Presentation is loading. Please wait.

Presentation is loading. Please wait.

Wilkes-Barre/Scranton International Airport Taxiway B Extension to the Runway 22 End By: Steve Mykulyn, PE and Rick Holes, PE September 28, 2017.

Similar presentations


Presentation on theme: "Wilkes-Barre/Scranton International Airport Taxiway B Extension to the Runway 22 End By: Steve Mykulyn, PE and Rick Holes, PE September 28, 2017."— Presentation transcript:

1 Wilkes-Barre/Scranton International Airport Taxiway B Extension to the Runway 22 End By: Steve Mykulyn, PE and Rick Holes, PE September 28, 2017

2 Project Team Prime Subconsultants CDI L.R. Kimball
Civil Design Partners Aided in Project Management, Surveying and all Permitting Arora Engineers, Inc. Aided with Airfield Electrical and Navigational Aid Relocation Applied Geoscience and Engineering, Inc. Aided with Geotechnical Investigation and Engineering Ohio University Avionics Engineering Center Aided with Glide Slope Design and Analysis KBA Engineering Aided with Construction Inspection

3 Existing Conditions Taxiway B Ended 1,200’ from Runway 22 Threshold
Existing Taxiway B Pavement is 100’ in Width 400’ from Runway 4-22 Centerline 75’ Striped for Taxiway 12.5’ Paved Shoulders (each side) Meets Some Group IV Criteria Runway 22 Glide Slope Antenna was in the RSA 850’ from Runway 22 Threshold 190’ from Runway 4-22 Centerline Runway 22 RVR was in the Extended Taxiway B Alignment 1,075’ from Runway 22 Threshold 395’ from Runway 4-22 Centerline 80+’ Dropoff in Terrain Beyond the End of Taxiway B

4 Pre-Construction Condition

5 Phase 1 – Preliminary Design and EA
Extend Taxiway B to Runway 22 End Three Alternatives Relocate Runway 22 Glide Slope Antenna and RVR Two Alternatives FAA Coordination and Reimbursable Agreement Complete an FAA Environmental Assessment Geotechnical Engineering

6 Additional Items to Consider
FAA Reimbursable Agreements Primary work was with the FAA Boston NAVAIDs Center Preliminary Design covered Scoping and Design Alternative Review A second Reimbursable Agreement was required for Final Design Two additional Reimbursable Agreements were required for Construction Required Coordination with various levels of the FAA Environmental Assessment Full EA required due to the presence of wetlands Coordinated with Resource Agencies Completed Alternatives Analysis Reviewed Environmental Impact Categories Reviewed Environmental Consequences

7 Additional Items to Consider
Geotechnical Investigation Borrow Area Determined how much material was available Developed new Blasting Plan Developed haul route to work area(s) Fill Placement Needed fill benching plan Develop tie-in with existing steep fill slopes Complete slope stability analysis for various fill slopes Analyze potential for mine void issues Large Boulders Left over from previous fill projects Needed to be incorporated into fill placement Determine how to break them down to useable sizes Determined how to haul them to the work area(s)

8 New FAA Taxiway Design Criteria
New Advisory Circular design criteria was used An Aircraft Analysis was completed The wingspan of the Aircraft using the Airport met FAA Airplane Design Group III 118’ Taxiway Safety Area 186’ Taxiway Object Free Area Based on the MD-Series Aircraft, the new TDG was 5 for this project Taxiway Design Group 5 Criteria 75’ Taxiway Pavement Width 25’ Taxiway Shoulders 12.5’ Paved Shoulders (each side) 12.5’ Turf Shoulders (each side)

9 Alternatives Five (5) final alternatives were analyzed
Straight taxiway extension with a capture-effect GS antenna on the right side of the Approach Taxiway extension that was routed around the GS critical area with a capture-effect GS antenna on the right side of the Approach Straight taxiway extension with an end-fire GS antenna on the right side of the Approach Straight taxiway extension with a capture-effect GS antenna on the left side of the Approach Straight taxiway extension with an end-fire GS antenna on the left side of the Approach

10 Taxiway B Alternative Summary
Work Element Alt. #1 Alt. #2 Alt. #3 Alt. #4 Alt. #5 Taxiway Access to RW 22 X Type of GS Antenna Proposed C-E E-F Location of Proposed GS Antenna Right Left GS Antenna Outside of RSA N/A GS Antenna Allowed inside of RSA ILS Hold Line Required 1,125’ 485’ No Fill Required (Cubic Yards) 487k 772k 860k 538k Land Acquisition Required (Acres) 0.41 3.10 Wetlands Impacted (Acres) 0.27 Existing GS On During Construction Yes Estimated Construction Time (Days) 324 431 342 548 357 Estimated Loss of Revenue $762k $962k $836k $0 Estimated Cost (Million Dollars) $7.24 $10.10 $8.94 $10.52 $9.30

