Presentation is loading. Please wait.

Presentation is loading. Please wait.

Cost Savings on Smaller P3 Projects

Similar presentations


Presentation on theme: "Cost Savings on Smaller P3 Projects"— Presentation transcript:

1 Cost Savings on Smaller P3 Projects
How to Structure a P3 to Create Genuine Value for Projects Starting at $20 Million and Up

2 Nationally recognized not-for-profit
Maximizes public benefit when using P3 Access to Tax-Exempt financing Issues bonds Owns the project on behalf of Public Entity until debt is retired Transfers project at no additional cost to public agency

3 Commodore Duchess Apartments
University of Washington, WA Bonds were issued in 1995 $7,385,000 in tax-exempt bonds Renovation of 1927 Hotel which was converted to 139 units of student housing

4 UAF Woods Center Food Services
University of Alaska Fairbanks, AK New Student dining facility and activities office $23,649,000 in tax-exempt bonds Mixed New-Construction (34,000 sq. ft.) and Rehabilitation (6,000 sq. ft.)

5 Center for Urban Waters
Tacoma, WA State-of-the-art marine research and testing facility LEED Platinum Finalist for ULI Award for Excellence $37,840,000 tax-exempt bonds

6 Riverside County Courthouse
Indio, CA 90,363 square foot, three-story office building and law library LEED Platinum $44.38 million tax exempt Bonds Early completion and $4.2 million in cost savings

7 Other Examples Patricia Bracelin Steele Building $62,540,000
Radford Court Apartments $53,125,000 Pacific Place Parking Garage $47,000,000 King Street Center $78,275,000 Lake Tapps Parkway $17,000,000 4225 Roosevelt $29,858,000 The Gateway at Alhambra $43,710,000 Issaquah Highlands $63,500,000 Redmond City Hall $39,230,000 Bothell City Hall $49,625,000 Edna Lucile Goodrich Building $56,805,000 Nordheim Court $34,085,000

8 What’s different about smaller projects?
Lower project cost Smaller projects cannot afford higher cost of conventional debt and equity Smaller projects have little room to accommodate the cost of the availability payment approach to O&M

9 Availability Approach
Comparing Models New American Approach Availability Approach Ownership Through an “On-Behalf-Of” not-for-profit Public ownership with private control Financing 100% tax exempt debt Equity and taxable debt Development Private build-to-suit; Integrated Delivery with incentives to perform Operations Private, cost-based & subject to performance Private availability-based Maintenance Privately contracted dedicated repair and replacement reserve Privately delivered and funded through long-term public obligations Occupancy Cost Lowest in the industry Generally higher to cover private guarantees Property Tax Usually exempt Typically subject to property tax

10 Four Principles How to Maximize Public Benefits in P3 Delivery for Social Infrastructure
Use Tax-Exempt Debt Use Private Development Align Risks and Rewards Maintain Public Control

11 Four Principles: The Use of Tax-Exempt Debt
Tax-Exempt Financing Taxable Financing 100% Tax Exempt Debt Combination of Taxable Debt and Equity Required Debt Coverage Ratio is 1.0 Required Debt Coverage Ratio is 1.1 or higher A Single Loan Two Loans – A Construction Loan and then a Permanent Loan More accepting of Subject to Appropriation and Abatement language Difficulty with Subject to Appropriation and Abatement language

12 Four Principles: Use of Private Development
Developers Work Efficiently – Time is Money! They Know How to Control Costs In-House Experience Rely Less on Consultants

13 Four Principles: Alignment of Risks and Rewards
Pay partners fairly for what they bring to the project Do not pay for what they do not bring to the project Private partners must be allowed to freely apply their knowledge, skill, management and experience Provide incentives to create efficiency Keep private property management terms short to keep performance and pricing competitive.

14 Four Principles: Maintain Public Control
The Public Agency pays for the project therefore it should have rights equivalent to ownership The Public Agency should have the right to take control of the SPE at any time should it desire to do so After the Public Agency finishes paying for the project they should be able to assume ownership without cost or delay

15 The New American Approach in Eight Steps

16 Public Facilities Group
The New American Approach: Step 1: Selecting the Not-for-Profit Partner Public Agency Public Facilities Group The Public Agency selects a not-for-profit to assist in a Public-Private Partnership RFQ/RFP Role of the Not-for-Profit Tasked with creating and staffing the Not-for-Profit Single Purpose Entity (SPE) That SPE will incur the projects debt through a tax-exempt bond sale That SPE will manage and own the facility on behalf of the government until debt is retired When Debt is retired the SPE transfers ownership to the Public Agency at no cost and without encumbrance

17 Qualities of the Not-for-Profit
Experience In: Structuring and Overseeing Complex Real Estate Development Tax-Exempt Bond Finance and Bond Compliance Asset Management The Not-for-Profit earns a small fee paid from bond proceeds for its work. It is not paid a consulting fee by the public agency.

