – Timeliness, Quality
Three companies decide independently to develop appointment scheduling software. They all have the knowledge and funding to create a good product. Company A releases on time with 100 known issues and is a success. Company B releases on time with 50 known issues and fails. Company C releases late with 10 known issues but fails because Company A had already captured the market. December 6, 2004
18
Common Release Problems
Take too long – impacts revenue Unpredictable – impacts dependent plans Poor quality – impacts support Not useful – impacts revenue Contents unplanned – impacts integrity Contents uncontrolled – impacts reliability Overlooked distribution/installation – impacts support Cowham, Robert. “Release Management – Making it Lean and Agile” CM Crossroads, Aug 16, December 6, 2004
19
The Challenge Time to Market vs Features vs Quality Time to Market
Only one top priority Balance – don’t ignore the other two Release criteria reflect priorities Product development methodology supports priorities: concurrent engineering, test-first development, prototyping Time to Market Features Quality December 6, 2004
20
Benefits of Release Management
More successful releases Consistent release process Predictability Integration Completeness Quality Communication December 6, 2004
21
Commitments to Customers, Stockholders, Employees Legal Considerations Return on Investment Worth installing? Installable Usable Supported Budget Timing Ready to sell? Demo updated Trained sales force Pricing Order Fulfillment Contracts ready Documentation ready Training materials Trained support staff Release Notes Known Problems FAQ, Knowledge Base Implementation impact Dependencies managed Meets requirements Minimize merging No “death march” Next project Well-defined scope Resources to support Predictable schedule Sufficient test time Meets requirements Dependable Installation Resources to support Predictable schedule Configuration Options Technical Documentation Stability, Scalability, Reliability Product Management Market position Product Roadmap Project Management Project delivery on-time Program Management Program meets expectations December 6, 2004
22
Software Development Life Cycle
How does it work? Types of Releases Software Development Life Cycle Release Process December 6, 2004
23
Types of Releases Major = significant new features, product launch, planned, pull, annual Minor = small new features, backwards compatible, planned, pull, semi-annual Patch = collection of bug fixes, planned, pull, quarterly Emergency = Urgent bug fix, harmful if not fixed, unplanned, push, as needed December 6, 2004
24
Attributes by Release Type
Features/Functions Bugs Cost Urgent Scheduled Pull Backwards Compatible Major Y (new) Minor Y (upgrade) Patch Fix December 6, 2004
25
Release Management in the Software Development Life Cycle
December 6, 2004
26
Activity Distribution
Release activities account for 10% of effort and 15% of schedule. McConnell, Steve. Software Project Survival Guide. Microsoft Press, 1998. December 6, 2004
27
December 6, 2004
28
Release Process Define Content Assign Version Plan Release Build
Package Deploy Test Control Change Assess Readiness Release Iterate December 6, 2004
29
1. Define Content Golden Build (software) Documentation
Training materials Marketing collateral Internal documents Customer Notification Release Notes December 6, 2004
30
1. Define Content: Must and Nice
Disp ID Severity Pri Description Nice 41928 enhancement P3 Performance - Publish: loadSiteLite() to replace loadSite() 59439 trivial P4 Misalignment of Editable site and Proof site sections on Manage site screen once the actor checks Lock-site checkbox. 59929 minor P5 Error message:Get A Quote form:The listed items in error message may need some order; by logical or by alphabetic 57954 major P2 Only Ford Make is displayed in 'Quick Quote Form' : GM Design 59368 Masthead descenders are being chopped off in Klamath_B_Dst design 57019 Can't tell mouse over selection from current page selection in nav 59726 Design Celandine: Titles (Header) for static pages are not bold as those for dynamic pages 60108 Misalignment of footer in Hours and directions page-Celandine designs Must 64793 create new Saab luxury design and homepage 64796 create new Land Rover luxury design and homepage December 6, 2004
