Presentation is loading. Please wait.

Presentation is loading. Please wait.

Functional Specification

Similar presentations


Presentation on theme: "Functional Specification"— Presentation transcript:

1 Functional Specification
H. Felice, D. Simon, J.M. Rifflet CEA/IRFU/SACM A. Foussat CERN for the QuaCo team Bidder’s Conference, CERN, July 7th 2016

2 Technical Context of QuaCo
One of the insertion magnets of the high luminosity upgrade located before the interaction points Belongs to the Matching Section magnets which match the optics function from the arc (regular cells) to the inner triplet Double aperture magnet: 2 individual apertures powered independantly in a common yoke MQYY HL-LHC layout - Ezio Todesco IP H. Felice - Functional Specification

3 Technical Context of QuaCo
Funding scheme aiming at supporting industries to develop and manufacture a First-of-a-kind magnet Starting point: a magnetic design as an example: which can be kept or modified Coil geometry including end spacers Contractor’s responsibility Provide a complete magnet design Tooling design and manufacturing Magnet manufacturing Contribution from the Buyer’s Group: Magnet protection study H. Felice - Functional Specification

4 Functional Specification
Document IT-4191/TE/HL-LHC EDMS No: Technical Scope of the PCP PCP phases Technical Deliverables Functional requirements Items provided by the Buyer’s Group Example of magnetic design Minimum set of electrical tests H. Felice - Functional Specification

5 Some Definitions and important points
TOOLING definition. Magnet tooling Tooling dedicated to the magnet and including coil fabrication tooling (winding mandrel, curing mold…), structure assembly tooling, support fixture Infrastructure tooling Tooling usable for several types of magnets such as winding machine, curing press… Development plan Unlike other magnet contracts (built-to-print), the Contractor is expected to propose a magnet development and manufacturing plan including measurement and QA methods The measurement accuracy and technique should be proposed by the Contractor and validated by the Buyer's Group H. Felice - Functional Specification

6 Information transfer from the Buyer’s Group to the company
All the Contractors will have access to the same background from the Buyer’s Group. This will cover the MQYY magnetic design and coil design as well as quench protection. Tools development are part of the scope of the QuaCo PCP and will have to be developped by the Contractors along with a development plan. Any Background from the contractor about previous magnets relevant to the Quaco PCP is welcome to the project and will be kept confidential H. Felice - Functional Specification

7 Design starting Point Files provided by the Buyer’s Group
Magnetic Files ROXIE: 3D and 2D, cadata, iron file Opera CONDUCTOR file only Coil model including end parts STP and CATIA files If the Contractor decides to modify the magnetic design, the magnetic design should be completed by the end of Phase I. H. Felice - Functional Specification

8 Technical starting Point
Material, equipment and components provided by CERN Material, equipment and components provided by CERN upon request NbTi insulated Cable Protection heaters Low carbon steel for magnetic yoke (Hot rolled: 5.8 mm thickness, 650 x 3000 to 4000 mm) Austenitic steel material Rad hard Material for end parts Calibrated warm magnetic measurements probe No other material or components supplied unless a need is clearly expressed by the Contractor and is considered relevant by the Buyer's group H. Felice - Functional Specification

9 Technical starting Point
Material, equipment and components provided by CERN Some samples can be provided if the need is demonstrated by the development and manufacturing plan NbTi insulated Cable Protection heaters Calibrated warm magnetic measurements probe The protection of the magnet relies on protection heaters. With protection heaters, the hot spot is expected to be below 200 K. Fault scenario are under study. For now there is no planned energy dump The zero will depend on the magnetic measurement system accuracy. H. Felice - Functional Specification

10 Miscellaneous technical questions
Radiation Hardness If impregnation is foreseen by the Contractor as part of the fabrication, Epoxy CTD 101 K has been granted acceptable for this application without the need to go to cyanate ester. Any other resin should be qualified LHC references : and  Persistent current: effect should be computed but not a driver for the design. Capacitive gauges This technology is not developed anymore at CERN. The instrumentation lab is open to discuss with Contractors possible route for instrumentation to be developed by the Contractor. Interface: An initial set of interface specification will be available early in Phase 1 and shall be sufficient to execute the work of Phase 1. Any modification from this initial spec is not expected to create any impact on price or schedule. The modification will typically be fine tuning of the yoke outer features (cut-outs for example). H. Felice - Functional Specification

11 Licences Use of ROXIE Use of Castem
Will be available without licensed BEM FEM module Use of Castem License of approximately 4500 €. No direct comparison with results from CEA as the development should be made only by the Contractors. ANSYS is of course acceptable for mechanical computation H. Felice - Functional Specification

12 Quaco 3 phases Phase 3 First-of-a-kind manufacturing and testing Phase1 Solution Design Phase 2 Engineering Design All tooling and components design completed and purchasing docs ready Tooling and components procurement H. Felice - Functional Specification

13 Scope of Phase 1 Conceptual designs of the tooling and of the magnet are expected including: A preliminary magnetic design; If the Contractor chooses to develop a new magnetic design, the 2D and 3D magnetic designs shall be finalized by the end of Phase 1. A conceptual design of the support structure consisting of finite element analysis and CAD models; Conceptual designs of the coil fabrication tooling and of the magnet assembly and support tooling (preliminary 2D and 3D CAD models). A preliminary manufacturing and inspection plan along with concept of assembly processes. Project management documents including the detail of the work either carried out at the Contractor’s premises or subcontracted. Reassessment of the work to be carried out in Phases 2 and 3. H. Felice - Functional Specification

