1 건설분야-교육자료 미디어개발 Construction Collapse during form installation after excavation on the lower part of masonry Power Point Training Material on Serious Accidents in Construction (Serious Accidents in Construction) The copyright to this material belongs to the Korea Occupational Safety and Health Agency. Unauthorized use and distribution are prohibited. If an individual uses this for non-commercial purposes, the Korea Occupational Safety and Health Agency must be cited as the source. A corporation using this material must obtain permission from the Korea Occupational Safety and Health Agency first. Using this material without prior permission will be considered copyright infringement, and legal action may be taken.

2 Table of Contents I. Fatality Overview II. Site Overview
III. Fatality Description IV. Fatality Cause V. Precautions

3 Think it over! Find out the Hazard Points in the figure below.

4 Collapse during form installation after excavation
on the lower part of masonry 1. Fatality Overview Date & Time: 11:45, June 19, 2007 (Tuesday) Place: new constructions of ○○ multiplex house site Victim: mold carpenter of a contractor (male/53) While the victim was installing a form on the lower part of excavated masonry retaining wall, old masonry and block wall collapsed and a falling stone hit the victim in the side. He was taken to the hospital. However, he died during medical treatment. Power Point Training Material on Serious Accidents in Construction Site Overview New construction multiplex house building (with 3 stories above ground and 1 below, 8 houses) site - Public works were under way. (overall process rate was 3%)

5 Collapse during form installation after excavation
on the lower part of masonry 3. Fatality Description At about 07:30, 7 workers (employer, carpenter 2, 2 iron bar workers, B/Operator) including the victim went to the site. From 08:00 to 11:40, they excavated ground on the bottom the existing masonry retaining wall (width: 0.8m, depth: 1.0m) using a small backhoe (Komatsu pc 18, so called, mini excavator). After that, they inserted iron bar (H: ≒ 2m) into the ground to install forms (euro-from). At about 11:45, the victim was installing joist (pipe for steel pipe scaffold) and sleeper (2’×2’ rectangular lumber) on the forms. At that time, block for the masonry and wall collapsed and a falling stone hit him in the side. He was took to the hospital. However, he died during medical treatment. Power Point Training Material on Serious Accidents in Construction 5

6 Collapse during form installation after excavation
on the lower part of masonry Power Point Training Material on Serious Accidents in Construction [Fatality Overview] 6

7 Collapse during form installation after excavation
on the lower part of masonry Power Point Training Material on Serious Accidents in Construction [Fatality Site (Refilled after fatal accident to prevent the second accident)] 7

8 [Masonry and wall collapse (upper house, refilled up)]
Collapse during form installation after excavation on the lower part of masonry Power Point Training Material on Serious Accidents in Construction [Masonry and wall collapse (upper house, refilled up)] 8

9 Collapse during form installation after excavation
on the lower part of masonry 4. Fatality Cause Insufficient protections against collapse such as preparatory study - For excavation close to old masonry and block wall, you must conduct a preparatory study to prepare protections against collapse. However, they did not prepare protections against collapse. Power Point Training Material on Serious Accidents in Construction 9

10 Collapse during form installation after excavation
on the lower part of masonry 5. Precautions Protections against collapse such as preparatory study - For excavation close to old masonry and block wall, you must conduct a preparatory study install retaining wall and must prepare protections against collapse of Shotcrete pouring such as reinforcement measures. Power Point Training Material on Serious Accidents in Construction 10