Presentation is loading. Please wait.

Presentation is loading. Please wait.

WIC deployment and commissioning in HIE-ISOLDE

Similar presentations


Presentation on theme: "WIC deployment and commissioning in HIE-ISOLDE"— Presentation transcript:

1 WIC deployment and commissioning in HIE-ISOLDE
Richard Mompo for the WIC team

2 Outline Quick overview of ISOLDE facility @ Cern
Upgrade of ISOLDE facility: HIE-ISOLDE Tailored WIC solution for HIE-ISOLDE HWC status Conclusions

3 Bird view of Meyrin site

4 ISOLDE Buildings

5 Courtesy of Y. Kadi

6 Courtesy of Y. Kadi

7 Superconducting linac upgrade
3 stages installation 3 MeV/u Existing part (REX-ISOLDE) 5.5 MeV/u Oct 2015 8 MeV/u June 2017 10 MeV/u >2018

8 Cryo-modules with superconducting cavities
S.C. solenoid: Final decision: QPS + PIC + EE systems not needed. S.C. cavities Modular installation

9 Top view of bld. 170 Courtesy of S. Maridor
4 racks reserved (in pink) for 2 WIC systems on the platform XT01 XT02 XT03 REX-ISOLDE XT00 Tunnel made of concrete blocks REX-ISOLDE and XT00 are refurbished b/w each stage to leave space for the S.C. cavities XT01 and XT02 (experimental lines) come at Stage 1 XT03 at Stage 2

10 Inside view of the tunnel
Courtesy of S. Maridor New XT00 line Existing: REX-ISOLDE Stage 1: Two cryo-modules

11 WIC (Warm magnet Interlock Controller) layout
Standardized interlock system for normal conducting magnets based on PLC: Collects inputs from thermo-switches, flow switches and internal PC faults Then gives the Power Permit to the power converter No Beam Dump at HIE-ISOLDE

12 The program running in the WIC is extremely simple
WIC principle The Warm magnet Interlock Controller is a PLC based system, using deported I/O crates (connected via Profibus). The Siemens “F” (F stands for Fail safe) Series PLC is used, offering a self checking safety environment and programming through ‘Safety Matrix’. We use generic SW and (to some extent) HW for all our installation, to allow for efficient and resource optimized installation, commissioning and operation. The program running in the WIC is extremely simple IF (Magnet Overheats) OR (Flow Switch opens) THEN [According to the Configuration file] Switch-off the relevant PC(s) IF (Magnet Overheats) OR (Flow Switch opens) OR (PC Status failure)THEN [According to the Configuration file] send Beam Dump signal

13 WIC design for HIE-ISOLDE
HIE-ISOLDE will be built in 3 stages The hardware (PLCs + Patch panels) is designed to cover the 3 phases 1st WIC to protect REX-ISOLDE + XT00 line 2nd WIC to protect XT01, XT02, XT03 experimental lines All control cables (Magnets + PCs) are already pulled for the 3 stages Modification between phases managed by software only: Will involved a full re-commissioning at each stage. Number of elements to connect: Existing (Rex-Isolde): Existing power converters 1 dipole 1 20 quadrupoles 1 steerer (H/V) 2 New magnets New Power converters 7 dipoles (S500) 32 quadrupoles 34 (Cobalt) 23 steerers (H/V) 53 (Cancun)

14 How it looks like in real…
XT03 line XT02 line Tunnel XT01 line completed Platform with WIC n°1+ PCs WIC n°2 2 quads + 1 steerer

15 Modification of the software part
First version of the generic code (for safety PLCs) was written for the LHC Experiences in the SPS and the Booster showed the need for more flexibility Decouple the Beam Dump and Fast Abort signal generation Reduce our dependence on BE/CO Before: WIC projects data not entered directly by us in a private DB  Not linked to Layout DB  Before: SQL scripts depending on CO support and difficult to maintain for the generation of config. files  ECR circulated to explain the reasons for the changes & impact on each machine & mitigations plans: LHC, SPS, Linac 4, LEIR, Linac 3

