1
TRACK: C (ENGINEERING) WORKSHOP: 5 Title: Managing The Gauntlet Speaker: Mark Day, Blue Grass Airport Date: February 19, 2015
2
aka Lexington’s Taxiway Safety Enhancement Program
Managing The Gauntlet aka Lexington’s Taxiway Safety Enhancement Program
3
BLUE GRASS AIRPORT (LEX)
RW ’x150’ RW ’x75’ Delta, American/USAir, United and Allegiant Airlines 600,000 Enplanements 1076 Acres Surrounded by historic Thoroughbred horse farms and Keeneland Race Track
4
EXISTING CONDITIONS Single commercial parallel Taxiway A
5
EXISTING CONDITIONS Single commercial parallel Taxiway A
Single connector taxiway to commercial and general aviation ramp
6
EXISTING CONDITIONS Single commercial parallel Taxiway A
Single connector taxiway to commercial and general aviation ramp Blind area to Air Traffic Control
7
EXISTING CONDITIONS RESULTS IN… Single commercial parallel Taxiway A
Single connector taxiway to commercial and general aviation ramp Blind area to Air Traffic Control RESULTS IN… Blind pushbacks into movement area
8
EXISTING CONDITIONS RESULTS IN… Single commercial parallel Taxiway A
Single connector taxiway to commercial and general aviation ramp Blind area to Air Traffic Control RESULTS IN… Blind pushbacks into movement area Single intersection congestion during peak traffic
9
EXISTING CONDITIONS RESULTS IN… Single commercial parallel Taxiway A
Single connector taxiway to commercial and general aviation ramp Blind area to Air Traffic Control RESULTS IN… Blind pushbacks into movement area Single intersection congestion during peak traffic Direct Path from the ramp to the runway
10
SOLUTION Eliminate Connectors
11
SOLUTION Eliminate Connectors
Realign portion of taxiway at 400’ separation
12
SOLUTION Eliminate Connectors
Realign portion of taxiway at 400’ separation Add connector taxiway from Taxiway A to ramp outside of blind area
13
SOLUTION Eliminate Connectors
Realign portion of taxiway at 400’ separation Add connector taxiway from Taxiway A to ramp outside of blind area Design new taxiways to current TDG standards
14
UNINTENDED IMPACTS ARFF inside Taxiway OFA
15
UNINTENDED IMPACTS ARFF inside Taxiway OFA RESULTS IN… Relocate ARFF
16
UNINTENDED IMPACTS RESULTS IN… ARFF inside Taxiway OFA
ARFF siting criteria at existing SRE and maintenance facilities RESULTS IN… Relocate ARFF
17
UNINTENDED IMPACTS RESULTS IN… ARFF inside Taxiway OFA
ARFF siting criteria at existing SRE and maintenance facilities RESULTS IN… Relocate ARFF Relocate SRE and maintenance facilities
18
Thank you PROJECT BENEFITS SAFETY
Reduce runway incursion potential by removing direct ramp-to-runway access. Eliminate head-to-head traffic. Changes to the movement area. Eliminates the ATC blind spot at Concourse B. Fewer and simpler SOPs for ATC. Eliminates LOA for pushback from gates B7 and B8. Reduces ARFF response time to the midfield of Runway 4-22. STANDARDS Taxiway conformance with current FAA design standards. Non-standard intersections of existing Taxiways A, C and A6 will be eliminated.