2 1. All of the following are correct concerning the Bid Form EXCEPT:
a. A document prepared in the form of information from the bidder to the Owner. b. It is always a part of the Contract Documents. c. It is prepared to assure a uniform arrangement which facilitates comparison and equal consideration for awarding the contract. d. It contains a space for the bidder's signature.

3 1. All of the following are correct concerning the Bid Form EXCEPT:
a. A document prepared in the form of information from the bidder to the Owner. b. It is always a part of the Contract Documents. c. It is prepared to assure a uniform arrangement which facilitates comparison and equal consideration for awarding the contract. d. It contains a space for the bidder's signature.

4 2. The purpose of the Invitation to Bid is to:
Attract qualified bidders Meet legal requirements on publicly bid projects To help prospective bidders decide whether to obtain the bidding documents.

5 2. The purpose of the Invitation to Bid is to:
Attract qualified bidders Meet legal requirements on publicly bid projects To help prospective bidders decide whether to obtain the bidding documents.

6 3. Criteria for setting the date for submission of bids should include all of the following EXCEPT;
Time for settlement of questions and discrepancies. Time required to process requests for approvals of substitutions. Time for the Owner to review the qualifications of the subcontractors. Time for collection of Subcontractor bids.

7 3. Criteria for setting the date for submission of bids should include all of the following EXCEPT;
Time for settlement of questions and discrepancies. Time required to process requests for approvals of substitutions. Time for the Owner to review the qualifications of the subcontractors. Time for collection of Subcontractor bids.

8 Bid security information Geotechnical data
Which of the following would be appropriate to be included in the "Information Available to Bidders": Bid security information Geotechnical data Time of completion to construct the project Description of the work

9 Bid security information Geotechnical data
Which of the following would be appropriate to be included in the "Information Available to Bidders": Bid security information Geotechnical data Time of completion to construct the project Description of the work

10 Right to reject bids and governing laws and regulations
5. The Invitation to Bid/Advertisement for Bid includes all of the following EXCEPT: Right to reject bids and governing laws and regulations Bid opening date, time, and location Details concerning bid security requirements Bidders prequalification

11 Right to reject bids and governing laws and regulations
5. The Invitation to Bid/Advertisement for Bid includes all of the following EXCEPT: Right to reject bids and governing laws and regulations Bid opening date, time, and location Details concerning bid security requirements Bidders prequalification

12 Comply with required bidding procedures
6. Sufficient information should be contained in the Bidding Documents to enable bidders to do all of the following EXCEPT; Comply with required bidding procedures Determine that the project meets all building codes Understand bidding and awarding requirements Understand conditions which apply after bid submission and prior to contract award.

13 Comply with required bidding procedures
6. Sufficient information should be contained in the Bidding Documents to enable bidders to do all of the following EXCEPT; Comply with required bidding procedures Determine that the project meets all building codes Understand bidding and awarding requirements Understand conditions which apply after bid submission and prior to contract award.

14 7. During the bidding process:
Bids may be discussed before the set time of their opening Subcontractors may not use Bid Depositories The Contractor should expect his potential Subcontractors to review those plans available in plan rooms. The bidder should be allowed to withdraw his bid before the specified time for receipt of bids.

15 7. During the bidding process:
Bids may be discussed before the set time of their opening Subcontractors may not use Bid Depositories The Contractor should expect his potential Subcontractors to review those plans available in plan rooms. The bidder should be allowed to withdraw his bid before the specified time for receipt of bids.