Mathieu, Gabriel, Max, Spyros, Guillaume
LHC SPARE CAVITY RF TEST PREPARATION Mathieu, Gabriel, Max, Spyros, Guillaume 01/11/2016 Mathieu Therasse
2
CAVITY PREPARATION FOR RINSING BEFORE COATING
½ Day, 2 persons Preparation Plates mouting PE flanges mounting Installation on the coating support Clearoom preparation Cane mounting Instrumentation connection 01/11/2016 Mathieu Therasse
3
CAVITY PREPARATION FOR RINSING BEFORE COATING
Particle counter Measurement done before the rinsing cane TOC and Resistivity Measurement done before and after the the rinsing cane Pupw = 3 bars During ≈1h Alcohol 5 bars, 20L Drying ≈2h Improvement to be schedule: Water parameters measurement after the cane filter (TOC, R, Particles) Water parameters measurement after the cavity (TOC, R, Particles) Water pressure increase 01/11/2016 Mathieu Therasse
4
RINSING BEFORE COATING
PC1 PC2 01/11/2016 Mathieu Therasse
5
CAVITY PREPARATION FOR RINSING AFTER COATING
1 Day, 2 persons Preparation: Flanges degreased (bldg 102) Flanges mounting RF Antennas: input 53.5 mm (7/16 feedthrough) and 2x output 34 mm (N Type) Top: transition CF300 to CF100 and the rinsing cane Bottom: «cone» use to collect the water and for pumping Intrumentation mounting Improvement to be schedule: Installation of a new electrical Crane in the cleanroom and adapted to lift heavy load Automatized rinsing system 01/11/2016 Mathieu Therasse
6
RINSING PROCESS 2 hours, 2 persons Setup Parameters
Cane fixed to the crane 0.2 m filtered Water on the cane top 0.2 m filtered N2 gas Water station: TOC and particle measurement (inlet) Water resistivity measurement (oulet) Parameters Rinsing pressure: 4 bars max Inlet water: TOC= 4-5 ppb R= 18.2 M.cm Particle: 0.1 um, 0.2 um Outlet water: Resistivity measurement: R>12.5 M.cm after 3 min (after rinsing) Improvement to be schedule: Water parameters measurement after the cane filter (TOC, R, Particles) Water parameters measurement after the cavity (TOC, R, Particles) The rinsing machine is not adapted for high pressure rinsing 01/11/2016 Mathieu Therasse
7
PC1 AND PC2 RINSING AFTER COATING
UPW station parameters UPW station parameters UPW parameters after filter (old filter) Measurement process error 01/11/2016 Mathieu Therasse
8
CAVITY DRYING AND PUMPING
½ Day, 2 persons Heater bands installation Filtered N2 gas (0.2 m, bottle) during pumping Pumping with liquid N2 Heating procedure Improvement to be schedule: Renew the bake out equipment (heater rack controller, heater bands) Vacuum at the end (with a primary pump): PC1: P=3x10-1 mbar PC2: P=3.4x10-1 mbar 01/11/2016 Mathieu Therasse
9
CAVITY CLOSURE ½ Day, 2 persons The closure is done in ISO 5 Baldaquin
Heater equipement removing Cavity and Baldaquin cleaning «cone» removing CF300 copper plated mounting Cavity transport to SM18 for the RF test preparation 01/11/2016 Mathieu Therasse
10
CAVITY MOUNTING ON THE RF TEST STAND IN SM18
1.5 Day, 2 persons Cavity connection to the insert pumping line Critical operation The area around the connection is cleaned (cleanroom standard process) Connection done in front of a laminar flow The cavity arrives in SM18 at P=1000mbar Cavity installation on the insert Improvement to be schedule: New mobile soft wall clean room (end of november 2016) 01/11/2016 Mathieu Therasse
11
CAVITY MOUNTING ON THE RF TEST STAND IN SM18
Slow pumping with a mobile pumping unit - Rinsing of the pumping connection 3x with flitered N2 gas (0.2 m) before cavity valve opening Membrane primary pump (3m3/h) Turbo pumping at 0.1 mbar Ionic pumping at 10-6 mbar Leak detection 3 hours+1 night, 1 person Leak rate: mbar l/s He gas 01/11/2016 Mathieu Therasse
12
CAVITY MOUNTING ON THE RF TEST STAND IN SM18
PC1 and PC2 leak detection PC1 PC2 First RF test First RF test Leak on a CF100: 10-7 mbar l/s Changing with a laminar flow Ionic pump equipped with a main valve changing Leak detection: 10-9 mbar l/s Final leak detection: 9.5x10-10 mbar l/s Second RF test CF300 changing stain steel to copper plated Leak detection: 9x10-10 mbar l/s Rmk: Small leak on the ionic pump main valve 01/11/2016 Mathieu Therasse
13
CAVITY MOUNTING ON THE RF TEST STAND IN SM18
½ Day, 2 persons Instrumentation mounting and testing - Safety valve 0.8 and 1 bar - Burst disk 2.5bars - PT 0-4 Bars - 6x TT cernox - 3x LT 1150 mm - 4 x Thermocouples - Heaters: - Heaters 2x 1kW (50Ω) - evaporator 500W (100 Ω) Improvement to be schedule: Add TT sensors on the cavity (top and bottom) Cryo control has to be finalized (process, heaters) (SM18 cryo shutdown) 01/11/2016 Mathieu Therasse
14
CAVITY MOUNTING ON THE RF TEST STAND IN SM18
Cryostat Preparation ½ Day, 2 persons Rmq: Insert support has to be validated by HSE Sensitive manipulation Cryo process Purge (1 night) Cooldown (1 day) Operation - 4.5K, P≈1.3bars - 2k, P ≈ 16 mbars (1 day) 01/11/2016 Mathieu Therasse