11 Preferred Alternative (#4)
Extend Taxiway B to Runway 22 End meeting current FAA Design Criteria 75’ Taxiway Width and 25’ Shoulders (12.5’ Paved/12.5’ Turf) Relocate Runway 22 Glide Slope Antenna to left side of Approach Capture-Effect Antenna Place fill to create required Glide Slope Critical Area Most expensive and most environmentally sensitive option Higher cost due to need to fill GS critical area Required land acquisition for GS critical area fill Impacted 0.27-acre of wetland area Could be constructed with limited impact to Airport operations

12 Preferred Alternative (#4)

13 Borrow Area Grading for Borrow Area
Approximately 2,800,000 Cubic Yards of Fill Available

14 Phase 1 Timeline Notice to Proceed – September 2012
Pre-Design Meeting – October 3, 2012 Finalization of Alternatives – December 5, 2012 Submission of First Draft EA – May 28, 2013 Submission of Final Draft EA – July 16, 2013 Submission of Final EA – September 9, 2013 Receipt of FONSI – September 27, 2013

15 Phase 2 – Final Design and Permitting
Final Design of Taxiway Finalize Taxiway Geometry Finalize Grading Grade full Runway Safety Area Taxiway superelevated along entire length Reconstruct Taxiway B5 to make grades work Pick up existing storm drainage Finalize Signage and Pavement Marking MOS for signs due to location on right side of taxiway Final Design of Glide Slope Finalize Grading of Critical Area Finalize new electric service to left side of Runway 4-22

16 Phase 2 – Final Design and Permitting
Wetland impacts required a Chapter 105 Permit Included enhancement of existing wetland mitigation area NPDES Permit Taxiway Extension was located in Lackawanna County Borrow Area and Wetland Mitigation Area were located in Luzerne County Both County Conservation Districts required submissions Stormwater Management Taxiway Extension required approval from Pittston Township and Luzerne County Project was located in a 60% Release Rate District Underground SWM was the only option Mine voids were an issue

17 Blasting/Hauling Design Concerns
Borrow Area was located approximately 0.8 mile from Glide Slope fill area and 1.5 miles from Taxiway fill area Borrow Area was located as close at 250’ from the ATCT and as close at 1,200’ from Runway 4-22 Borrow Area had been used numerous times in the past Fractured rock Large boulders

18 Proposed Construction Contracts
Site Preparation Included E&S and Stormwater Management GS critical area was to be completed first Included fill, seeding and mulching for GS critical area Taxiway fill was allowed up to 25’ below the existing grade in order to keep the existing GS antenna functioning Included fill placement to rough subgrade for taxiway Estimated construction time was 450 days NAVAIDs Installation Included new Glide Slope Antenna construction New Antenna and shelter were provided by FAA Included FAA tuning and flight check Included demolition of existing Glide Slope Antenna Estimated Construction Time was 120 Days

19 Glide Slope Critical Area Grading Plan

20 Taxiway Extension Grading Plan

21 Proposed Construction Contracts
Taxiway Paving Included fine grading of subgrade and subbase placement Included underdrain installation Included paving and pavement marking Included shoulder backup grading and seeding and mulching Estimated construction time was 90 Days Taxiway Lighting Included new regulator and home runs for this section of taxiway Included all taxiway lighting installation for Taxiway B from Runway to the Runway 22 End Included signage installation Estimated construction time was 120 Days

22 Final Paving Plan

23 Final Lighting and Signage Plan

24 Proposed Contracts and Schedule
Received First Bids in July 2014 Site Preparation (Leeward Construction) - $8,455,002 NAVAIDs (Joyce Electrical) - $566,675 Started Site Preparation Construction November 10, 2014 Started NAVAID Construction March 2015 Received Second Bids in June 2016 Paving (Popple Construction) - $2,040,538 Lighting (Walsh Electrical) - $442,410.50 Started Paving and Lighting Construction September 26, 2016

25 Glide Slope Critical Area Construction

26 Taxiway Fill Construction

27 Mine Voids

28 Borrow Area

29 Taxiway Paving

30 Summary Total project time from start to finish was 5 years
New taxiway opened on July 18, 2017 Runway 22 REILs were completed on August 25, 2017 Total Project Cost = $15.7 Million 915,000 cubic yards of fill 8,700’ of storm drain installation More than 12,000 tons of asphalt pavement 33 new LED taxiway lights and 39 incandescent lights were replaced with LED lights Nearly 4 miles of electrical cable was installed

31 Wilkes-Barre/Scranton International Airport Taxiway B Extension to the Runway 22 End Thank You From: Steve Mykulyn, PE and Rick Holes, PE September 28, 2017


Download ppt "Wilkes-Barre/Scranton International Airport Taxiway B Extension to the Runway 22 End By: Steve Mykulyn, PE and Rick Holes, PE September 28, 2017."

Similar presentations


Ads by Google