Presentation is loading. Please wait.

Presentation is loading. Please wait.

S. Bettoni for the CTF3 commissioning team CTF3 commissioning status

Similar presentations


Presentation on theme: "S. Bettoni for the CTF3 commissioning team CTF3 commissioning status"— Presentation transcript:

1 S. Bettoni for the CTF3 commissioning team CTF3 commissioning status

2 Outline CTF3 for CLIC Machine commissioning: 2008 milestones:
Combiner ring model improvement New lines in operation: TL2 TBTS CALIFES 2008 milestones: Factor 4 recombination demonstrated First drive beam in PETS (w/o and w recirculation) First probe beam Bunch length measurement: RF pickup Coherent diffraction Other topics: Steering algorithms Transient compensation The 2009 of CTF3 Conclusions

3 CLIC as a multiTeV collider
Basic features High acceleration gradient (100 MV/m) “Compact” collider - overall 3 TeV  50 km Normal conducting accelerating structures High acceleration frequency (12 GHz) Two-Beam Acceleration Scheme Cost effective, reliable, efficient Simple tunnel, no active elements Modular, easy energy upgrade in stages Drive beam A, 240 ns from 2.4 GeV to 240 MeV Main beam – 1 A, 160 ns from 9 GeV to 1.5 TeV 140 MW

4 CLIC Layout 3 TeV Main beam IP 48.4 km e+ injector, 2.4 GeV
e+ main linac e- main linac , 12 GHz, 100 MV/m, 21.1 km BC2 BC1 e+ DR 365m e- DR 365m booster linac, 9 GeV decelerator, 24 sectors of 878 m IP BDS km 48.4 km drive beam accelerator GeV, 1.0 GHz combiner rings Circumferences delay loop 72.4 m CR m CR m CR1 CR2 Delay loop 326 klystrons 33 MW, 139 ms 1 km 326 klystr 33MW TA R=120m 245m e+ PDR 365m e- PDR 365m 4.2A, 139 ms Drive beam generation complex 101A, 244 ns Main beam Main beam generation complex

5 CTF3: CLIC R&D Issues – WHERE?
Small scale version of the CLIC RF power source Provide the RF power to test the CLIC accelerating structures and components Full beam-loading accelerator operation Electron beam pulse compression and frequency multiplication Safe and stable beam deceleration and power extraction High power two beam acceleration scheme recombination x 4 recombination x 2 bunch length control bunch compression fully loaded acceleration PETS on-off structures 12 GHz 30 GHz two-beam acceleration deceleration stability phase-coding Structures Structure materials Drive Beam generation PETS on-off DB decelerator CLIC sub-unit

6 CTF3 status in the years 2004 2005 Linac DL CR 2006/7/8
Thermionic gun Linac DL CR 2006/7/8 D F F F D D D F D F F F D D D F F F D D D F F F D D D F F F D D D F F F D D D F F F D F D D D F F F D D D F F F D D F F F D D D F F F D D F F D D F D F F D D F F F D D D D D D F F F D D D D D F D D D F F F F F D D D D D F D D F D F F D D F F D D CLEX F D F F D D CTF2 CLEX building in 2006/7 30 GHz production (PETS line) and test stand Photo injector / laser tests from Oct. 2008 TL2 2008 Complete apart from TBL TL2, TL2’ installed

7 Main points of the commissioning
Delay loop: 2 x current multiplication by DL TL1: 3.5 A in TL1 Magnetic and RF injection in CR CR: Bad cabling quadrupoles Wrong BPM calibration Combined function magnets not properly modeled FAST VERTICAL INSTABILITY

8 The 2008 of CTF3 30 GHz DL & CR 30GHz only RUN 1 DL, CR, TL2 TBTS
Installation: TL2, CALIFES, TBTS Linac only Today RUN 2 Linac, Ring area, (CLEX) PETS in TBTS Installations CALIFES PETS CALIFES RUN 3

