LIU / HL-LHC Cost and Schedule Review

Similar presentations


Presentation on theme: "LIU / HL-LHC Cost and Schedule Review"— Presentation transcript:

1

2 LIU / HL-LHC Cost and Schedule Review
17-19 October 2016 17-19 October 2016

3 LIU-PSB Table of contents: Outcomes of the Cost and Schedule review
Klaus Hanke, Bettina Mikulec, Gian Piero Di Giovanni, LIU-PSB Working Group Table of contents: Outcomes of the Cost and Schedule review Baseline beam parameters Machine layout Status of work progress Mandatory CONSolidation items Risks and mitigation Budget, manpower, EVM Schedule 17-19 October 2016 LIU / HL-LHC Cost and Schedule Review LIU-PSB : Klaus Hanke - BE/OP

4 March 2015 : Outcomes of the Cost and Schedule review
Findings The goal for the PSB upgrade is to produce higher brightness beams to match the HL-LHC requirements. This will also allow higher beam intensities for non-LHC beams. The LIU-PSB contains two parts: connection of the PSB with LINAC4 and 2 GeV energy upgrade of the PSB of the extraction energy. The cost of PSB is reasonable, since all the elements are standard or similar to existing equipment. Power converters are the biggest fraction of the budget of PSB. Comments The cost estimates are largely based on existing equipment and are well founded It is difficult to reduce cost through scope reduction. The beam instrumentation considered for scope reduction is essential for efficient commissioning after LINAC4 connection and PSB 2 GeV upgrade. High schedule risk due to a 5 month overload for installation during LS2. Removal of unused old cables at the PSB is a high priority and needs to be started as soon as possible. Recommendations Schedule removal of old cables at the PSB as soon as possible Start installation of equipment for the PSB upgrade as soon as possible to alleviate the schedule problem during LS2 17-19 October 2016 LIU / HL-LHC Cost and Schedule Review LIU-PSB : Klaus Hanke - BE/OP

5 2016 Beam Parameter** Table
Standard scheme N (x 1011p/b) e (mm) Bl(ns) Number of bunches PSB/ring 34.2 1.7 650 1 PS 32.5 1.8 205 4 + 2 SPS 2.6 1.9 3.0 4 x 72 LHC 2.3 2.1 1.6 10 x 288 ** In each machine beam parameters are given at injection and after RF capture LHC Injectors Upgrade (LIU) Project Description, LIU-PM-RPT-0015 17-19 October 2016 LIU / HL-LHC Cost and Schedule Review LIU-PSB : Klaus Hanke - BE/OP

6 25 ns Beam Performance 17-19 October 2016 LIU / HL-LHC Cost and Schedule Review LIU-PSB : Klaus Hanke - BE/OP

7 LIU-PSB activities EYETS 2016-2017
Vers PS Renovate electronics for 4 BR.BCTDC (section 9) 4 New monitors BR.TMD (8L1) New ring Trajectory Measurement System (PSB-TMS) New BLMs (FIC detectors) New prototype wire Scanner BWS (4L1) New Tune pick-up BPM (3L1) Exchange Septum SMH (15L1) New kicker KSW (16L1) Replace kicker KSW (16L4) Move kicker KSW (from 16L4 to 2L1) Relocate Monitor BTV (BT.BTV30) Enlargement of the shaft New wideband electrostatic pick-up BPM (BTP.BPMW15) 17-19 October 2016 LIU / HL-LHC Cost and Schedule Review LIU-PSB : Klaus Hanke - BE/OP

8 LIU-PSB activities YETS 2017-2018
Vers PS New SEMGrid (4L1 ring 3) 17-19 October 2016 LIU / HL-LHC Cost and Schedule Review LIU-PSB : Klaus Hanke - BE/OP

9 LIU-PSB activities LS2 Vers PS New Absorber/Scraper Under studies: Change of the beam stoppers New vacuum window before the PSB Dump New Wire Scanner x4 (11L1) New RF bypasses Laminated side plate on bending (BHZ MAIN) Parallel shunt resistors on quadrupoles (QDE, QFO) and bending (BHZ MAIN) magnets Transverse Feedback New interlock system PSB extraction to PS New finemet cavities BR2&4.C02 7L1 BRr.C04 13L1 BR.C16.5L1 New Wire Scanner x3 (4L1) New extraction kicker (BEr.KFA14L1) New PSB Injection Region Remove the current sector (1L1) New H- charge exchange injection systems PSB Injection Systems: New Injection bending (BHZ INJ) New Distributor (BI.DIS10) New Septa (BI.SMV10) Relocate beam instrumentation (BI.BTV30) Change of the magnets PSB Extraction and Transfer: New BHZ EXT New septum (BT.SMV10 and BT.SMV20) Relocate beam instrumentation (BT.BTV10) New kicker (BT.KFA10) Change the magnets 17-19 October 2016 LIU / HL-LHC Cost and Schedule Review LIU-PSB : Klaus Hanke - BE/OP