16 The software part (2/2) HIE-ISOLDE project: Guinea pig to test: Major changes in the generic code of the PLC New process of generation of config. files for the PLC and WinCC software WinCC config file PLC config file Controls Configuration Database Magnet E1.1 PC Status 1 E3.1 PC Mask Beam Dump Card EB12-14 Card EB16-18 Card 20 EB62-64 Magnet + PC Status + Pow Failure Hardware configuration WIC Editor -> APEX interface Fast Abort PLC generic code: - 2 independent matrices - Increase of size of the matrices 11x -> 12x 8 DO modules WinCC generic code New «Lock» feature New color code (orange = passivation) Adapt to the modifications in the PLC code Java scripts Data recorded in Controls DB First use of java scripts to generate config files First use of WIC editor 5 months of thorough & iterative tests with EN/ICE Transition very well prepared well ahead of time by Ivan (with BE/CO) to define the DB structure, the WIC Editor and writing the Java scripts

17 How it looks like from the WinCC supervision
Remote supervision/testing of the installation Archiving of faults Main faceplate PC widget Magnet widget

18 Documentation Work Package Description (WPD) approved on EDMS
Second version in preparation Commissioning procedure was co-written between the main stakeholders MPE, EPC and MSC A SharePoint website was put in place for the follow-up of the commissioning steps for each circuit.

19 Future project? Studies on-going to build a storage ring (TSR) New building for TSR machine : 670 33.27 m 26 m Building 508 B 170

20 Conclusions I was involved at a very early stage in the project
Numerous advantages: Apply LHC standards, optimization of (cabling) costs, rack reservation, cable pulling secured, integration of our interlock boxes etc... Drawback: Many iterations of the layout design. All deliverables installed in February 2015… on time for the HWC Very high motivation in the teams involved in the project (# renovation project) Coordination and installation went smoothly Several issues found on the ‘old’ Rex-Isolde magnets: Responsibility of MSC. Phase 1 of the project will be finished (for us) by end of June 2015 Physics foreseen for October 2015 

21 Thank you for your attention
Special thanks to: Markus Zerlauth Pierre Dahlen Ivan Romera Ramirez Yan Bastian Geza Csendes Chantal Chervet & Jocelyne Dechelette (cabling) Jeronimo Ortola Vidal: EN-ICE Jonas Arroyo Garcia: EN-ICE Nikolay Tsvetkov: BE-CO Erwin Siesling: BE-OP (Integration) Michele Martino: TE-EPC Jeremie Bauche: TE-MSC Antony Newborough: TE-MSC Georgi Minchev Georgiev EN-EL Walter Venturini Delsolaro: BE-RF (RF + HWC) Thank you for your attention

22 Reserved slides

23 Interlock boxes Interlock boxes are placed on or close to each magnet to collect all input signals. For maintenance purpose, a remote test feature is implemented (by means of a relay) in order to simulate the opening of any input signal. This operation can be done remotely and allow us to check periodically the installation during shutdowns.

24 Type of Interlock boxes used at HIE-ISOLDE
1-channel - Interlock Box: Dipoles, Quads 1x Thermo-switch + 1x Remote test 2-channels - Interlock Box: Steerers (H/V) 2x Thermo-switches + 2x Remote test 4-channels - Interlock Box: Triplets, Doublet 3x Thermo-switches + 1x Flow switch + 4x Remote test New design for Hie-Isolde

25 WIC elements installed in LHC tunnel
Thermoswitch - ELMWOOD Type 3106 – T117 Magnet Interlock Box where a relay is installed to simulate the opening of a Thermo-switch Note: Only the Magnet Interlock Boxes are installed in the LHC tunnel (I/O crates are installed in US/UJ/TZ areas)

26 Courtesy of Y. Kadi

27 Courtesy of Y. Kadi

28 Courtesy of Y. Kadi


Download ppt "WIC deployment and commissioning in HIE-ISOLDE"

Similar presentations


Ads by Google