31
2. Assign version Version is a unique identifier for the product state as of a certain point in time. Not all versions are released. Versions are sequential. Versioning Schemes relate to release types, product management, and configuration management: Major.Minor.Patch.Fix, e.g. 1.0, 1.1, 1.1.2, Major.Feature.Patch, e.g. 1.0, 1.1, 1.1.2 Major.Feature.Patch.Build, e.g December 6, 2004
32
3. Plan Release Dependencies Customer commitments Revenue recognition
Resource availability: people, environments Introducing too much change at once Stabilizing between releases Organizational capability December 6, 2004
33
3. Plan Release: Milestones
Scope Freeze 9/7 COMPLETE Functional Freeze 9/17 Functional Test Complete 9/30 Code Freeze 10/1 Regression Test Complete 10/13 Golden Build 10/8 Performance Test Complete Mock Deployment 10/12 FAILED 10/14 Deployment Plan Review 10/15 Go/No-Go COMPLETE – GO Executive Approval COMPLETE-APPROVED RELEASE December 6, 2004
34
4. Build Build (What) Visibility (Who) Frequency (When) Purpose (Why)
Private System Build Individual Developer One or more times per change task Provide feedback to the developer of the changes just implemented in the private workspace. Integration Build Whole Development Team After each change task and/or one or more times per day (e.g. Nightly) Integrates the latest changes in the repository and runs automated tests against the release providing feedback to the development team. Release Build Independent Test (QA or V&V) Team and Customers At the end of each iteration/release Packages release for distribution to the development team’s customer. Appleton, Brad. “Agile Build Promotion: Navigating the Ocean of Promotion Notions”, CM Crossroads, September December 6, 2004
35
5. Package Create the release package containing all release deliverables File: tar, .zip, .exe, .ear Medium: CD-ROM, tape, file server Bill of Materials lists what’s in the package Final release package is “golden build” December 6, 2004
36
6. Deploy Deployment Plan Install Team Deployment Plan Review
Mock Deploy Mock Rollback Contact List December 6, 2004
37
6. Deploy: Sample Steps December 6, 2004 1
Nitra "Version 2.3.3" Deployment 2 WLS 8.1 on SMTP servers Thomas 4 Verify router updates in env file 5 Verify UPSShip updates in Env File 9 Validate receipt of Nitra, LMCC Tar Balls and Mapping Loader script Claus 10 Add Scion Altercast fonts (Bug 61506) 11 Prep-Outage Tasks 1 hr Steven 12 Hot Backup Nitra DB 55 min 9:00 PM 9:55 PM 13 Check 3rd Party Services (Chrome, AIC, Vicinity) 10 mins 9:30 PM 9:45 PM Jeff M 14 Team Check-In 5 mins 9:50 PM Team 15 Check CDC design flag to true 16 Outage 17 NO DEALER ACCESS 9:50 AM 9:55 AM 18 NO CONSUMER ACCESS 10:00 PM 22 Shutdown Servers 40 mins 23 Disable Nitra Monitoring 3 mins 10:05 PM 10:08 PM 24 Disable Incoming Leads (no consumer access) 2 mins 10:10 PM 25 Allow Existing leads to pass (Big IP) 10:12 PM 26 Bring down WLS (Nitra and LM) 30 mins 10:42 PM 27 Snapshot net-app (back up file system) 10:44 PM 28 Deployment time noted (for rollback purposes) 1 mins 10:45 PM 29 Database Modifications 31 LMCC DB Script 10 min 10:55 PM 11:05 PM 32 Run script for Mapping loader 11:15 PM 33 Code Deployment (LM and Nitra Clusters) December 6, 2004
38
7. Test Plan ahead for test environments Execute Test Plan
Functional test: does it function as required? Regression test: did old bugs reappear? Performance test: does it perform within acceptable limits? Reliability test: does it function consistently over time? Stress test: does it function consistently under volume? December 6, 2004
39
8. Control Change Baseline scope, requirements, design
Accommodate controlled change Avoid scope creep Allow change, it’s reality Change requests Change request decision (approve, reject, defer) Change Control Board (CCB) Cross-functional representation Impact analysis Business drivers December 6, 2004
40
9. Assess Readiness Release Criteria define “done”
Defined Deliverables Features: Must Have vs Nice to Have Quality: test results, metrics Schedule: time-to-market criteria Objective, quantifiable criteria preferred Organizational Readiness Support, Training, Marketing, Sales Acceptable Risk December 6, 2004
