1 Hall A Target Status 9/27/16 Dave Meekins

2 Hall A Target Issues from last run Summer testing New business:
Lost loop 3 cell Every loop leaks Summer testing Leak testing with cold target(s) New business: Request to update solid target ladder Request to install LiH target Performed Post Run as found

3 Cold Leak Testing New pulse tube refrigerator test stand
Leak testing can now be done cold 6K or less depending on mass Test: Block assemblies Small components Full 24hr to turn around Can find leaks but not pin point them

4 Ongoing Work Lost loop 3 cell due to external overpressure
Leak testing the loops/cell blocks Found cold leaks in all loops this summer using ESR Leaks were still present when cells were removed Week for turn around Removed cell blocks and piping for testing in EEL All blocks leaked cold Solid target (optics) altered

5 Loop 2 Cell Block Knife edge damaged
Repaired by skim cutting knife edges in Shop Edges are now slightly deeper than original flanges Custom cut gaskets for each flange

6 Blanked off cell block Installed in test stand and cooled to <10K Filled with He Perform external leak test Can only show “leak/no-leak”

7 Current Status Solid target work is complete
updated multi-C optics target Cleaned up some control issues Performed cold testing of cell blocks only Found all blocks leaking Continue with seal testing Working on installation of loop piping After installation of cell blocks/piping Install cells Install solid targets Align

8 Schedule 1 day Wed 9/28 Install loop piping 1 day Wed 9/28 Leak test cell block with indium seals 1 day Thu 9/29 Leak test with thicker CF gaskets 1 day Sun 10/2 Install cell blocks 1 day Sun 10/2 Connect piping 1 day Mon 10/3 Install solid targets 1 day Tue 10/4 Align target 2 days Tue 10/4 - Wed 10/5 Close chamber and pump 1 day Wed 10/5 Pump/purge loops 1 day Thu 10/6 Cool down 2016 2016 Day 1 2 3 4 5 6 7 8 9 2016 Today


Download ppt "Hall A Target Status 9/27/16 Dave Meekins."