Presentation is loading. Please wait.

Presentation is loading. Please wait.

COOPERATION PLAN for the EIA and Regulatory Review of an NWT Pipeline Ricki Hurst : Pipeline Readiness Office, DIAND Bonnie Gray: Northern Gas Development,

Similar presentations


Presentation on theme: "COOPERATION PLAN for the EIA and Regulatory Review of an NWT Pipeline Ricki Hurst : Pipeline Readiness Office, DIAND Bonnie Gray: Northern Gas Development,"— Presentation transcript:

1 COOPERATION PLAN for the EIA and Regulatory Review of an NWT Pipeline Ricki Hurst : Pipeline Readiness Office, DIAND Bonnie Gray: Northern Gas Development, NEB Inuvik Petroleum Show June 2002

2 What is the Cooperation Plan?
Plan coordinates activities of EA and regulatory boards and agencies for review of a major trans-regional natural gas pipeline through the NWT Plan developed in advance of an application to provide a regulatory roadmap and reduce confusion or duplication Plan based on goodwill and willingness to cooperate within existing legislation

3 Background Perception that regulatory system in the NWT was unclear, cumbersome, lengthy Uncertainty in the EIA/regulatory process is a key issue for proponents making a decision on routing Coordinating and clarifying Regulatory Process one thing that could be done to assist industry Plan involves at least 12 parties - both EIA and regulatory Boards and Agencies Focus on coordinating those with public hearing functions

4 Background (con’t) Chairs of all boards and agencies first met in November 2000 Meetings of Chairs and their Working Group have continued until now Chairs expressed desire early to work together to increase efficiency and reduce duplication process led to the Draft Cooperation Plan released in January 2002 for public comment From March-May 2002 the Boards and their Working Group have revised the Plan based on this public input Cooperation Plan now final

5 Who’s involved? ISR EIRB NEB CEAA DIAND NWT WB ILA Sahtu LWB
Yukon Govn’t IGC Gwich’in LWB GNWT ISR EISC MVEIRB Deh Cho ISR JS MVLWB Observers Agencies with a direct interest Agencies with public hearing processes

6 Assumptions/Principles
Plan had to apply to either an Over-the-Top or Mackenzie Valley stand alone project ‘made-in-the-North’ solution joint panel-level assessment for EIA must reduce duplication must enhance public participation couldn’t bind or pre-judge any decisions to be made by legislated Boards & Agencies

7 Inuvialuit Claim Settled 1984 Gwich’in Claim Settled 1992 Sahtu Claim Settled 1993 North Slave Deh Cho Unsettled South Slave

8 Main Elements of the Plan
separate EIA and regulatory processes NEB may be involved in EIA (Section 15) coordinated EIA and regulatory hearings consolidated information requirements common project secretariat common technical support shared public registry public involvement plan to be developed processes triggered by a ‘project information package’ or PIP and ‘suite of applications’

9 Phases of the Plan Preparation (next 6 months)
Preliminary Information Package - PIP ARC PIP received MV Producers PIP - Fall 2003? Pipeline Application (mid-late 2003?) EIA and Regulatory Hearings Completion of Regulatory Process

10 Environmental Assessment
Single EA done through joint panel involving CEAA, MVEIRB, Inuvialuit - panel size and composition and T of R to be determined based on 2 agreements: - Inuvialuit and Minister of Environment - MVEIRB, Inuvialuit and Minister of the Environment panel arrangements are triggered by preliminary information package (PIP) & “suite of applications” but not final until formal application

11 Regulatory Agreement NEB, MVLWB, NWTWB, GL&WB, SL&WB, DIAND, DFO, DOE, GNWT all distinct mandates - some common issues coordinate regulatory hearings in time & place consolidate information requirements integrate technical support to assist all panels develop common public registry avoid revisiting EA issues in regulatory proceedings

12 What didn’t happen? No Comprehensive Study option
Requires a full panel review No project splitting - ISR upstream development and gathering system/ Mackenzie Valley pipeline No joint NEB-Regulatory-EA panel (the “heroic” option)

13 Timing much depends on Applicant filings
Plan shows a 24-month process from application to leave to construct issues - MVRMA process is 3-step process triggered by applications & not by PIP Comparisons to Alaska/USA process (ie. 18 months)

14 Recent Steps Draft Cooperation Plan went out for 60 days public comment (January-March 2002) Written comments reviewed and suggestions incorporated into Final Cooperation Plan Letters sent from Chairs to contributors advising them of status and major changes in Plan Final Cooperation Plan tabled with Minister Final Cooperation Plan printed and released

15 Next Steps - Implement Cooperation Plan
Finalize Environment/Inuvialuit EIA Agreement Finalize Environment/MVEIRB/Inuvialuit EIA Agreement Finalize Regulators Agreement Finalize Consolidated Information Requirements Develop Public Involvement Plan Set up common public registry Design common project secretariat Design common technical support team


Download ppt "COOPERATION PLAN for the EIA and Regulatory Review of an NWT Pipeline Ricki Hurst : Pipeline Readiness Office, DIAND Bonnie Gray: Northern Gas Development,"

Similar presentations


Ads by Google