10 Cost to Completion (Material + M to P) [kCHF]
LIU-PSB Top 10 WPs Workpackage Description Cost to Completion (Material + M to P) [kCHF] LIU-PSB 5 Power Converters 21,435 LIU-PSB 4 RF systems 13,281 LIU-PSB 9 LINAC4 to PSB transfer line and PSB injection systems 7,752 LIU-PSB 6 Beam  instrumentation 3,755 LIU-PSB 15 Civil Engineering 3,266 LIU-PSB 10 PSB Extraction system and PSB-PS transfer line 3,045 LIU-PSB 3 Magnets 2,956 LIU-PSB 12 Electrical Systems 2,718 LIU-PSB 13 Cooling and Ventilation 2,351 LIU-PSB 8 Vacuum System 1,768 LIU-PSB 14 Installation, Transport and handling 1,015 LIU-PSB 23 Half-Sector Test Project + Stripping Foil Test 900 LIU-PSB 7 Beam Intercepting Devices 803 LIU-PSB 1 Management 536 LIU-PSB 11 Controls 330 LIU-PSB 17 Interlock systems 244 LIU-PSB 21 Commissioning and Operation 145 LIU-PSB 20 Survey 48 LIU-PSB 2 PSB Beam dynamics 35 Total 66,380 17-19 October 2016 LIU / HL-LHC Cost and Schedule Review LIU-PSB : Klaus Hanke - BE/OP

11 Progress on individual equipment / System (top 10)
Equipment / Systems Activity Description Status Due date (EYETS, YETS, LS2) power converters (21,435 kCHF) injection power supplies 2 GeV Main Power supply other pc for 2 GeV upgrade all ready procurement started on schedule for LS2 EYETS LS2 RF systems (13,281 kCHF) new wideband RF cavities new LL RF system successful tests with prototypes; reviewed procurement in progress mainly deployed LS1 PSB injection systems (7,752 kCHF) new hardware for distribution to 4 rings, new chicane and painting bumpers, foil mover, powering, vacuum and instrumentation mock-up, stripping foil test and HST in progress EYETS/ 17-19 October 2016 LIU / HL-LHC Cost and Schedule Review LIU-PSB : Klaus Hanke - BE/OP

12 Progress on individual equipment / System (top 10)
Equipment / Systems Activity Description Status Due date (EYETS, YETS, LS2) beam instrumentation (3,755 kCHF) specific injection diagnostics PSB rings: new orbit system, new wire scanners, turn by turn profile measurement commissioning (Half Sector Test HST) procurement, prototyping EYETS LS2 and before civil engineering (3,266 kCHF) bldg. 245 alcove for BSW (bumper) transformers handed over, safety assessment ongoing crash program before LS2 2 GeV extraction and transfer (3,045 kCHF) upgrade/replacement of kickers and septa design/procurement/production all on track LS2 17-19 October 2016 LIU / HL-LHC Cost and Schedule Review LIU-PSB : Klaus Hanke - BE/OP

13 Extraction Systems KFA14L1 - Horizontal Extraction Kicker
BESMH - Horizontal Extraction Septum KFA10 kicker – Vertical recombination 4 to 2 SMV10 septum – Vertical recombination 4 to 2 KFA20 kicker – Vertical recombination 2 to 1 SMV20 – Vertical recombination 2 to 1 17-19 October 2016 LIU / HL-LHC Cost and Schedule Review LIU-PSB : Klaus Hanke - BE/OP

14 Progress on individual equipment / System (top 10)
Equipment / Systems Activity Description Status Due date (EYETS, YETS, LS2) magnets (2,956 kCHF) modifications main magnets injection magnets large 2 GeV bends other extraction magnets on schedule for LS2 all ready LS2 EYETS electrical systems (2,718 kCHF) de-cabling new cable requests racks and infrastructure cables identified, ready to go all requests collected, budget determined and allocated new rack space created EYETS, LS2 17-19 October 2016 LIU / HL-LHC Cost and Schedule Review LIU-PSB : Klaus Hanke - BE/OP

