DICKINSON AVENUE RECONSTRUCTION
PUBLIC MEETING July 19, 2017 &
2
DICKINSON AVENUE PROJECT OVERVIEW BEGIN PROJECT
3
DICKINSON AVENUE PROJECT OVERVIEW BEGIN PROJECT END PROJECT
4
DICKINSON AVENUE PROJECT OVERVIEW BEGIN PROJECT 1.06 MILES END PROJECT
5
DICKINSON AVENUE PROJECT OVERVIEW BEGIN PROJECT END PROJECT 1.09 MILES
6
DICKINSON AVENUE TOTAL 2.15 MILES PROJECT OVERVIEW BEGIN PROJECT
END PROJECT
7
PROJECT OVERVIEW 10’ Concrete Multi-Use Path on east side of Dickinson
No additional ROW required Approximate Construction Cost $9,300,000 Additional detention will be provided to account for additional pavement
8
DICKINSON AVENUE TYPICAL SECTIONS STORM SEWER SECTION
9
CURB & GUTTER / STORM SEWER SECTION – 50’ / 60’ ROW
DICKINSON AVENUE CURB & GUTTER / STORM SEWER SECTION – 50’ / 60’ ROW EXISTING PROPOSED TRAVEL LANE TRAVEL LANE MULTI-USE TRAIL
10
DICKINSON AVENUE TYPICAL SECTIONS OPEN DITCH SECTION
11
OPEN DITCH SECTION – 70’ ROW
DICKINSON AVENUE OPEN DITCH SECTION – 70’ ROW EXISTING PROPOSED TRAVEL LANE TRAVEL LANE MULTI-USE TRAIL
12
CONSTRUCTION / TRAFFIC CONTROL
Bid separately as 2 projects Phase 1 – South Portion S.H. 96 to F.M. 646 – 12 months One- way detour phase – 4 months Phase 2 – North Portion E. Walker to S.H. 96 – 12 months One- way detour phase – 8 months Access to all properties will be maintained
14
DICKINSON AVENUE CONSTRUCTION TIME PHASE 2 – 12 MONTHS
15
SCHEDULE Public Meeting July 2017 70% Submittal July 2017
90% Submittal September 2017 Bid South Project (S.H. 96 to F.M. 646) October 2017 Construction South Project December 2017 – December 2018 (12 months) Bid North Project (E. Walker to S.H. 96) January 2019 Construction North Project March 2019– March 2020 (12 months)