9 2008 CTF3 experimental program
1st run (April - June) Injector & Linac: establish stable & documented working point, automatic beam steering & steering algorithm studies, diagnostics consolidation, stability studies, EUROTeV BPMs Delay Loop: complete beam optics measurements (dispersion, orbit, kick measurements, matching), re-establish combination TL1 & combiner ring: complete optics studies (dispersion, closed orbit correction, matching, tunes, kick measurements, quad displacement evaluation, matching), tune and b function dependence of vertical instability, factor four combination with DL bypass (≥ 10 A) DL, TL1 & CR: factor 8 combination (≥ 15 A) 2nd run (July - September) Complete DL + CR, new RF deflectors (20 A ?) TL2 commissioning First CALIFES commissioning TBTS commissioning (no PETS) 3rd run (September - December) Complete above program Coherent Diffraction Radiation tests TBTS, PETS running in

10 2008 CTF3 experimental program
1st run (April - June) Injector & Linac: establish stable & documented working point, automatic beam steering & steering algorithm studies, diagnostics consolidation, stability studies, EUROTeV BPMs Delay Loop: complete beam optics measurements (dispersion, orbit, kick measurements, matching), re-establish combination TL1 & combiner ring: complete optics studies (dispersion, closed orbit correction, matching, tunes, kick measurements, quad displacement evaluation), tune and b function dependence of vertical instability, factor four combination with DL bypass (≥ 10 A) DL, TL1 & CR: factor 8 combination (≥ 15 A) 2nd run (July - September) New RF deflectors, Complete DL + CR (20 A ?) TL2 commissioning First CALIFES commissioning TBTS commissioning (no PETS) 3rd run (September October - December) Complete above program  First CALIFES commissioning Coherent Diffraction Radiation tests TBTS, PETS running in

11 Measurements in CTF3 Several measurements are performed in the machine to validate the optics models: Response matrix: High precision method Symmetric and multiturn kick (ring) Dispersion measurements Tune measurements Steering algorithms applied in the machine: Ring orbit correction Dispersion free steering (Linac) Bunch length measurement Transient compensation

12 Problem solved since September 2008
Gun instability Stable Unstable CTF3 Linac is fully loaded The energy transferred to the beam depends on the beam current Gun instability (HV fluctuations) The current is different shot to shot The energy gain is different shot to shot Position jitter in dispersive regions Set up and measurements VERY difficult Problem solved since September 2008

13 CTF3 commissioning status
Combiner ring CTF3 commissioning status

14 Combiner ring kick measurements
To maximize the precision of the measurement in the ring: The multiturn response matrix has been measured: easier to identify the discrepancies Symmetric kicks analysis: easier to identify a single quad error Several bugs found TURN 1 TURN 2 TURN 3

15 Combiner ring: correcting the bugs
Dispersion Combined function magnets (reused from EPA): New model of the combined magnets has been used The k1 strength has been lowered with respect to the one used in the EPA model Increase of the strength of the J-type quads Cross-cabled control units for quadrupoles power converter Tunes

16 Wiggler currents adjusted according to kick measurements
Tune measurements W/O correction Wiggler currents adjusted according to kick measurements W correction

17 Fast vertical instability disappeared!
current vertical horizontal Old deflectors BPM signals shoving vertical instability New deflectors BPM signals, no instability

18 CTF3 commissioning status
Transfer line TL2 large part done by RRCAT: Optics design Aluminium vacuum chambers Bending magnets CTF3 commissioning status

19 TL2 optics Module-3 Module-2 Module-1
Tunable R56 (from to +0.35) Achromatic arc Final matching doublet Module-2 Straight section for tail clipper CLEX-CR buildings not at the same height (achromat) Matching section Module-1 From CR extraction point to the first bend magnet (achromat) Beam direction For more details see “Optics design”, Amalendu Sharma et al., 2007 CTF3 collaboration meeting, Link

