Presentation is loading. Please wait.

Presentation is loading. Please wait.

Progress of Electricity Market Reform in the UK

Similar presentations


Presentation on theme: "Progress of Electricity Market Reform in the UK"— Presentation transcript:

1 Progress of Electricity Market Reform in the UK
Angela Knight, Chief Executive, Energy UK

2 Electricity Market Reform (EMR)
2 Electricity Market Reform (EMR) The policy was designed to: Promote decarbonising of the electricity generation sector as the principle route for meeting the UK greenhouse gas emissions. Provide a subsidy for all low carbon generation and not just renewables (nuclear and CCS); and Set in place a framework for a capacity mechanism to ensure that electricity is available to meet demand from existing and new converted generation.

3 Currently being decommissioned
3 UK Generation Fleet The UK generation fleet is old and the reinvestment challenge is significant: Coal (30-40%); gas (30-40%); and nuclear (15-20%); balance renewables Much of the coal is closing due to the LCPD and the balance by 2200 to meet the IED Nuclear is old and needs rebuilding Station Technology Status Capacity Date of Closure/ mothballing Teeside CCGT Closed 1875MW April 2011/October 2013 Kings Lynn mothballed 325MW March 2012 Roosecote 165MW October 2012 Keadby 735MW March 2013 Derwent closed 214MW December 2012 Kingsnorth Coal 2.0GW December2012 Grain Oil 1.3GW Shotton 210MW June 2012 Didcot A Cockenzie 1.2GW Tilbury Coal/Biomass 1.1GW October 2013 Fawley 1.0GW Uskmouth 0.36GW March 2014 Ferrybridge Partial closure 0.98GW of 1.98GW Peterhead 1.8GW of 2.2GW Ironbridge Biomass/coal Due for closure 340MW By end of 2015 (under LCPD) Littlebrook 1245MW Barking 1000MW Currently being decommissioned

4 Government and Opposition Parties publically declared vision is to:
4 Government and Opposition Parties publically declared vision is to: Decarbonise power generation; and Maintain security of supply; and Keep energy affordable Known as the “trilemma”, is this achievable?

5 The Contract for Difference (CfD) is at the heart of EMR
5 The Contract for Difference (CfD) is at the heart of EMR Gives revenue certainty to investors in low carbon generation, including wind, solar, biomass and nuclear and CCS Government has set administrative strike prices but there will be compensation for contracts based on prices. CfD generators sell their output into the market in the normal way but when the wholesale market is below the strike price, the generation is “topped up” The sum over and above the wholesale market price is added to the consumer bill. This is all done through the central counterparty.

6 Contracts for Different and “strike prices”
6 Contracts for Different and “strike prices” Published administrative strike prices are: Onshore wind – 95mwh Offshore wind – 155mwh Biomass – 105mwh Nuclear – case by case (Hinkley Point C offered mwh) Solar – 120mwh

7 Contracts for Different and “strike prices”
7 Contracts for Different and “strike prices” CfD’s awarded to date are:- Total additional cost on consumer bills by 2020 for CfDs capped at £7.6bn. CfD works out at roughly £30 per annual average domestic bill by 2020. £104 overall from all low carbon spends under the LCF Project Developer Technology MW Location Beatrice SSE - Beatrice Offshore Windfarm Limited Offshore wind 664 Outer Moray Firth, Scotland Burbo Bank extension Dong Energy Wind Power A/S 258 Liverpool Bay Drax Unit #1 Drax Biomass conversion 645 Selby, North Yorkshire Dudgeon StatOil and Statkraft - Dudgeon Offshore Wind Limited 402 The Wash Hornsea 1 1200 North Sea, off the Yorkshire coast Lynemouth Lynemouth Power Limited 420 Ashington, Northumberland Teesside MGT Power Limited Dedicated Biomass, CHP 299 Middlesbrough Walney Extension 660 Irish Sea

8 Investment slowing £100 Billion required by 2020 or thereabouts
8 Investment slowing £100 Billion required by 2020 or thereabouts Current expenditure run rate is £13bn pa and is substantial considering: Falling energy demand; Pressure from consumers on affordability; and Political, regulatory and policy risk Renewables capacity grew by 50Gw in 2013 to 20Gw in total and projected to double by 2020. Investment in conventional generation insufficient Capacity market introduced with first auctions this year

9 Issues (1) Wholesale market depressed by policy interventions
9 Issues (1) Wholesale market depressed by policy interventions Gas economies problematic Capacity market does not deliver until 2018/2019 Closure programme accelerated and capacity margin narrowed – down to 4.1%. Concerns rising in respect of security of supply

10 Issues (2) Interconnection tendency to be substantial due to:
10 Issues (2) Interconnection tendency to be substantial due to: Carbon price floor Balancing and transmission costs apportionment “merchant” interconnector model Market no longer gives market signals Consumers resisting paying for the programme Increasing concern in respect of onshore wind Generation closure programme and new generation opening programme not connected.


Download ppt "Progress of Electricity Market Reform in the UK"

Similar presentations


Ads by Google