1 City of Roundup, Montana
Water System Informational Meeting February 2, 2016

2 Distribution System 2010: 2016 (After all Phase 3)
Estimated 45,680 feet of cast iron mains (8.65 miles) 2016 (After all Phase 3) Estimated 23,960 feet of cast iron mains remaining (4.54 miles) 47.5% Completed

3 2010 Cast Iron Mains

4 2016 Cast Iron Mains

5 Leveraging Project Funds
Total Funds for Phases 1-3: TSEP = $1.5 million Coal Board = $1.0 million CDBG = $450,000 (Phase 3) DNRC/RRGL = $200,000 SRF Loan = $1.4 million City Reserves = $520,000 Total = $5,070,000

6 Current Distribution System Issues
Excessive Leakage High Iron and Manganese Not Enough Valves Rust Chunks Inadequate Fire Flow

7 Fire Flows-After Phase 3

8 Leaks Since 2010

9 Estimated Costs for Improvements

10 Phase 4 Rehabilitation

11 Phase Costs

12 Phase 4 Funding Plan TSEP Grant $ 500,000 DNRC Grant $ 125,000
CDBG Grant $ 450,000 Coal Board $ 200,000 SRF/RD Loan $ Total: $1,275,000

13 What if we don’t get all grants?
Option 1: Take a grant cycle off. Option 2: Reduce the scope of improvements Option 3: Supplement with a new SRF loan Option 4: Supplement with a new RD grant/loan Option 5: MMIA funds? Option 6: Other?

14 Questions and/or Comments?