20 Beam setup in TL2 → Quad scan in CTS and tracking to the start of TL2
MTV TL1 LINAC CT DL CTS CR TL2 CLEX → Quad scan in CTS and tracking to the start of TL2 → Uncertainty on the initial conditions: → Error in the TL1/CR model → Small variations of the quads strength in the TL1/CR model → Error in the measurement propagated through TL1 and CR → New equipment to read the BP in the line: → Some problems at the beginning of the commissioning → Relatively strong optics → Since a certain time radiation alarm made operation in this area slow and annoying

21 TL2 status at the end of the year
Beam through TL2 → Uncertainty on the initial conditions: → Modified module-2 quads to compensate the possible different initial conditions → Found and corrected model-measurements discrepancies in CR (only during this shut down) → Installed MTV at the beginning of TL2 (during this shut down) → Greatly improved the BPs reading (interactions with LAPP people) → Relaxed optics searched → Discovered bug: → last quadrupole of the first triplet of module-2 had a maximum value lower than the read one (Loic) TL2 status at the end of the year BUT …

22 Kick measurements Kick 615 Kick 435 Kick 125 → Up to now NO huge discrepancies between the machine and the model found

23 During this shut-down the two exit chicanes were extended
For 2009 run improvements The operation of the machine was very tedious in the CR extraction zone because of radiation problems. DL TL1 CRM CR TL2 CLEX During this shut-down the two exit chicanes were extended Tail Clipper installed in TL2: It is made of kicker and dump that sits just above the beam It allows to regulate recombined train length The dump serves as a beam stopper to protect CLEX so It makes possible simultaneous operation of DL/CR and installations in CLEX

24 CLEX (CLIC Experimental area)
existing building D F F F D D D F D F F F D D D F F F D D D F F F D D D F F F D D D F F F D D D F F D F F D D D F F F D D D F F F D D F F F D D D F F F D D F F D F D D D D D F F F F F D D D D D D F D D D D F F F F F D D D D F D F F D D D D F D D F D F D F D D D F F D F D D F F F Test Beam Line TBL 42.5 m 8 m 2 m D F DUMP ITB 1.85m CALIFES Probe beam injector LIL - ACS 0.75 TBL 2.5m 22 m 2.0m 6 m 16.5 m TBTS 16 m TL2 ITB (not base-line) CALIFES Probe beam Two Beam Test Stand Probe Beam Everything installed, apart from TBL CTF3 commissioning status

25 PETS A fundamental element of the CLIC concept is two-beam acceleration, where RF power is extracted from a high-current and low-energy beam in order to accelerate the low-current main beam to high energy.

26 Drive beam generation scenarios
CTF3 #1 DL DBA CR CTF2 CLEX TBTS <30A CTF3 #2 Operation mode #1 #2 #3 CLIC Current, A < 30 14 4 101 Pulse length, ns 140 <240 <1200 240 Bunch Frequency, GHz 12 3 PETS power (12 GHz), MW <280 61 5 135 DL 14 A CR CTF2 TBTS CLEX CTF3 #3 To produce the CLIC nominal PETS power 22 A drive beam would be necessary. DL 4 A CR CTF2 CLEX TBTS

27 PETS with external re-circulation
The recirculation Variable Splitter (coupling: 01) Variable phase shifter To the Load PETS output Drive beam PETS input PETS with external re-circulation A fraction of the power going out from PETS is resent to the SAME PETS structure CLIC nominal 6.0 A Problem 2008 run: Splitter: stuck in undefined position (not remotely controllable) Phase-shifter: stuck in undefined position (not remotely controllable) 5.0 A 4.0 A 3.5 A 240 ns CLIC nominal R. Corsini, I. Syratchev

28 Beam in TBTS PETS story Total ~ 30 hours integrated conditioning time (15/11/2008 to 15/12/2008) Gradually increasing current arriving at PETS, up to ~ 5A, 11/12 14/11: First beam 2A w/ recirculation (by chance: positive build-up!) 21/11: Manually forces splitter to extreme position: no recirculation (to verify beam generated RF power) 28/11 : Adjusted phase-shifter : back to constructive recirculation mode