15 Cable Clean-Up ~1800 new cables for LIU – no more space on cable trays
cable clean-up in stages: 2014/15: identification of obsolete cables - done YETS 2015/16: disconnection of obsolete cables – done only one problem encountered during re-start! 3. EYETS 2016/17: cable removal de-cabling and re-cabling of presently not obsolete cables remain to be done in LS2 (or in case of an early Linac4 connection) 17-19 October 2016 LIU / HL-LHC Cost and Schedule Review LIU-PSB : Klaus Hanke - BE/OP

16 New Rack Space 2015 2016 rack support structures in place
storage space cleared new false floor in place 2016 17-19 October 2016 LIU / HL-LHC Cost and Schedule Review LIU-PSB : Klaus Hanke - BE/OP

17 New Rack Space 17-19 October 2016 LIU / HL-LHC Cost and Schedule Review LIU-PSB : Klaus Hanke - BE/OP

18 Due date (EYETS, YETS, LS2)
Progress on individual equipment / System (top 10) Equipment / Systems Activity Description Status Due date (EYETS, YETS, LS2) cooling & ventilation (2,351 kCHF) bldg. 245 (2 GeV MPS) PSB cooling station contract signed design being finalised before LS2 LS2 vacuum system (1,768 kCHF) contributor to all other items all on track EYETS-LS2 17-19 October 2016 LIU / HL-LHC Cost and Schedule Review LIU-PSB : Klaus Hanke - BE/OP

19 Progress Status Summary
Equipment / Systems March 2015 status October 2016 status Remarks power converters POPS-B procurement injection power supplies ready assessment after POPS incident RF tests with prototype cavity reliability run done reviewed and full installation decided for LS2 all on track injection systems on track for end 2016 ready baseline: LS2 ready for early L4 connection 17-19 October 2016 LIU / HL-LHC Cost and Schedule Review LIU-PSB : Klaus Hanke - BE/OP

20 Injection Systems new vertical distribution septum new distributor
bumper magnets foil mover 17-19 October 2016 LIU / HL-LHC Cost and Schedule Review LIU-PSB : Klaus Hanke - BE/OP

21 Half-Sector Test (HST)
HST installation completed in Linac4 transfer line; waiting for first 160 MeV H- beam helped already discovering a few design and fabrication issues will reduce technical and planning risks for installation and commissioning Stripping foil test stand Stripping foil system Chicane magnets + H0/H- dump Temporary dump permanent installation of stripping foil test stand in Linac4 line to Linac4 dump completed  evaluation of stripping foils and system 17-19 October 2016 LIU / HL-LHC Cost and Schedule Review 17-19 October 2016 LIU / HL-LHC Cost and Schedule Review LIU-PSB : Klaus Hanke - BE/OP LIU-PSB : Klaus Hanke - BE/OP

22 First Beam on Stripping Foil Test Stand 13 October
50 MeV H- beam from Linac4 view screen stripping foil 17-19 October 2016 LIU / HL-LHC Cost and Schedule Review LIU-PSB : Klaus Hanke - BE/OP

23 Injection Review September 2016
The Linac4-PSB connection readiness was reviewed in September 2016 in order to derive a comprehensive, detailed plan and list the associated risks. This could happen in case of a major LHC break-down which would open a time window long enough to do this Conclusions: all Linac4-PSB equipment is ready for a connection as from spring 2017 critical items are no show stoppers connection could be done in (6 +3) months Half Sector Test is extremely important, as well as the Linac4 reliability Run, which is endorsed 17-19 October 2016 LIU / HL-LHC Cost and Schedule Review LIU-PSB : Klaus Hanke - BE/OP

24 Progress Status Summary
Equipment / Systems March 2015 status October 2016 status Remarks beam instrumentation number of items still in design phase Linac4 related diagnostics ready and being tested (HST) otherwise on track for LS2 or earlier commissioning of diagnostics before LS2 where possible on track civil engineering bldg. 245 under construction bldg. 245 handed over safety assessment ongoing some other activities 17-19 October 2016 LIU / HL-LHC Cost and Schedule Review LIU-PSB : Klaus Hanke - BE/OP

