Download presentation
Presentation is loading. Please wait.
1
11 T Dipole Integration & Plans M. Karppinen
From short models to the series
2
M. Karppinen CERN TE-MSC
11 T Nb3Sn Dipole Project Short model program Magnetic and mechanical design validation Conductor development Magnet protection Material choices Fabrication process validation Scale-up Coil fabrication (winding, curing, reaction, impregnation) Handling Cold mass integration (collaring, yoke assembly) Cold mass integration Cold bore tube Bus-bar routing Interconnects Spool correctors Heat exchanger Instrumentation Alignment Cryo-assembly (5.5 m) Cold-test in SM18 Collimator integration Collimator dimensions Interfaces (powering, instrumentation, vacuum, cryogenics, ...) Cryostat design QC and testing Transport & handling 12 June 2013 M. Karppinen CERN TE-MSC
3
M. Karppinen CERN TE-MSC
11T Dipole Coldmass (5.3 m) 5´772 5´911 5´546 6´257 (Ltotal) 242.5 5´772 (LCM) To reduce the length by 0.2 m the B0 shall be T, which requires additional ~530 A (wp 81% => 85%) TF correction requires -300 A, so a bi-polar 600 A trim PC could do the job. 12 June 2013 M. Karppinen CERN TE-MSC
4
FNAL 1-in-1 Model Magnet (1m) & CERN Coils
Courtesy of D. Mitchell, FNAL 22 May 2013 M. Karppinen CERN TE-MSC
5
CERN Construction Status
Coil fabrication tooling: Winding, curing, and reaction fully operational Vacuum impregnation system now commissioned Practice coil fabrication PC-#1-2 (Cu-cable) reacted, being impregnated PC #3 Nb3Sn (low-Jc WST strand) scrapped Nb3Sn (RRP-54-61) reacted, to impregnate Magnet R&D: Cable insulation (braided S2-glass & Mica) ODS (oxide dispersion strengthened) wedges Selective laser sintering (SLS) end spacers Coil pre-loading concept (“pole-loading”) Magnet protection (inter-layer heater) Coil reaction Coil impregnation Reacted Nb3Sn (RRP-54/61) coil 12 June 2013 M. Karppinen CERN TE-MSC
6
M. Karppinen CERN TE-MSC
CERN 11 T Dipole Coil Loading plate 2 mm 316LN SLS End Spacers with “springy legs” ODS Cu-alloy Wedges Braided 11-TEX S2-glass on “open-C” Mica sleeve Courtesy of D. Mitchell, FNAL 12 June 2013 M. Karppinen CERN TE-MSC
7
CERN Short (2 m) Model Program
Assemble and test the RRP-54/61 coil (reacted) as single coil assembly (MBHSS101) using existing collars, yoke, welded outer shell, and end plates Two RRP-108/127 coils to assemble and test the 1st 1-in-1 model (MBHSP101) Two RRP-132/169 coils to assemble and test the 2nd in-1 model (MBHSP102) Collared coils from MBHSP101 & 102 to assemble and test the 1st 2-in-1 model (MBHDP101) Idem for PIT-cable: 2 x 1-in-1 model (MBHSP103-4) to have tested collared coils for the 2nd 2-in-1 model (MBHDP102). Will be conflicting with MQXF and other magnet projects in terms of human resources and infrastructure 12 June 2013 M. Karppinen CERN TE-MSC
8
CERN Single Coil Assembly
Courtesy of C. Kokkinos & T. Lyon CERN TE-MCS Aftrer assembly at 293 K At 1,9 K, T, 14.1 kA Azimuthal coil stress (Mpa) Azimuthal coil stress (Mpa) 12 June 2013 M. Karppinen CERN TE-MSC
9
CERN Short Model Schedule
Oct-Nov -13 Jan-Feb -14 Apr-May -14 1-in-1 #1 Test Nov -14 – Jan -15 Feb-Mar -15 1-in-1 #2 Test Apr-Jun -15 2-in-1 #1 Test 1-in-1 #3 Test 1-in-1 #4 Test 2-in-1 #2 Test 12 June 2013 M. Karppinen CERN TE-MSC
10
CERN Prototype (5.5 m) Schedule
Start with winding trials using Cu-cable: simplified trials coil with bare cable first practice coil with insulated Cu-cable to react and pot (PC-1). First Nb3Sn practice coil with possibly low-performance (cheaper) cable (PC-2) First “real” coil (PC-3) to cold test as a single coil (mirror?) Four (or eventually more..) more coils for 2 collared coils to construct the full-scale proto and test it in Mid-2016. the 5.5 m schedule is compatible with the present LMF plans including the major procurements Additional coil production lines will be required for series magnets It is also vital to get the industry on board during the prototype construction to be ready for the series units 12 June 2013 M. Karppinen CERN TE-MSC
11
CERN 5.5 m Prototype Schedule
May-June 2015 July-August 2016 Single coil Qualification Test 5.5-m-long 2-in-1 Prototype Test 12 June 2013 M. Karppinen CERN TE-MSC
12
Series production (First impression)
LS2: Ions: Install 2 x units (4 X 5.5 m CM) in IR2 + 1 spare Protons: Install 4 x units (8 X 5.5 m CM) in IR7+ 1 spare Deliver 6-10 fully tested 5.5-m-long 11 T Dipole cold masses Integrate 2-4 fully tested 15.6-m-long cryo-assemblies in the LHC Coil production: 12-20 off 5.5-m-long coils to deliver 1 Production line/2 production lines 1/2 coil in 12 w, 2/4 coils in 17 w All coils: months / months Cold mass integration: Two collared coils 8 months / 5 months Cold mass assembly 1 month Cryostat assembly 1 month Cold test 2 months 6-10 CM X 11 / 9 months = / months Cryo-assembly: Cold mass integration: 2 months Cold test: 2 months 2 complete units min. 28 months 12 June 2013 M. Karppinen CERN TE-MSC
13
Cold mass vs. coil production lines
12 June 2013 M. Karppinen CERN TE-MSC
14
2 Off Cryo-Assemblies for IR2
12 June 2013 M. Karppinen CERN TE-MSC
Similar presentations
© 2024 SlidePlayer.com Inc.
All rights reserved.