29 The recirculation: measurements
With the maximum current sent to PETS (~5 A) this year 30 MW power obtained instead of less than 5 MW! Power: PETS out, to load, reflected Corresponding pulse intensity^2 (the BPM before, and two first after PETS): E. Adli, R. Corsini, I. Syratchev

30 Very nice according of the modeling with the measurements
The recirculation: model/measurements Model (power) Measured (power) Measured (current) Very nice according of the modeling with the measurements E. Adli

31 CALIFES commissioning
D F DUMP 1.85m CALIFES Probe beam injector LIL-ACS TBL TBTS TL2’ Dec 1st Earlier the laser was used by PHIN The beam with laser pulse train of 100 ns length (150 bunches) 100% transmission through the 1st cavity Dec 8th Laser broken Measurements continued using the dark current 30th March Restart

32 Several steering algorithms have bee applied in the machine
→ Closed orbit correction (ring) → Dispersion free steering (Linac)

33 CR orbit correction algorithm
Best eps value iteratively determined: → Tolerance on the maximum allowed beam displacement and maximum value of the currents in the correctors for i = 1:n_max_step if i == 1 eps(i) = eps_start*fact; else eps(i) = eps(i-1)*fact; end [theta_s,thetap_s,corr_s,final_s,idec_s] = correction_1_mod(eps(i),RM',x_BP'); Curr_tot_s(i,:) = start_corr'+theta_s; Curr_tot_max(i) = max(abs(start_corr'+theta_s)); if abs(Curr_tot_max(i)) > max_I_corrs_tol fact = 1.1; x_max_exp = max(abs(x_BP+RM'*theta_s)); if x_max_exp < tol break fact = 0.9; Curr_tot = Curr_tot_s(end,:); e value Check and new e value

34 CR response matrix Orbit closure:
→ The response matrix is built using both the first and the second turn orbits Kick at corrector 242 Correctors Turn 1 Turn 2 BPM/BPI Kicks in the correctors to measure the response matrix: → The value of the kick in each corrector is determined according to the maximum tolerated losses in the last read BPM/BPI

35 CR orbit correction: the results
Inputs: → Tolerated maximum x-displacement = 4 mm → Maximum current in the correctors = 10 A → Maximum allowed losses = 10% Tolerance on the orbit correction limited by the incoming orbit jittering

36 Steering algorithms in the Linac
E. Adli → The CTF3 linac has been used as a facility of the TBL to test the Beam Based Alignment algorithm → Use this technique to steer the beam during the CTF3 linac operation Structure of the CTF3 linac (not to scale) → Studied algorithms: → All-to-all (A2A): steers the beam to get BPM zero-readings, by inverting the response matrix of the nominal machine optics → Dispersion free steering (DFS): minimizes (at the same time) of the orbit and the dispersion, using the responses corresponding to different optics: → Used responses: → Measured. Necessary to re-measure it each time the optics changes → Model-based. Nice model identification (BPM readings corrector strengths) necessary before

37 Steering algorithms in the Linac: the results
E. Adli Linac orbit after all-to-all correction A2A worked well A2A (measured response) → convergence after 2 iterations A2A (model response) → convergence after 4 iterations Comparison between results of Dispersion Free Steering and All-to-All DFS worked well Simulated BPM offset: A2A → residual dispersion ~ 15 mm DFS → residual dispersion of a factor 3 smaller

38 Bunch length measurements
H. Shaker, A. Dabrowski et al. M. Micheler et al. Use the radiation emitted by electrons passing close to a medium Standard RF deflector and novel RF pickup technique

39 Transient compensation
A. Dabrowski et al. 32 Tungsten plates (2mm thick) spaced by ~1mm Energy along the pulse measurement ΔP/P (%) Steady State High Energy Transient ~ 40 % > E0 Time (ns) Nominal RF settings ΔP/P (%) Steady State Transient compensation ~10% < E0 Time (ns) Adjusted RF arrival timing Electrons

