Presentation is loading. Please wait.

Presentation is loading. Please wait.

CLAS12 Forward Tracking: Status and Challenges

Similar presentations


Presentation on theme: "CLAS12 Forward Tracking: Status and Challenges"— Presentation transcript:

1 CLAS12 Forward Tracking: Status and Challenges
Region 1- Idaho State stringers are doing final wires on the 3rd and 4th chambers. Have a full stringing crew in place Region 2- Old Dominion is almost finished stringing the 6th (final) Region 2 chamber. They have fully tested all previous chambers at high voltage; found very few problems and fixed all of them. Region 3- First two Region 3 chambers are done with stringing, and have gas bags in place. High-voltage testing is underway. (see photo) Installation Plans- Rack locations for high-voltage, low-voltage and signal readout will all be on the floor to both sides of the torus. Plans are being made to begin cable and connector labeling and refurbishment; delayed somewhat by recent flood. Overall: Most sub-tasks have been completed; stringing is about 60% complete (see project summary plot) Oct. 10, 2012 CLAS12 Forward Tracking: Status and Challenges

2 ‘Region 3’ Work at Jlab & Project Status
CLAS12 Drift Chamber Construction Status Region 3 Chambers at Jlab Oct. 10, 2012 CLAS12 Forward Tracking: Status and Challenges

3 DC12 Challenges and Mitigation Strategy
Refurbishing old equipment: we plan to re-use HV cables and distribution boxes but some pins are damaged and difficult to buy we plan to re-use post-amplifier/discriminator boards and crates and LeCroy FASTBUS TDC’s (difficult to maintain) evaluate equipment; investigate alternative solutions (started); we have many spares On-chamber instrumentation: HV boards must be mounted on chamber; cables soldered on with full length rolled up design, prototype, test, re-design (we have an experienced crew) Achieving 250 micron resolution: survey to 100 microns relative to toroidal geometry know B-field to <1% relative to toroidal geometry account for distortions: wire sags and endplate bowing of ~1mm size  we have a very reproducible link-mounting scheme; survey points will be included in the cryostat design; conceptual plans for B-field mapping started; we have experience doing alignment using real data Oct. 10, 2012 CLAS12 Forward Tracking: Status and Challenges

4 A new DC board with tracking trigger ?
based on capabilities of a new “drift chamber readout board”: amplifier, discriminator, TDC FPGA architecture allows “segment-finding” fully-pipelined readout of data and trigger logic  trigger can associate a charged track with a hit in a scintillator-based detector Oct. 10, 2012 CLAS12 Forward Tracking: Status and Challenges

5 CLAS12 Forward Tracking: Status and Challenges
How does it work? Oct. 10, 2012 CLAS12 Forward Tracking: Status and Challenges

6 CLAS12 Forward Tracking: Status and Challenges
Underlying logic? Move triangular template across superlayer; occupancy of 2 or greater is a ‘half-cluster’, aligned ‘half-clusters’  ‘cluster’ Oct. 10, 2012 CLAS12 Forward Tracking: Status and Challenges

7 Operating Cost Savings
Units Saved / Year Cost / Unit Yearly Savings Data Storage Tapes 3000 Tbytes * .75 35$ / Tbyte 80 k$ Maintenance Manpower 100 FTE days 45$/day 4 k$ Power Savings 60,000 kW-hrs 0.10$/kW-hr 6 k$ Offline cpu Cycles 10^8 cpu-secs ? Total Cost Savings ~ 100 k$ Oct. 10, 2012 CLAS12 Forward Tracking: Status and Challenges

8 CLAS12 Forward Tracking: Status and Challenges
DCRB Cost and Schedule Table 1 Project Cost Description Quantity Price Labor Notes Ext Price Turnkey Production 252 $1600 2 weeks Procurement $405K Delivery ARO 8 wks. delivery Acceptance Testing 3 weeks Specify/Purchase 9U x 160mm VXS crate 18 $10K 1 weeks $180K Crate acceptance Power test Full crate DCB test verification Full function test Installation & commissioning 4 weeks Hall installation/test Totals 15 weeks $585K Oct. 10, 2012 CLAS12 Forward Tracking: Status and Challenges

9 Magnetic Field Measurement
Small manufacturing defects can lead to measurable changes in tracking what is the effect of a 2mm radial shift in one coil? on a small-angle, high-momentum electron in the bore (convenient place to measure B) 7o, 10 GeV/c electron B ~ 2 T r = 42 cm Oct. 10, 2012 CLAS12 Forward Tracking: Status and Challenges

10 Magnetic Field Measurement
2mm coil shift  0.7 % change in B at 42 cm radius 2mm coil shift  40 Gauss dipole field on axis Oct. 10, 2012 CLAS12 Forward Tracking: Status and Challenges

11 CLAS12 Forward Tracking: Status and Challenges
Summary The CLAS12 drift chamber project proceeds well; still plenty to do: instrumentation, installation, commissioning and calibration. An alternative DC readout board with FPGA technology enables flexible charged-track triggering, reduces tape usage and offline computing, and saves money. Small distortions in torus manufacture can cause significant tracking distortions; schemes to measure magnetic field must be developed. Oct. 10, 2012 CLAS12 Forward Tracking: Status and Challenges

12 Forward Tracker: Dependence of Momentum Resolution on DC Resolution
Backup slide: Multiple scattering dominates fractional momentum resolution vs. Effect of changing resolution 250 350 microns Oct. 10, 2012 CLAS12 Forward Tracking: Status and Challenges


Download ppt "CLAS12 Forward Tracking: Status and Challenges"

Similar presentations


Ads by Google