SOFTWARE LIFE-CYCLES Beyond the Waterfall.

Similar presentations


Presentation on theme: "SOFTWARE LIFE-CYCLES Beyond the Waterfall."— Presentation transcript:

1 SOFTWARE LIFE-CYCLES Beyond the Waterfall

2 The WATERFALL LIFE-CYCLE Milestones Requirements System Design
Standards Detailed Design Implementation Installation & Testing Documents Maintenance

3 Problems with the Waterfall Model
sequentiality late testing paradigm late feedback to customer and engineer minimal risk management for customer and engineer

4 The “V” LIFE-CYCLE Requirements Acceptance Test System Design
Integration Test Detailed Design Module Test Implementation

5 Analysis of the V-Shaped Life-Cycle
Improves the testing paradigm ==> Quality Assurance Does NOT really improve: sequentiality feedback risk management (during development)

6 INCREMENTAL DEVELOPMENT Requirements Global System Design Detailed D.
Implem. Implem. Implem. Testing Testing Testing Maintenance

7 Analysis of Incremental Development
Assumes independent subsystems! Improves (by delivering smaller units): feedback: stepwise testing Avoids monolithic product Does not really improve: risk management during development sequentiality: subsystems

8 (Rapid) Prototyping Goals: break away from sequentiality
speed up feedback minimize risks for customer and engineer incomplete but executable cheap and fast

9 Prototyping Definition (A. Davis):
A prototype is a partial implementation of a system, constructed primarily to enable customer, user, or developer to learn about the problem or its solution. Types: evolutionary / throw-away horizontal / vertical

10 Horizontal Prototyping
f1 fn user hardware

11 Vertical Prototyping f1 fn user hardware

12 Analysis of Pure Prototyping
Improvements: breaks sequentiality supports fast feedback opportunity for risk management Problems: missing organisational structure ==> combine with a life-cycle

13 The Spiral Model Goals: risk management compatible mix between
clear structure (life-cycle) & flexible prototyping supports fast feedback & quality assurance

14 risk analysis p r o t o t y p e s evaluate alternatives,
identify & resolve risks determine objectives, alternatives, constraints risk analysis p r o t o t y p e s principles req. plan require- system ments dev. detailed design design plan integ. plan implement plan the next phase test & install develop & verify product

15 End of Section 1c coming up: methodologies for analysis & design