1 THEMIS Mission Confirmation Readiness
Review Peter R. Harvey University of California - Berkeley

2 GSFC-Required Additional Management
Issue#1. Staffing GSFC-Required Additional Management UCB Has Complied with Additional Personnel Swales/Hammers Oversight: Dave King (fmr GSFC/JSC Shuttle) Mission I&T : Rick Sterling (RHESSI) SE Oversight : - Thermal : Paul Cleveland (GSFC, RHESSI) - Software: Dave King / Will Marchant (EUVE, ChipSat) - I&T : Terry Sharton (JPL retired, RHESSI) ISM : Peter Berg (RHESSI) IDPU Dev Lead: Michael Ludlam (Rosetta)

3 Issue#2. Instrument Schedules
Add Detail to Instrument Schedules Continued to Detail Schedules (Definition & Resources) Worst Instrument Schedule (ESA) Added Instrument Manager (C. Scholz) Had n tasks, Now has M tasks At PDR, the instrumentation used 13 schedules, 1417 tasks Currently, we use 20 schedules, 2121 tasks Resource loading being added as time permits. Schedule Maintenance Instrument Developers Report to Their Schedule Weekly 1 Full-Time Scheduler for Instrumentation Provides Status to Project Management & Mission Manager

4 Impacts of Delayed GSFC-UCB Contract
Issue#3. Contracting Impacts of Delayed GSFC-UCB Contract GSFC-UCB Contract Definitized December 2003 UCB-Swales subcontract work agreed by all parties Implement subcontract value per CSR proposal Add Swales-developed CPU card as mod 1 Subcontract Expected in February timeframe Contract Delay has had no known cost or schedule impacts to reserves.

5 Develop Integrated Risk Management
Issue#4. Risk Develop Integrated Risk Management GSFC Provided Risk Management Training to UCB Jan 2004 THEMIS Risk Management Plan Submitted Jan 2004 UCB/Swales Risk Lists Integrated and Provided to Explorers

6 Issue#5. Separation System
Expedite Separation System Development Prioritizing the Separation System tests at Swales Long Lead Item (NSI’s) are currently critical path. Review of Test Plan Considered Essential to the Effort

7 Expedite ODA Issue Resolution
Issue#6. Orbit Debris Expedite ODA Issue Resolution Submitted Orbit Debris Analysis Results Lower Perigee Option Helps but may Impact Science Studies with KSC and Boeing to Provide Possibilities Examining Possible Options to Increase Reliability from 0.83 Reliability of a Single-String Probe will Never be 0.99

8 Issue#7. Instrument Thermal
Instrument Thermal Design Instrument Thermal Design presented only at Peer Reviews    Detailed thermal analyses have been completed for all instruments            Currently on 3rd iteration of integrated instrument/spacecraft model            Hot/Cold cases have been identified and are being used            Board level thermal analyses are in progress    Peer Review of instrument thermal design has been scheduled for last week in February    Paul Cleveland (RHESSI) Providing Oversight of system level thermal design

9 Issue#8. Monitoring Separation
Add Separation Monitoring for Probes 2-5 Top Probe Will Transmit Separation in RealTime All Other Probes Will Be Programmed to Monitor Probe Sep Each Probe will have Gyros On Replay of All Probes after Separation one at a time. Details in MPDR RFA #17