25 POPS-B Building 245 completed
Converter hall False floor Loading platform 17-19 October 2016 LIU / HL-LHC Cost and Schedule Review LIU-PSB : Klaus Hanke - BE/OP

26 Progress Status Summary
Equipment / Systems March 2015 status October 2016 status Remarks extraction systems and transfer line design phase procurement / manufacturing on track magnets procurement ongoing, on track electrical systems cable inventory being set up identification of obsolete cables cable inventory complete, DICs and DECs submitted, budget settled and transferred to EL code (all TIDs done) clean up for 2016/17 EYETS 17-19 October 2016 LIU / HL-LHC Cost and Schedule Review LIU-PSB : Klaus Hanke - BE/OP

27 Progress Status Summary
Equipment / Systems March 2015 status October 2016 status Remarks cooling & ventilation cooling inventory being set up cooling inventory complete ventilation specs being compiled contract for bldg. 245 signed on track vacuum system contributing to all other activities 17-19 October 2016 LIU / HL-LHC Cost and Schedule Review LIU-PSB : Klaus Hanke - BE/OP

28 Documentation & Reviews
LIU-PSB counts 65 documents released since 2015, including ECRs internal assessment of L4 connection readiness / internal review PSB-PS transfer line second full Finemet review internal review beam intercepting devices Linac4 connection readiness review 17-19 October 2016 LIU / HL-LHC Cost and Schedule Review LIU-PSB : Klaus Hanke - BE/OP

29 Major Baseline Changes
Equipment / Systems Description Status RF full replacement of all ferrite cavities including C16 by wide band Finemet system (before plan was to replace C02/C04 only) reviewed and approved remains within cost envelope C&V separation of the TT2 cooling from the PSB (more logical architecture, more operational flexibility) cost neutral for LIU (some cost for CONS), approved no change of CtC 17-19 October 2016 LIU / HL-LHC Cost and Schedule Review LIU-PSB : Klaus Hanke - BE/OP

30 Finemet© Baseline Finemet© review September 2015 approved replacement of all 3 present cavity systems with Finemet© Test with ring 4 prototype cavity proved that Finemet© was suitable: As an h=1 C02 replacement from 600 kHz-1.8 MHz As an h=2 C04 replacement from 1.2 MHz-3.6 MHz As a C16 replacement from 6-16 MHz for longitudinal blow-up It could be used as a combined h=1 & h=2 replacement by splitting the available voltage between the harmonics Group of 4 superposed cavity couples in one PSB section 10-cell prototype MA cavity in PSB ring 4 17-19 October 2016 LIU / HL-LHC Cost and Schedule Review LIU-PSB : Klaus Hanke - BE/OP

31 Mandatory CONSolidation activities for LIU-PSB
Equipment / Systems Description Risks if not done Due date PSB cooling plant full renovation reliability issue, non conformities LS2 CONS budget rack supports old racks are sitting on false floor safety non-conformity mainly EYETS cable clean up removal of obsolete cables LIU installations not possible EYETS handling tools consolidate overhead cranes LIU installations not possible; delays LS1 (done) A number of high-cost CONS items (RF, Power) have been integrated in the LIU baseline at the beginning of the project 17-19 October 2016 LIU / HL-LHC Cost and Schedule Review LIU-PSB : Klaus Hanke - BE/OP

32 Risks summary Equipment / System Risks Risk Level class Mitigation
POPS-B building assessment after POPS incident schedule: 4 m  high but OK for LS2 cost: 120 kCHF  low complete assessment and implement mitigation measures POPS-B power supply same technology as POPS cost: 500 kCHF issues are understood and mitigation measures put in place 17-19 October 2016 LIU / HL-LHC Cost and Schedule Review LIU-PSB : Klaus Hanke - BE/OP

33 Overall Cost to Completion
Systems 2015 CtC [kCHF] 2016 CtC [kCHF] Comments Grand total LIU-PSB 67,339 66,380 17-19 October 2016 LIU / HL-LHC Cost and Schedule Review LIU-PSB : Klaus Hanke - BE/OP

