Presentation is loading. Please wait.

Presentation is loading. Please wait.

Further Testing – April 10, 2011

Similar presentations


Presentation on theme: "Further Testing – April 10, 2011"— Presentation transcript:

1 Further Testing – April 10, 2011

2 Operational Ballast Trial Initial Conditions Met Video Feed Register
Time To Sink (s) Depth (ft) Level Submarine Resurface Watertight Central Hull Pass/ Fail 1 Yes None 741 3 No Fail 2 747 740

3 Operational Ballast Volume Of Submarine: 41968.25056 mL
Mass Of Submarine: g Initial Density: kg/L Initial Buoyancy: N Density At Submersion: kg/L Buoyancy At Submersion: N Change In Volume Through Submersion: L Change In Buoyancy Through Submersion: Percent Of Ballast Tanks Filled With Water To Submerge: %

4 Propelled Neutral Buoyancy
Dove underwater but did not attain neutral buoyancy Inclined dive due to center of mass alignment

5 Stationary Neutral Buoyancy
Dove underwater but did not attain neutral buoyancy Inclined dive due to center of mass alignment

6 Three Degrees Of Freedom
Dove underwater but did not attain neutral buoyancy Inclined dive due to center of mass alignment

7 Waterproof Test Purpose Procedure Expected results Results
To test the central hull and ballast tanks for leaks. Avoid electrical damage Procedure Hold submarine vertically Insert into water layer by layer, noting where water leaked Expected results No leaks Results One leak was found on the viewport

8 Test Conclusions Inclined dive cannot be righted
Still not waterproof although significant improvement shown

9 Refining Epoxy over front porthole for sealing
A 45 pound weight was added to the submarine Realigns center of mass with center of buoyancy Drastically alter initial density Requires less water in ballast system to submerge Less water weight in the ballast system will stop the system from performing a torque as easily Faster sink time

10 Final Testing – April 22, 2011

11 Operational Ballast Trial Initial Conditions Met Video Feed Register
Time To Sink (s) Depth (ft) Level Submarine Resurface Watertight Central Hull Pass/ Fail 1 Yes None 293 8.0 No Part. Pass 2 295 3 290

12 Operational Ballast Volume Of Submarine: 44804.35156 mL
Mass Of Submarine: g Initial Density: kg/L Initial Buoyancy: N Density At Submersion: kg/L Buoyancy At Submersion: N Change In Volume Through Submersion: L Change In Buoyancy Through Submersion: Percent Of Ballast Tanks Filled With Water To Submerge: %

13 Operational Ballast

14 Operational Ballast

15 Operational Ballast

16 Operational Ballast

17 Propelled Neutral Buoyancy
Dove underwater but did not attain neutral buoyancy Inclined dive due to center of mass alignment

18 Stationary Neutral Buoyancy
Dove underwater but did not attain neutral buoyancy Inclined dive due to center of mass alignment

19 Three Degrees Of Freedom
Dove underwater but did not attain neutral buoyancy Inclined dive due to center of mass alignment

20 Test Conclusions Adding the weight did not help keep the submarine from inclining Waterproofing was finally successful Voltage drop is too great for the receiver extension wire

21 Future refinements Trim tanks Some other form of ascension
Propeller Placement

22 Lessons Learned (Randy)
Unforeseen Problems Construction Physics Importance of calculations

23 Lessons Learned (Grant)
Water can be hard to seal out Fiberglass is a mess Dust Off does not taste good Center of Mass means a lot Physics does exist Calculus has a practical application Remote control can be unpredictable Spare at least as much time in refinement as you do your original prototype Do it right the first time

24 Lessons Learned (David)
Water is a challenge Importance of physics concepts Do not procrastinate Calculus has a purpose

25 Summary The submarine did not achieve all that it was set out to do, but gave it a good shot Physics and calculus are used before you design something It can be hard to make all systems run simultaneously Test for waterproofing by parts not the full submarine at once This was the most productive and eventful work team and project in the Academy due to our past experiences


Download ppt "Further Testing – April 10, 2011"

Similar presentations


Ads by Google