40 Where is the drive beam? Phase coding recombination in DL DL CR
1.5 GHz DL CR D F CTF2 CLEX recombination in DL Beam all the way through CLEX Factor 4 recombination in CR

41 Where is the probe beam? CALIFES
Responsibility of IRFU (DAPNIA), CEA, Saclay Dark current Dark current K 10 20 25 25 beam dump quadrupoles 15 MV/m compression 17 MV/m acceleration 17 MV/m acceleration CALIFES

42 The 2009 of CTF3 Sections in operation Linac PHIN CALIFES DL & Ring
30 GHz TL2, TBL, TBTS (DB) CALIFES CLEX stop CALIFES TL2 TBTS TBL Delay Loop C. Ring

43 CTF3 commissioning status
DRIVE BEAM MODEL VALIDATION Gun instability disappeared Linac commissioned Delay loop factor 2 multiplication obtained Vertical instability in the combiner ring eliminated: factor 4 multiplication achieved TL2 commissioning started Beam in PETS: power produced w and w/o recombination MODEL VALIDATION Gun instability disappeared Linac commissioned Delay loop factor 2 multiplication obtained Vertical instability in the combiner ring eliminated: factor 4 multiplication achieved TL2 commissioning started Beam in PETS: power produced w and w/o recombination IN PARALLEL Steering algorithms (Linac and ring) Bunch length measurements Transient compensation PROBE BEAM First probe beam produced: CALIFES commissioning started Ultimate the commissioning of the new lines (TL2+CLEX lines) Put in operation DL and CR together to send ~30 A in PETS First acceleration of the probe beam CTF3 commissioning status

44 Extra slides

45 Delay loop principle double repetition frequency and current
parts of bunch train delayed in loop RF deflector combines the bunches

46 RF injection in CR Cring = (n + ¼) l
combination factors up to 5 reachable in a ring Cring = (n + ¼) l injection line septum local inner orbits 1st deflector 2nd deflector 1st turn lo RF deflector field 2nd 3rd lo/4 4rd

47 DL 2 1 Factor 2 in the delay loop achieved 3

48 Wiggler currents correction
W/O correction W correction CTF3 commissioning status

49 Tune measurements: the procedure
→ The measurement (oscilloscope + ”eyes”): → Fractional part of the tune determined from the Fourier transform of the H (V) signal in a BPM: → The sign is determined by the slope of the tune as a function of the quad strength variation → Compromise between oscillation amplitude and number of turns f MAIN QL QR I H V Nice reliability of the measurements Time consuming (H and V measurements can take also half a day) → The model comparison (automatic): → Scan of the tunes as a function of the current in a quads family → Scan over the energy range

50 Error in the CR model → For the several corrections of the TL1/CR model the TL2 behavior predicted by the model (TL2 nominal optics) sensibility.m

51 “Small” distributed errors (TL1+CR)
→ Random errors (gaussian mean = 0, s = 1% x INOM) in TL1 and half of CR generateErrors.m

52 But in any case … 04/12/2008

53 CTF3 commissioning status

54 The 2009 goals of CTF3 30 GHz: Two structure test (TM02) + breakdown studies CALIFES Beam characterization, beam to TBTS (most likely still reduced current) Delay Loop Back in operation, retrieve combination x 2 (~ 7 A) Combiner Ring Final optics checks, isochronicity, put together with DL (> 24 A) TL2 Complete commissioning, bunch length control, > 20 A transported to users TBTS PETS to nominal power/pulse length (15 A, recirculation) Beam commissioning of probe beam line First accelerating structure tests (one structure ? – CLIC G) Two-beam studies (deceleration/acceleration), initial breakdown kicks studies TBL PETS validation (100 MW, need > 20 A), beam line studies (2-3 PETS ?) PHIN Beam characterization, reach ½ of nominal bunch charge ? Others CDR studies in CRM, beam dynamics benchmarking, stability studies, control of beam losses…

55 End


Download ppt "S. Bettoni for the CTF3 commissioning team CTF3 commissioning status"

Similar presentations


Ads by Google