34 Cost to Completion Variation
WP Description 2015 CtC [kCHF] 2016 CtC [kCHF] Delta [kCHF] Comments LIU-PSB 12 Electrical Systems 2,091 2,718 627 mostly DC cabling LIU-PSB 13 Cooling and Ventilation 1,762 2,351 589 full inventory and costing done LIU-PSB 5 Power Convertors 20,850 21,435 585 LIU-PSB 6 Beam instrumentation 3,358 3,755 397 tune pick-up, turn by turn LIU-PSB 8 Vacuum System 1,494 1,768 274 LIU-PSB 7 Beam Intercepting Devices 544 803 258 BI beam stopper LIU-PSB 9 LINAC4 to PSB transfer line and PSB injection systems 7,614 7,752 138 LIU-PSB 14 Installation, Transport and handling 953 1,015 62 LIU-PSB 20 Survey 40 48 8 LIU-PSB 2 PSB Beam dynamics 34 35 1 17-19 October 2016 LIU / HL-LHC Cost and Schedule Review 17-19 October 2016 LIU / HL-LHC Cost and Schedule Review LIU-PSB : Klaus Hanke - BE/OP LIU-PSB : Klaus Hanke - BE/OP 34

35 Cost to Completion Variation
WP Description 2015 CtC [kCHF] 2016 CtC [kCHF] Delta [kCHF] Comments LIU-PSB 21 Commissioning and Operation 145 LIU-PSB 1 Management 539 536 -3 LIU-PSB 17 Interlock systems 256 244 -12 LIU-PSB 11 Controls 364 330 -34 LIU-PSB 10 PSB Extraction system and PSB-PS transfer line 3,082 3,045 -37 LIU-PSB 15 Civil Engineering 3,325 3,266 -59 LIU-PSB 23 Half-Sector Test Project + Stripping Foil Test 1,016 900 -116 reduced cost of BI equipment LIU-PSB 3 Magnets 3,720 2,956 -764 below initial estimates LIU-PSB 4 RF systems general services 13,202 2,950 13,281 79 -2,950 wrongly allocated to LIU-RF 4 and transferred in 2016 to general services WPs Total 67,339 66,380 -959 17-19 October 2016 LIU / HL-LHC Cost and Schedule Review 17-19 October 2016 LIU / HL-LHC Cost and Schedule Review LIU-PSB : Klaus Hanke - BE/OP LIU-PSB : Klaus Hanke - BE/OP 35

36 EVM Metrics 17-19 October 2016 LIU / HL-LHC Cost and Schedule Review
SV = -3,567 kCHF AC = -164 kCHF [1] Schedule Variance (SV) = Earned Value (EV) – Planned Value (PV) [2] Cost Variance (CV) = Earned Value (EV) – Actual Cost (AC) 17-19 October 2016 LIU / HL-LHC Cost and Schedule Review 17-19 October 2016 LIU / HL-LHC Cost and Schedule Review LIU-PSB : Klaus Hanke - BE/OP LIU-PSB : Klaus Hanke - BE/OP 6

37 EVM Metrics In kCHF Comment Schedule Variance -3,567 BE-BI: Cables and electronics for beam loss monitors not yet delivered (new electronics not yet validated). SV = -500 kCHF. BE-CO: Control infrastructure: hardware for LS1 and LN4 signals not yet purchased. SV = -120 kCHF. BE-RF: Amplifiers, cavities and ancillaries production for RF consolidation not yet started. SV = -500 kCHF. TE-ABT: Foil handling system (mechanical parts & vacuum equipment) not linear: only 2 sets over 8 (WU from Jun-15 to Nov-16); BI.BSW magnets: reporting by unit, not all components received (vacuum chambers, coils, yokes) and assembly not yet started; delays in the purchase of prototype hardware for electronics and controls for kickers. SV = -1,150 kCHF. TE-EPC: Transformer and strip line for booster injection septa converters not yet purchased; booster injection stripping foil chicane converters series assembly and tests not yet started; delays in the delivery of 20 kA, 6kA and 3.4 current transducers; LHC600A-40V power racks and modules for booster injection not started; power cables for booster MPS not yet purchased. SV = -950 kCHF. Cost Variance -164 TE-ABT: Components for foil handling systems and BI.BSW magnets received but not reported as general reporting by unit. CV = -400 kCHF. EN-EL: delays between the commissioning of equipment and the payment of the invoice. CV = +300 kCHF. 17-19 October 2016 LIU / HL-LHC Cost and Schedule Review LIU-PSB : Klaus Hanke - BE/OP

