1 Millworks 5.0

2

3

4 Design Constraints Site sits above Madison Road; separated by retaining wall Rail line Ring road is privately owned. Cast Fab and Milacron have access easements Extensive roadway improvements are needed to accommodate dense redevelopment Need to maintain pedestrian bridges Northern portion of site abuts loading docks for Center of Cincinnati Industrial & retail uses across Madison Road

5 Market Constraints Competing office sites along I-71 at Montgomery, Ridge, Smith/Edwards & Dana Competing retail sites at Smith/Edwards, Montgomery (XU) Competing residential at Marburg Square, 4120

6 Important Considerations
Retail and entertainment should complement Oakley Square, not compete with it Oakley opposes more big box development Redevelopment should connect to neighborhood Displaced businesses should be relocated inside the city City’s financial participation should be reasonable Opportunities for reuse of existing buildings? Environmental considerations: siting residential uses on cleanest portion of the site

7

8

9 Millworks 1.0 (2004-5) Vision Land Development & Trademark Property Co. 2 phases Cost for first phase: $88M City role: $10M in TIF/$3M CORF grant 514,000 sf in total for phase 1 80,000 sf office (heart hospital) 75,000 sf Showcase Cinemas 89,000 sf Jungle Jim’s Grocery 270,000 sf restaurant, retail (lifestyle center), and possibly hotel Possibility of 150,000 SF of office in phase 2

10 Millworks 1.0

11 Millworks 2.0 (May 2006) VLD, Prudential REIT & Trademark Property Company 2 phases Cost for first phase: $122M City role: $10M in TIF/$3M CORF grant 570,000 sf in total for phase 1 125,000 sf office 75,000 sf Showcase Cinemas 300,000 sf restaurant & retail (lifestyle center), including Jungle Jim’s 70,000 sf of condominiums Possibility of office, hotel, retail & residential in phase 2

12 Millworks 2.0

13 Millworks 3.0 (Nov 2006) VLD & Bear Creek Capital One phase
Cost: $268M City role: $30M in TIF/$3M CORF grant 1.7M sf in total 600,000 sf office 75,000 sf Showcase Cinemas 325,000 sf restaurant & retail (lifestyle center) No Jungle Jim’s 700,000 sf of residential space

14 Millworks 3.0

15 Millworks 4.0 (Nov 2007) VLD & Frontier Renewal
67 acres (lost control of the Milacron property) Two phases: 1) site prep, 2) sell of components to other developers Cost: $300M City role: $55M in TIF/$3M CORF grant Approximately 2M sf in total 715,000 sf office 75,000 sf Showcase Cinemas 388,000 sf restaurant & retail (lifestyle center) 160,000 sf hotels 679,000 sf residential

16 Millworks 4.0

17 Millworks 5.0?

18 Jeff McElravy