UK Link Programme Update to PNUNC August 13th, 2013

Similar presentations


Presentation on theme: "UK Link Programme Update to PNUNC August 13th, 2013"— Presentation transcript:

1 UK Link Programme Update to PNUNC August 13th, 2013

2 Introduction The aim of this session is to provide an overview of the anticipated programme activity for the replacement of UK Link It should be noted that at present these timescales are indicative and as more information becomes available as the programme progresses formal updates will be provided. 2

3 Programme Indicative Path
2013 2014 2015 2016 Q1 Q2 Q3 Q4 Logical Analysis DBI Sourcing HLD Detailed Design Cutover and go-live Build & Dev Test System & User Test Design R2 Cutover and go-live Build Test Data Cleansing Stakeholder Engagement Note: assumes a release based approach 3

4 Indicative Path: Logical Analysis Logical Analysis Key Deliverables
2013 2014 2015 2016 Q1 Q2 Q3 Q4 Logical Analysis Logical Analysis Key Deliverables Phase started 25th March 2013 Develop Logical Process & Data Models for the requirements captured in the BRDs during Project Nexus and known future requirements Undertake a detailed review of the Non-Functional Requirements. Define and introduce Competency Centre to support delivery of future changes as an enduring service Output will inform and support all future phases of the Programme Note: assumes a release based approach

5 Indicative Path: High Level Design High Level Design Key Deliverables
2013 2014 2015 2016 Q1 Q2 Q3 Q4 High Level Design Key Deliverables High Level Architecture Design, details the high level future state business processes and solution design Security Architecture and Policies, details at high level the framework to protect all assets Integration Architecture, details at high level, the integration framework between all systems, both internal to Xoserve and external Test Strategy & Plan, defines the overall test approach and each test phase with corresponding timelines Programme Delivery, definition and timescales of the remaining phases and indicative release plan High Level Design Note: assumes a release based approach

6 Indicative Path: Detailed Design Detailed Design Key Deliverables
2013 2014 2015 2016 Q1 Q2 Q3 Q4 Detailed Design Key Deliverables Detailed Architecture Design Detailed Security Architecture and Policies Detailed Integration Architecture Detailed Test Strategy & Plan, defines the overall test approach for each test phase with corresponding timelines Programme Delivery, definition and timescales of the remaining phases and detailed delivery plan Detailed Data Migration plan Detailed Design Note: assumes a release based approach

7 Indicative Path: Build Build Key Deliverables
2013 2014 2015 2016 Q1 Q2 Q3 Q4 Build Build Key Deliverables Technical Specification; Batch Job Configuration; Installation Guides Training Content & Materials; Test scripts Cutover plan Service Transition plan Dependencies / Impact on Legacy Systems Note: assumes a release based approach

8 Note: assumes a release based approach
Indicative Path: Test 2013 2014 2015 2016 Q1 Q2 Q3 Q4 Test Key Deliverables Under take User and System Test Review test results Dev Test System Test Integration Test Performance Test User Acceptance Test Technical / Operations Test Industry / Regulatory Transition handover document System & User Test R1 Go live Note: assumes a release based approach

9 Indicative Path: Release 2 Release 2 Key Deliverables
2013 2014 2015 2016 Q1 Q2 Q3 Q4 Release 2 Key Deliverables Same deliverables as Release 1, without High Level Design and potentially shorter timelines. Build Design Test R2 Go live Note: assumes a release based approach

10 Indicative Path: Data Cleansing & Migration
2013 2014 2015 2016 Q1 Q2 Q3 Q4 Data Cleansing Key Deliverables Data Cleansing Strategy & Approach Identification of Data Issues Data Topics Data Profiling Data Issue Analysis & Prioritisation Industry Engagement UK Link Steady State Cleansing Data Cleansing Progress Reporting Data Cleansing & MIgration Note: assumes a release based approach

11 Indicative Path: Stakeholder Engagement
2013 2014 2015 2016 Q1 Q2 Q3 Q4 Stakeholder Engagement Key Deliverables Identify stakeholders Understand Stakeholder Expectations Analyse and Map Stakeholders (Involve / Influence) Develop, maintain an effective communication plan (Review / Modify) Increase Stakeholder cooperation and success in delivering overall objectives (Impact of Change, Testing phases) Reduce the risk of misunderstanding the scope of work Stakeholder Engagement Note: assumes a release based approach