18 Public Facilities Group
The New American Approach: Step 2: Selecting the Private Development Team The Public Agency, with assistance from the Not-for-Profit, selects the development team through a RFQ / RFP process. Public Agency Public Facilities Group RFQ/RFP Developer Architect Development Team General Contractor

19 Best Practices in Public Procurement (After the Decision to Use an Alternative Development Process)
Issue an RFQ Identifies team members Asks for their experience on similar projects Asks for references Does not ask for design concepts or costs

20 The RFP: Six Important Questions
Issue an RFP for the Development Team Who are the Team Members What are their time commitments & experience on similar projects? How does the team expect to create public value? Will they accept the terms of the pre-development agreement and the development agreement? Ask for them to bid all fees and soft costs based on an assumed per square foot hard cost. Ask them to confidentially provide financial information and litigation history.

21 The RFP: Do Not ask for Architectural Renderings!

22 The RFP: Digging Further
Interview the Teams Also conduct separate interviews for each team member Visit their projects Examine their financials and litigation record in the team’s offices Review references from other Public Agencies

23 The New American Approach: Step 3: Design and Predevelopment
The Developer, Architect, and General contractor come together with the Public Agency and the Not-for-Profit to advance the design from concept drawings, through schematics and design development, arriving at a Guaranteed Maximum Price (GMP) The Developer secures approval of all Entitlements The Public Agency and the Not-for-Profit negotiate a long term lease Public Agency Public Facilities Group Developer Architect Development Team General Contractor

24 The New American Approach: Step 4: Financing Contracts and Bond Sale
The Not-for-Profit creates a Special Purpose Entity (SPE) to own and finance the asset The SPE, the Public Agency, the Development Team and the Finance Team produce all Financing Documents A lease agreement is prepared and executed Tax-Exempt bonds are sold to finance the project Public Agency Public Facilities Group Special Purpose Entity Developer Architect Development Team General Contractor

25 63-20 Bonds Revenue Ruling allows a not-for-profit corporation to issue debt to finance a facility for tax exempt purposes, provided: A local governmental entity endorses the financing The facility will be occupied by a governmental or tax exempt entity The facility reverts to the ownership of the endorsing local governmental entity at the retirement of the debt

26 The New American Approach: Requirements for Starting Construction
Design and Pre-Construction Construction Public Entity Public Facilities Group Public Entity Public Facilities Group Lease Special Purpose Entity Special Purpose Entity Developer Architect Developer Architect Development Team Development Team General Contractor General Contractor GMP Lease Entitlements Sub Contractors

27 The New American Approach: Step 5: Construction
After the Bonds are sold, the Special Purpose Entity (SPE) gives the Development Team a notice to proceed The Development Team begins construction The Not-for-Profit staffs the SPE through a Development Services Contract During construction, the SPE and the Public Agency collaborate to issue an RFP for property management services Public Agency Public Facilities Group Lease Special Purpose Entity Developer Architect Development Team General Contractor Sub Contractors

28 The New American Approach: Step 6: Construction Completion
Public Agency Lease payments begin at Certificate of Occupancy After the completion of all punch list items the SPE issues a Certificate of Final Acceptance. The SPE enters into the Property Management Agreement with the selected property manager Public Agency Public Facilities Group Lease Special Purpose Entity Developer Architect Development Team General Contractor Sub Contractors

29 The New American Approach: Step 7: Operations and Maintenance
With the Certificate of Occupancy and the Certificate of Final Acceptance the Public Agency begins its tenancy The Not-for-Profit continues to staff the SPE The Property Manager oversees Operations and Maintenance duties working for the SPE and in-service to the Public Agency Public Agency Public Facilities Group Lease Special Purpose Entity Private Property Management

30 The New American Approach: Operations and Maintenance Renewal
Every 3 to 5 years the management agreement will be re-bid to guarantee a competitive operation and maintenance package for the building Public Agency Public Facilities Group Lease Special Purpose Entity Private Property Management

31 The New American Approach: Unique Public Safeguards
The Public Agency can take control of the SPE at any time by replacing it as the member and then replacing the board of directors Public Agency Lease Special Purpose Entity Private Property Management

32 The New American Approach: Step 8: Transfer of Ownership
After the bonds have been retired ownership of the project transfers to the Public Agency at no cost. Public Agency Ownership Facility

33 Questions and Discussion

34 Upcoming Webinars Register at our website publicfacilitiesgroup.org
P3 Negotiation Prep 1: Comparing Public Delivery and Private Delivery Processes October 12th, 2017; 9am-11am pacific P3 Negotiation Prep 2: Comparing Public Financing and Private Financing Options October 26th, 2017; 9am-11am pacific P3 Model Comparison November 9th, 2017; 9am-11am pacific New American Approach; Using Tax-Exempt Debt in a P3 November 30th, 2017; 9am-11am pacific


Download ppt "Cost Savings on Smaller P3 Projects"

Similar presentations


Ads by Google