14 Deliverables of Phase 1 H. Felice - Functional Specification
Description D1.1 Conceptual Design Report (CDR) of the magnet covering the results obtained in Phase 1 including: Magnetic design study Conceptual mechanical design study List of requirements met by the design D1.2 Preliminary 2D and 3D CAD models of the magnet D1.3 Conceptual Design Report of the Tooling including: Coil fabrication tooling conceptual design Magnet assembly tooling conceptual design D1.4 Development and Manufacturing plan including: Detailed plan for Phase 2 detailed engineering design Detailed plan for the mock-ups to be developed in Phase 2 Detailed plan for manufacturing, assembly and testing processes of the magnet List of available tooling including required upgrade if necessary List of tooling to be procured to complete the three Phases Subcontrating plan D1.5 Detailed schedule for the three Phases D1.6 Preliminary Quality Assurance plan including risk assessment one month after the start of Phase 1 for Buyers Group approval. D1.7 Final Phase 1 Technical Report including the reassessment report of R&D effort for Phases 2 and 3 H. Felice - Functional Specification

15 Scope of Phase 2: Detailed Engineering Design
Final coupled magnetic and mechanical design including integration features. Final CAD models of the magnet and its components and of all the related tooling. A final manufacturing and inspection plan including assembly and fabrication procedures. Mock-ups and associated tooling if required. Updated project management documents including the list of work carried out at the Contractor’s premises or subcontracted. All the purchasing documents for the procurement of the magnet tooling and components Reassessment of Phase 3 work H. Felice - Functional Specification

16 Deliverables of Phase 2 Deliverable Description D2.1
Detailed Design Report (DDR) covering all the results obtained in Phase 1 and 2 including: Detailed Magnetic design optimisation Detailed Mechanical design optimisation Sensitivity analysis toward fabrication Magnet protection items provided by the Buyers Group Updated list of requirements met by the design D2.2 Detailed 2D and 3D CAD manufacturing drawings of the magnet and subcomponents including instrumentation schematics D2.3 Detailed 2D and 3D CAD drawings of the manufacturing tooling D2.4 Manufacturing and Inspection Plan (MIP) D2.5 Mock-ups, if any, in agreement with development plan D2.6 Updated schedule D2.7 Final Quality Assurance plan D2.8 Technical mid-phase report D2.9 Final technical specification for tooling and components D2.10 Final Phase 2 Technical report D2.11 Technical specification of the MQYY First-of-a-kind and reassessment report of R&D effort for Phase 3 H. Felice - Functional Specification

17 Scope of Phase 3: First-of-a-kind manufacturing and testing
Procurement of all the components and tooling to proceed with magnet fabrication. Coils fabrication Assembly of the magnet Final as-built CAD models and 2D drawings Updated project documents. Each stand-alone aperture and the First-of-a-kind magnet shall be validated by ambient temperature Factory Acceptance Tests Minimum Tests proposed in FS The First-of-a-kind magnet shall be packed and shipped to the Buyers Group (CERN or CEA/Saclay). The address will be communicated to the Contractor during Phase 2. H. Felice - Functional Specification

18 Deliverables of Phase 3 Deliverable Description D3.1
Delivery certificates of tooling D3.2 Delivery certificates of magnet components (excluding the components provided by CERN, indicated in § 2.4) D3.3 One practice coil (trial full-scale coil built to validate the coil fabrication process), nine fully conforming cured coils including one spare coil D3.4 Completed Manufacturing and inspection plan including updated list of subcontracted activities. D3.5 Quality control and test reports in compliance with § 5.2 and § 5.3 D3.6 As-built 2D and 3D CAD manufacturing drawings of the magnet D3.7 As-built 2D and 3D CAD manufacturing drawings of the tooling D3.8 Delivery of MQYY quadrupole with complete MTF traveller and shipment file D3.9 Updated detailed schedule D3.10 Updated Quality Assurance plan D3.11 Technical quarterly reports D3.12 Pre-commissioning of the manufacturing tooling D3.13 Commissioning report of the manufacturing tooling D3.14 Final manufacturing report covering All the results obtained in Phase 1, 2 and 3 Final list of requirements met by the magnet D3.15 Preliminary technical specification of the MQYY series magnet H. Felice - Functional Specification

19 Ownership of the infrastructure tooling
The Contractor owns the tooling before Quaco PCP or develops and buys the tooling during Quaco PCP with its own funds The infrastructure tooling stays at the company at the end of Quaco. Only functional drawings (not detailed) will be requested by the Buyer’s Group at the end of Quaco to allow fabrication of the series. The Contractor develops and buys the tooling during Quaco PCP with Quaco funds If the Contractor uses the tooling either in the Buyer’s group series production or in any commercial exploitation, the tooling remains with the Contractor (clause #8 of the FA) H. Felice - Functional Specification

20 Any additional questions?
H. Felice - Functional Specification


Download ppt "Functional Specification"

Similar presentations


Ads by Google