EA Renovation –EATM– 15.08.2017 Project status
East Hall under construction EA Renovation –EATM– Project status S. Evrard – EN-EA, on behalf of the Project Team
2
AGENDA PLAN Civil Engineering: IT preparation
RP Assessment for the Civil Engineering Works Risk Analysis Schedule Upgrade of EN-EA equipment Primary dump for T9-T10-T11 S.Evrard, EATM
3
PLAN: overview DASHBOARD EDMS 1739802 12.06.2017 PLAN TOOL Level 1
Level 1 Responsible Group Plan ID EAR 1 Management S. Evrard, M. Lazzaroni EN-EA 11254 EAR 2 Magnets R. Lopez TE-MSC 11255 & 11256 EAR 3 Power Converters K. Papastergiou TE-EPC 11461 EAR 4 Beam instrumentation J. Tan BE-BI 11259 EAR 5 Beam Intercepting Devices M. Calviani EN-STI 11182 & & & & 10007 EAR 6 Vacuum System V. de Jesus 11277 EAR 7 Networks L. Borakiewicz IT-CS 11343 EAR 8 Controls M. Gourber-Pace BE-CO 11274 EAR 9 Electrical Systems S. Bertolasi EN-EL 11260 & & 11262 EAR 10 Cooling and Ventilation M. Battistin EN-CV 11446 EAR 11 Installation, Transport and handling C. Bertone EN-HE 11447 EAR 12 Civil Engineering S. Mcilwraith SMB-SE 11455 EAR 13 Radiation Protection R. Froeschl HSE-RP Included in other plan activity for general RP EAR 14 Machine Interlocks R. Mompo TE-MPE 10812 EAR 15 Alarms S. Grau BE-ICS 10771 & 10745 EAR 16 Personnel Protection System E. Sanchez-Corral Mena 11286, 11287, 11288 EAR 17 Survey D. Missiaen EN-ACE 11279 EAR 18 Commissioning and Operation S. Evrard 11280 EAR 19 Safety E. Harrouch EAR 20 Shielding M. Lazzaroni EAR 21 Collimation A. Ebn Rhamoun 10814 & 10011 EAR 22 Gaz D. Jaillet 11448 EAR 23 Exp. Areas & Layout change 11454 EAR 24 Dismantling 11252 & 11253 S.Evrard, EATM
4
PLAN: overview S.Evrard, EATM
5
B157 Renovation on Meyrin Site
Location – Meyrin Site (Swiss side) Internal client : EN/EA 47m B157 113m «Afin d’améliorer les conditions de travail dans ce bâtiment, son enveloppe sera rénovée (façades et toiture). En effet, d’importantes pertes de chaleur sont causées par la mauvaise isolation thermique de ses façades et du toit. De plus, certains des constituants de l’enveloppe contiennent de l’amiante et devront être déposés et traités de manière adéquate. C. Gasnier & S. Mcilwraith B157 renovation – SMB Strategic Review – EDMS:
6
1. Technical description – Work zone 1
Glazing to replace 250m2 Roof / ceiling panels to remove 4600m2 Suspended scaffolding (~5000 m2) C. Gasnier & S. Mcilwraith B157 renovation – SMB Strategic Review – EDMS:
7
1. Technical description – Work zone 2
Fibre-cement cladding to be replaced (1200 m2) Glazing to replace(1250 m2) C. Gasnier & S. Mcilwraith B157 renovation – SMB Strategic Review – EDMS:
8
1. Technical description - CE Baseline
3 technical issues with roof / ceiling: 1) Ceiling contains asbestos – danger to safety 2) Ceiling / roof are almost uninsulated – loss of energy 3) Roof is not waterproof* – rain penetrates interior Option Asbestos Insulation Waterproofing* 1) New false ceiling below existing - (Impossible to pierce existing asbestos-containing material) + = 2) Replace false ceiling 3) Remove false ceiling / replace roof Beyond the 3 above criteria, option 3 has the following advantages / disadvantages: - 1 intervention to ensure next life cycle of roof (building is 55y old) - 1 intervention of complex site installations - 1 period of co-activity with physics - Waterproofing of the building to be ensured during works Methodology to be detailed by bidders C. Gasnier & S. Mcilwraith B157 renovation – SMB Strategic Review – EDMS:
9
1. Technical description
Envelope composition (Architects preliminary design – June 2017) -Safety guardrail -Sandwich panels on roof (removal of old steel roof) Thickness : 120 mm U=0.20 W/(m2.K) Good thermal insulation -Polycarbonate panels on upper part: U=1.20 W/(m2.K) Translucent or transparent Light material (no modification of the structure necessary) -Sandwich panels on facades: Thickness : 100 mm U=0.23 W/(m2.K) -New glazings on lower part (North façade) and upper part: Double glazings C. Gasnier & S. Mcilwraith B157 renovation – SMB Strategic Review – EDMS:
10
1. Technical description
Envelope composition (Architects preliminary design – June 2017) C. Gasnier & S. Mcilwraith B157 renovation – SMB Strategic Review – EDMS:
11
B157 renovation – SMB Strategic Review – EDMS: 1831287
4. Planning Critical path until FC ! Worksite starts on Nov. 1st C. Gasnier & S. Mcilwraith B157 renovation – SMB Strategic Review – EDMS:
12
Civil Engineering Works – Removal of Waste
SMB has provided waste estimates needed Zoning concept has been defined and sent to the Swiss Radiation Protection authority (OFSP) OFSP has accepted our proposal of the zoning concept An in-situ measurement and sampling campaign has already been launched to validate the proposed zoning layout as agreed with OFSP The RP requirement based on the zoning concept will now be included in the Invitation to Tender Dosimetry for radiation workers Control measurements on the work-site Waste conditioning requirements R. Froeschl Status Update - RP Assessment – EDMS 21/07/2017
13
Project Safety Risk Analysis Schedule
EDMS# Flammable gas - ATEX zones Meeting with D. Jaillet – 5/09/2017 Capacitors Meeting with F. Boattini and K. Papastergiou – 8/09/2017 Shielding Blocks calculation note Meeting with M. Lazzaroni – 12/09/2017 Airborne activation - Ventilation system, P&ID Meeting with M. Battistin and R. Froeschl – 25/09/2017 APR Meeting with E. Sanchez, R. Froeschl, F. Pirotte, D. Chapuis, M. Battistin - 05/10/2017 S. Cherault
14
Upgrade EA Equipment Collimator Converter & absorber Cerenkov counter
Collimator 2 jaws installed New equipment Control Collimator 4 jaws LS2 Specification New control Cerenkov counter Function On operating, East Area Upgrade, LS2 A. Ebn Rahmoun A. Ebn Rahmoun,
15
Integration Collimator Cerenkov Converter D. Brethoux & A. Ebn Rahmoun
Project Team #6
16
East Area Renovation – Preliminary design for primary dump T9/T10/T10
Primary protons need to be dumped after hitting target T9/T10 Secondary beams are derived at an angle Primary protons need to be dumped after production target Dump has two functions Dump primary protons Provide passage for secondaries 3rd MCB 2nd MCB 1st MCB Targets Q74 T11 T10 T9 Primary dump Maarten van Dijk M. van Dijk, East Area Renovation – Preliminary design for primary dump T9/T10/T10
17
East Area Renovation - Beam line layout
Initial layout Dump front view Initial layout 3m high, 3.20m wide Varying thickness of iron Vacuum tubes T9/T10/T11 Ø159mm Primary beam dumped directly below T9/T10 T11 T10 T9 Primary beam height = 1260 mm Angle = 0° 784 mm 609 mm Damien Brethoux 20cm 100cm 240cm Maarten van Dijk J.Bernhard, East Area Renovation - Beam line layout
18
East Area Renovation – Preliminary design for primary dump T9/T10/T10
Adapted design – v3 Horizontal slice – beam T10 Pushed T11/QFO2 about 36cm upstream to allow more iron Iron thickness: T cm T9 / T cm Corner at T11 has most significant problems Will be blocked by a magnet Need to check what impact would be XZ – beam at T10 Maarten van Dijk M. van Dijk, East Area Renovation – Preliminary design for primary dump T9/T10/T10
19
Primary beam dump for T9/T10/T11
Several iterations of design for primary beam dump for T9/T10/T11 Improvement over initial design Preliminary adapted design Made of standard sized iron blocks Holes for secondary beam now 80mm Ø Holes for primaries T9 / T10 beam are 10cm Ø, length: 20cm air, 20cm Al, 50cm W Significant punchthrough at corner of T11 Need to assess impact Will iterate design further with input from RP (Robert Froeschl) Include magnet T11/QFO2 Maarten van Dijk M. van Dijk, East Area Renovation – Preliminary design for primary dump T9/T10/T10
20
Thanks for your attention !