41
9. Assess Readiness: Release Criteria
Quality Testing Complete (functional, regression, performance, reliability, stress) Successful Mock Deployment Successful Mock Rollback "Golden" Build in Hand Features All “must have” features complete Documentation and Help updated Release Notes Accepted by Customer Support Schedule Schedule Clearance (no conflict) Outage Notification Processed Release Package Delivered to IT Acceptable Deployment Night Coverage Acceptable Post-Deployment Coverage Go/No Go Meeting yields Go decision. Punch List completed. December 6, 2004
42
Assess Readiness: Metrics
Common metrics: fix rate, find rate, defect density, rate of change Example: find rate vs fix rate Stability reached at week 35 of testing, when defects fixed exceeds defects opened. December 6, 2004
43
9. Assess Readiness: Go/No-Go
Release Readiness Assessment Are all release criteria equal? Can any criteria be waived? Go/No-Go Formal sign-off by stakeholders Meeting, vote Recommendation by Release Manager Go with Punch List Executive Approval December 6, 2004
44
10. Release Formal release by Configuration Mgmt
Deploy to Production or Distribute to Customer December 6, 2004
45
10. Release Programs Alpha = test by in-house department
Beta = test by small group of customers Pilot Early Adopters General Availability (GA) = all customers December 6, 2004
46
Would you ship it? Situations Is it ready? Would you ship it?
December 6, 2004
47
Situation #1: Class registration
Criteria Zero priority-one defects Ready in time for class registration on April 1 Data One priority-one defect affecting 100 music majors out of 3,000 students. Fix estimate is 3 days. Today is March 15. Ship it? More data? December 6, 2004
48
Situation #1: Other Factors
Cost: Penalty for late delivery? Confidence: accurate estimate? Complexity? Quality: Danger of breaking something else? How much testing is needed? Schedule: Holidays? Vacation? Customer availability? Hard deadline? Relationship: Unhappy customer? Reference site? Workaround: Manual? Send staff on site? December 6, 2004
49
Situation #2: Java web search tool
Criteria Acceptable performance: + 10% current Backwards compatibility Data Performance on page load is 5% better Performance on search is 20% worse Fix will require customer to download new Java Virtual Machine (JVM) Ship it? More data? December 6, 2004
50
Situation #2: Other Factors
Quantify: How much loss? < second? Accuracy: performance test environment? Alternatives: Optional download? Automatic download? Support: Ease of download? Increased support load? Competition: Market leader? Slipping? Usability: lose customers if slow? December 6, 2004
51
What did we learn? Release Management Definition Key Practices
Key Principle Release Process Features, Quality, Time to Market December 6, 2004
52
Release Management Definition
The process by which a product is made ready for distribution to customers. Release management is the coordination of all the activities leading to and including product release to customers. The purpose of release management is to ensure products are ready when promised. December 6, 2004
53
Key Practices Release Planning: Manage and publish release schedule
Define deliverables included in a release Manage dependencies across components and activities in the release Coordinate activities across company Control changes that would impact the release schedule Establish release criteria Assess release readiness December 6, 2004
54
Key Principle: Define “Done”
Deliverables Dependencies Avoid scope creep but allow change Release criteria Objective Quantifiable Cross-functional December 6, 2004
55
Release Process Define Content Assign Version Plan Release Build
Package Deploy Test Control Change Assess Readiness Release Iterate December 6, 2004
56
The Challenge Time to Market vs Features vs Quality Time to Market
Only one top priority Balance – don’t ignore the other two Release criteria reflect priorities Product development methodology supports priorities: concurrent engineering, test-first development, prototyping Time to Market Features Quality December 6, 2004
57
Q & A THANK YOU! December 6, 2004