LCLS Klystron Modulator AIP Sec 28 AIP Review Feb 2010

Similar presentations


Presentation on theme: "LCLS Klystron Modulator AIP Sec 28 AIP Review Feb 2010"— Presentation transcript:

1 LCLS Klystron Modulator AIP Sec 28 AIP Review Feb 2010
Briant Lam and Ben Morris

2 Project Description Refurbish Sector 28 klystron modulators to demonstrate improvements to the safety and reliability of the 6575s that will enhance LCLS Safety: Segregate electrically hazardous circuits Control electronics in “touch safe” enclosures Reliability: Replacing obsolete and problematic relay logic control system with a modern PLC Redesign high failure components Internal voltage regulation, alternative to VVS

3 Prototype Status Construction completed
Testing began with water load in B015 in November, continuing today

4 B015 Testing Status Run at 21.5kV & 30Hz, several hours of operation
Validate higher rep rate (limited power) Finalize documentation

5 Prototype: – April 2010 Production: May – Sept. 2010 Schedule
Complete B015 testing: 3/19 Install at 28-1: 3/30 Design validation (full power testing): 4/30 Production: May – Sept. 2010 Contingent upon completion of documentation and finishing validation of prototype unit: 5/3 No contingency to order long lead parts: now Modulator production rate: 3 weeks/modulator Sector 28 complete: 9/30 (22 weeks)

6 Cost Project Budget: $441k Cost to Date (-1/10) Cost to Complete
$362k for ED&I and B&H ED&I cost overrun Cost to Complete Prototype & documentation (ED&I): $20k Production (B&H) Seven modulators M&S: $20k/modulator (8% G&A assumed) Labor: $12.5k/modulator (53% G&A assumed) Total: $227k Total cost-to-complete: $247k

7 Cost Budget Actual ED&I 2010-Jan $272k Cost to complete $20k Total
B&H $90k $227k $230k $317k ($87) Contingency $88k Total Cost $441k $609k ($168)

8 Budget Overruns Issues ED&I B&H Contingency: enough for B&H overruns
Assumed very little engineering development when in reality considerably more was needed B&H PLC costs: $1k estimate vs. $10k actual (EPICS) Contingency: enough for B&H overruns

9 Change Scope Increase Funding Potential Solutions
Existing funding sufficient to complete prototype and two production units Limited statistical sample to evaluate efficacy of improvements with only 3 units in operation Increase Funding Additional $168k allocation in FY10 Complete S28 by end of FY10 Defer additional $168k allocation until FY11 Finish prototype, build remaining 2 in FY 2010 Complete remaining 5 units during FY11-Q1 Limited delay in amassing operational data