38 Manpower bottleneck with expert manpower in beam dynamics
fellows are essential for the overall work progress FTE 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 Total Staff 9.7 18.2 32.8 34.5 39.3 40.9 39.7 38.2 48.1 44.2 6.3 351.9 Fellows 0.4 2.8 4.2 3.6 8.6 10.1 6.5 2.0 1.0 40.2 MPA 0.6 0.3 0.0 4.1 1.5 2.1 9.6 10.7 21.3 37.0 39.1 52.0 52.5 48.3 49.1 45.2 401.7 17-19 October 2016 LIU / HL-LHC Cost and Schedule Review 17-19 October 2016 LIU / HL-LHC Cost and Schedule Review LIU-PSB : Klaus Hanke - BE/OP LIU-PSB : Klaus Hanke - BE/OP

39 Master Schedule Evolution of the main master schedule
the estimation time for the beam commissioning has been detailed on the master schedule. the long shutdown 2 has been postponed by 6 months and extended by 6 months. March 2015 EYETS YETS LS2 October 2016 LS2 17-19 October 2016 LIU / HL-LHC Cost and Schedule Review LIU-PSB : Klaus Hanke - BE/OP

40 Summary / Major upcoming Milestones
project well on track base line stable, no major changes cost risk classification (1) confirmed major work/procurement ongoing; ramping up expenses next milestone EYETS 2016/17:cable clean-up, number of installations (e.g. beam instrumentation) important results of the Half Sector Test to come 17-19 October 2016 LIU / HL-LHC Cost and Schedule Review LIU-PSB : Klaus Hanke - BE/OP

41

42 Spare Slides 17-19 October 2016 LIU / HL-LHC Cost and Schedule Review
LIU-PSB : Klaus Hanke - BE/OP

43 Evolution of EVM Planned Value
17-19 October 2016 LIU / HL-LHC Cost and Schedule Review LIU-PSB : Klaus Hanke - BE/OP

44 Lessons from POPS Incident
Modification of B245. Delay in planning: two months (additional 4 months for building the power converters was announced (LIU-PSB Meeting 175  07 June 2016). Delay inside the margin of the project planning. In case of particular issues 50% of that will not be recovered. Additional costs: <120kCHF (less than 5% of the cost of the Building) Problem occurred in POPS: Delay in planning: four months (known problems have been understood and solution for POPS container is under design-construction for EYETS. Nevertheless testing of the power converter protections may go wrong and oblige to step back) Additional costs: < 500kCHF (10% of the cost of the power converters) 17-19 October 2016 LIU / HL-LHC Cost and Schedule Review LIU-PSB : Klaus Hanke - BE/OP

45 POPS experience feedback on POPS-B
POPS experience feedbacks: Reduce the fault energy in case of capacitor short circuit Improve design of capacitors with ageing tests Improve design of capacitor room following explosion analysis Study alternative protections in the power converter Build an off-line testing platform 17-19 October 2016 LIU / HL-LHC Cost and Schedule Review LIU-PSB : Klaus Hanke - BE/OP

46 POPS experience feedback on POPS-B
POPS experience feedbacks: Reduce the fault energy in case of capacitor short circuit Limit damages to ¼ of the capacitors Fuses blown very quick strongly limiting the energy losses Implementation ongoing for POPS 17-19 October 2016 LIU / HL-LHC Cost and Schedule Review LIU-PSB : Klaus Hanke - BE/OP 46

47 POPS experience feedback on POPS-B
Additional tests to prove resistance to short circuit POPS experience feedbacks: Improve design of capacitors with ageing tests Ageing + discharge tests shall be completed by October 2016 2 x 720 h left 370 h left 600 h left Removed for film analysis 17-19 October 2016 LIU / HL-LHC Cost and Schedule Review LIU-PSB : Klaus Hanke - BE/OP

48 POPS experience feedback on POPS-B
POPS experience feedbacks: Improve design of capacitor room following explosion analysis Pressure wave calculation Effects on the structure PO for consultancy to be released in the next days (60kCHF) Possible remedies (POPS) 17-19 October 2016 LIU / HL-LHC Cost and Schedule Review LIU-PSB : Klaus Hanke - BE/OP

49 POPS experience feedback on POPS-B
Fast DC circuit breaker POPS experience feedbacks: Study alternative protections in the power converter Build an off-line testing platform Check repair before restarting Design ongoing 17-19 October 2016 LIU / HL-LHC Cost and Schedule Review LIU-PSB : Klaus Hanke - BE/OP