1 Pittsburgh (PA), USA, 2017 September 18th – 21st
Session C6 – September 20th Red River Delta Waterway Modernization (Vietnam) From Conception to Supervision : Feedback on 5 years of Environmental, Social and Safety Supervision Franck PRESSIAT (CNR) - Tuan ANH PHAM (VIPO) - Thi THANH (PMUW) - Noreen BEG (WB) Pittsburgh (PA), USA, 2017 September 18th – 21st

2 Red River Delta Waterway Modernization
Corridor 1 : 160 km 14 constructions sites 24 Contractors 2 Industrial ports Corridor 1 Ninh Phuc Industrial port Hanoi 6 packages Flow diveder Viet Tri Industrial port Corridor 3 Mom Ro – Canal Deviation Do Bui Curve modification Lach Giang estuary Breakwater and channel access Corridor 3 : 160 km 3 construction sites 18 contractors

3 Red River Delta Waterway improvement
Ninh Phuc Port (after) (before) Hanoi’s “6 packages” Flow divider Lach Giang Estuary breakwaters and channel access Mom Ro Deviation

4 Construction contractors and Subcontractors
Actors and tasks Funder and Project Adviser Borrower and Project Owner Consultant, Designer, Project Manager and Supervision Subcontractor Consultant, Design and Construction sites Supervision Construction contractors and Subcontractors Construction Operations

5 Consultant Missions EIA (Environment Impact Assessment) RAP
(Resettlement Action Plan) EMP (Environment Management Plan) Conception phase DMDP (Dredged Disposal Management plan) Supporting Project Owner during Administrative Inspections and exchanges with World Bank Construction Phase Contractors’ SEMP reviewing Environmental Monitoring Safety Supervison HIV Prevention program (workers and local people) Social supervision on site Environmental Supervision Reporting to Project owner Control the Contractors Environmental monitoring

6 A challenge : how to combine construction, Environment and Safety
pied de page 17/11/

7 Environment, Safety and social aspects
The consultant controls and monitors the works impacts on air, water, soils and sediments quality + biodiversity Organize training sessions to improve Contractors and workers skills Check that all the Environmental actions are engage Exchanges with Project Owner staff and WB to propose / illustrate alternatives and optional solutions Specific information, training and control are undertaken concerning safety equipment and procedures for workers who have few experience of maritime works. SOCIAL / Education of Workers and local population CNR has set up with a Vietnamese NGO a program of education related to the risk of HIV and other sexual diseases. 14 meetings concerning 750 workers and local people were organized on the different packages along the Red River Delta. pied de page 17/11/

8 Another challenge : Reach the International standards… and consider the local reality !!!
World Bank Expected level National Legal level Initial level Progressive steps… … or barrier ??? pied de page 17/11/

9 Example : Waste management
Real possible progress Initial level Wood Rubble Metal Food Plastic Glass Zinc Copper Paper Officially Expected level pied de page 17/11/

10 Possible actions to improve the levels
Explanations and Training Site controls and recontrols Identify the progress, report and congratulate Blaming and penalties if not respecting rules pied de page 17/11/

11 Environment Construction Waste Air monitoring Water monitoring
Biodiversity pied de page 17/11/

12 Safety pied de page 17/11/

13 Local production of young Casuarinas
Social Historical and religious Heritage’s Protection Maximum preservation of agriculture lands Casuarina plantations for local resources Internship Agronomist student visiting local tree garden Local production of young Casuarinas pied de page 17/11/

14 HIV prevention HIV Prevention Plan for Local people and workers
Theory and practice with local NGO HIV Prevention Plan for Local people and workers > 750 persons – 14 sessions pied de page 17/11/

15 Finally : a collective success
pied de page 17/11/

16 Thank you for your attention Cảm ơn bạn đã quan tâm của bạn
Muchas gracias por su atención Merci pour votre attention