1 Notes on Ramp-Up and Production

2 LEP-II : Main Parameters (Nb/Cu)

3 288 Cavities Total…ILC 16,000, Active length = 500 m

4 4 cavity module, 11.3 m long

5 72 Modules Total..ILC = 2000 36 klystrons

6 Cavity Development 1989: Nb cavity : Four prototypes at CERN
1992: 20 cavities, 3 vendors 1992: Change in technology from Nb to Nb-Cu, 3 Vendors selected Initial production rate < 20 /year Final production rate 50/year

7 Initial Cavity/Module Production
Modules delivered 12 accepted / 2years 50/year < 20/year

8 50/year

9 6 years total 29/year 24/year 12/ year 4/year

10 Initial and Final LEP Cavity Performance

11 CEBAF, JLAB, 338 cavities, 40 modules (8-cavity)
1500 MHz, 5-cell cavities 8-cavity Cryomodules

12 Timeline (Initial Development to Installation – 6 years)
1987: 4 vendor competition, B&W, TRW, Dornier, Interatom (now ACCEL) 2 cavities each, tested at Cornell Facilities installation at Jlab started 1989: Order placed to Interatom (now ACCEL) 1990: Initial production rate 3 cav/month Oct 1990 : Full production rate 12 cav/month One vendor Early 93: Cavity order completed (338 cavities) May 93 : 28 modules installed in one linac

13

14 R&D With Industry Phase Before LHC Approval
Initial R&D with industry, 1991 – 1994 7 x 1.3m magnets/modules ordered from 5 firms 7 x 10 m long magnets/modules ordered from 4 firms LHC approved in Dec 1994

15

16

17 After LHC Approval (1995) Initial Stages
The LHC requires 1200 cryomodules (15 m long) as compared to the ILC’s 2000 modules (12 m long). There were three stages before the sizable “pre-construction” series of 90 modules in 2001. Stage 1 start in October 1995: After design and modeling work at CERN, 3 prototype coils were built in industry and modules assembled and tested at CERN. Stage 2 (summer 1998): Vendors assembled 9 modules (3 per vendor) at CERN using magnet assembly facilities installed at CERN. Stage 3: Beginning of Pre-series of 90 modules (end of 2002) Vendors then manufactured a total of about 20 modules (7 per vendor). About 6 of these were fully tested (2 per vendor). Pre-series production released In all, a total of 32 modules were prepared by the CERN/industrial collaboration before releasing the pre-series production of 90.

18 6 years = pre-construction and construction
1200 cryomodules, 1 B$ scale, smaller but comparable to ILC Main Linac Scale 6 years = pre-construction and construction 2 years

19 LHC R&D and Production Phases
LHC Project Approval 1 m 10m 12 m