1 Kalaallit Airports A/S
General Presentation June 2017

2 TOPICS About Kalaallit Airports A/S Management and Organization Project Strategy Area requirements Activities and status Project Financing Economics Uncertainties Commercial matters

3 ABOUT KALAALLIT AIRPORTS
Kalaallit Airports A / S was founded on July 1, 2016 and is owned 100% by the Government of Greenland The Company's purpose is to construct, own and operate airports in Nuuk, Ilulissat and Qaqortoq. Prior to the founding of the company, the Ministry of Infrastructure initiated the necessary feasibility studies and started the development of construction programs. Naalakkersuisut has as of subscribed for share capital in the company by 200 million DKK. On 30 December 2016, the Government of Greenland invested an additional 94.3 million DKK as subordinated loan to the company.

4 MANAGEMENT AND organization
Johannus Egholm Hansen, Chairman of Board - Professional Board Member, Business Consultant and Lawyer - Many years of International management, trade, project, M & A, and legal experience - Experience with infrastructure investments - Deputy Chairman of the Board during Airport Development in the Faroe Islands Presidency Finance Committee Committee of Construction Peter Christiansen, Deputy Chariman Executive MBA; Cand.merc. Strategy, Organization and Leadership at Copenhagen Business School - Chief Financial Officer Presidency Committee of Construction Anna-Berit Koertz, Board member - Bachl. of Commerce, Accounting internal/external, IT, Corporate Finance, Leadership and Org. E-MBA Shipping & Logistics, Strategy, Organization, Operations Management, International Economics, Finance, Shipping and Supply Chain Management - Many years of experience with financing, including Project financing and board work Finance Committee Jàkup Sverri Kass, Board member - Cand.ling.merc. - Airport Director and Professional Board Member - Many years of management, sales and marketing experience Operating Committee Aviâja Lyberth Lennert, Board Member - Diploma of Arts; Bachelor of Science in Sociologi - Board work, project management and management. Operating Committee Steffen Ulrich-Lynge, CEO - Engineer - Great management experince - Responsible for the construction of regional airports in Greenland Operating Committee Committee of Construcion Peter Wistoft, CFO - Former equity partner at Deloitte (Former state-authorized public accountant) - Expert in accounting & budgeting - Management experience

5 Management and organization
Steffen Ulrich-Lynge, CEO Peter Wistoft, CFO Others Aviaaja Knudsen, Project Director Jesper Nordskilde, Project Manager Annie Lennert, Administrative Manager

6 Project Strategy Overall planning Project planning
Separation of runway projects and service and terminal projects, both in the project planning and execution phase Creation of Greenlandic jobs, competence-development and knowledge sharing will be among the criteria for selection of project advisors and contractors Project planning Project programs are based on the following runway lengths, as decided by Inatsisartut and Naalakkersuisut; Qaqortoq: meters Ilulissat: meters Nuuk: meters Runways designed with 2-4 months shifted intervals Planning of airport buildings are expected to start medio 2017 The Board considers own supply of technical equipment and machinery

7 Project strategy Execution
Commencement of tender process for construction contracts requires a new decision by Naalakkersuisut Initiation of runway projects with 2-4 months intervals Initiation of terminal- and service buildings with 2-4 months intervals The Board considers the possibility of offering alternative timetables during project management, due to constraints on entrepreneurial capacity and the risk of higher prices

8 Area requirements - qaqortoq

9 Area requirements - nuuk

10 Area requirements - ilulissat

11 PLANNED PLANNED PLANNED
5. ACTIVITIES & STATUS QAQORTOQ ILULISSAT NUUK PLANNED PLANNED PLANNED Dialogue with commercial stakeholders ongoing ongoing ongoing (Eg Mittarfeqarfiit, Air Greenland, etc.) Project Organisation ongoing ongoing ongoing Selection of technical client advisor (Inuplan) completed completed completed Tender for advisory sevice regarding EIA completed completed completed Selection of advisor regarding EIA (NIRAS) completed completed completed Project programe and C-estimate completed completed completed Regulatory approvals throughout throughout throught 2017+ - EIS quarter quarter quarter. 2018 Regulatory approvals throughout throughout throughout Land Allocation quarter quarter quarter. 2018 Regulatory approvals throughout throughout throughout Aviation Authority approval quarter quarter quarter. 2018 Regulatory approvals July July July 2017 - Project permit from ”Infrastructure”

12 PLANNED PLANNED PLANNED
5. ACTIVITIES & STATUS QAQORTOQ ILULISSAT NUUK PLANNED PLANNED PLANNED Pre-qualification of enginee. companies, runway completed completed completed Tendering and selection of enginee. companies completed completed compledet runway ILS Simulations finished finished Development of Business and Financing Plan Aug Aug Aug. 2017 Pre-qualification of enginee. companies, buildings June-Aug June-Aug June-Aug.2017 Tender concerning enginee. companies, buildings Sept.-Nov Sept.-Nov Sept.-Nov. 2017 Engineering of terminal and service buildings Dec Dec Dec Dec Dec Dec. 2018 Project proposals and B-estimates for runways Dec Aug Oct Mar Nov Jan. 2018 Preparation of tender documents July July July 2017- for the choice of corporate Finance Advisor Aug Aug Aug. 2017 Selection of corporate Finance Advisor Sept Sept Sept. 2017 Development of Information Memorandum Sept Sept Sept to lenders Mar Mar Mar. 2018

13 PLANNED PLANNED PLANNED
5. ACTIVITIES & STATUS QAQORTOQ ILULISSAT NUUK PLANNED PLANNED PLANNED Negotiating with lenders and contracting Apr Apr Apr June June June 2018 Main project and updated B-estimates,runways April Dec Feb July Mar Maj 2018 Tender for Construction Contracts, runways Aug April June 2018- Okt June Aug. 2018 Land construction, runways Nov June Sept Nov Nov Jan. 2020 Tender forConstruction Contract, buildings Jan Jan Jan Mar Mar Mar. 2019 Terminal and service buildings, construction April April April 2019- Sept Sept Sept. 2021 Pavement, runway lighting and nav. equipment May May May 2020- Commencement of airport operations Oct Oct Oct. 2021