TPC Commissioning: DAQ, ECS aspects

Similar presentations


Presentation on theme: "TPC Commissioning: DAQ, ECS aspects"— Presentation transcript:

1 TPC Commissioning: DAQ, ECS aspects
Franco Carena Pierre Vande Vyvre 17 February 2006 TPC commissioning: DAQ, ECS

2 TPC commissioning: DAQ, ECS
Standalone run Required A DCS with SMI Finite State machines (FSM) FEE Triggered by LTU + TTC system Readout by DDL + DATE system Raw data with Event IDs from Trigger Control by a Detector Control Agent (DCA) The DCA for the TPC commissioning is ready 17 February 2006 TPC commissioning: DAQ, ECS

3 TPC commissioning: DAQ, ECS
17 February 2006 TPC commissioning: DAQ, ECS

4 TPC commissioning: DAQ, ECS
17 February 2006 TPC commissioning: DAQ, ECS

5 DAQ Hardware installed at Point 2
6 SIUs Fibre SXL2-CR1 20 fibers tested: - round-trip att. < 4 dB - one way 176 metres 2 + 1 LDCs Switch 1 GDC Local storage 2 TB RAID 5 RCU RCU RCU RCU PC SIU SIU SIU SIU SXL2 PC RCU RCU SIU SIU (control) HLT Farm PX24/CR2 General Purpose Network (GPN) 4 x DRORC 2 x DRORC DRORC LDC LDC LDC Event Building Network (Gigabit Ethernet) PX24/CR1 GDC Server Network Gateway HW available for 2 sectors: 12 SIUs 12 DRORCs 12 DIUs (DATE, ECS) TDS 17 February 2006 TPC commissioning: DAQ, ECS

6 TPC commissioning: DAQ, ECS
Calibration runs Meeting about TPC/TRD FERO Control 31-Jan-06 The TPC requires several different types of calibration runs: Pedestal taking Pulser calibration Laser calibration Krypton calibration All the above calibration procedures must be Defined: sequence of operations Implemented: 1 (set of) program(s) for each operation Included in the DCA: procedure steering the execution of the operations. Implemented as a FSM coded in SMI. 17 February 2006 TPC commissioning: DAQ, ECS

7 An example: pedestal calculation
Consists of the following operations: Set FEE to ‘pedestal mode’ Done using the DCS Data taking (DAQ+LTU) Recording on local LDC disk No event building Compute pedestal on every LDC Pedestal can be stored immediately or later in database to be loaded via DDL or DCS Set FEE to ‘normal mode’ The implementation of a pedestal run requires work in the TPC-DCS 17 February 2006 TPC commissioning: DAQ, ECS

8 TPC-DCS without pedestal mode
STANDBY GO_STANDBY CONFIGURE STDBY_CONFIGURED STOP CONFIGURE GO_READY READY 17 February 2006 TPC commissioning: DAQ, ECS

9 TPC-DCS with pedestal mode
STANDBY GO_STANDBY CONFIGURE STDBY_CONFIGURED END_PEDESTAL_MODE STOP CONFIGURE SET_PEDESTAL_MODE GO_READY READY PEDESTAL_MODE 17 February 2006 TPC commissioning: DAQ, ECS

10 Next steps for calibrations
Name of a person responsible for TPC calibrations This person defines every calibration procedure: Sequence of operations Building blocks (programs, who provides them) The ECS team implements the logic to steer the calibration procedure (commands sent to DCS, DAQ, LTU) The building blocks are provided by the TPC team Tests and debugging 17 February 2006 TPC commissioning: DAQ, ECS