Download presentation
Presentation is loading. Please wait.
1
Harley-Davidson Museum
Milwaukee, WI. Jonathan Rumbaugh, BAE/MAE Mechanical Option Advisor: Dr. William Bahnfleth
2
Project Sponsors
3
Presentation Outline Project Background Existing Conditions
Thesis Goals Depth One Thermal Bridging Depth Two Heat Rejection Cooling Tower River Water Depth Three CHP Feasibility Conclusions
4
Building Statistics Size (Total Square Feet): 130,000
Number Stories Above grade: 3 Construction timeline : April 2005 – May 2008 Overall Project Cost: $75 million
5
Location & Layout N
6
Location & Layout N
7
Location & Layout
8
Location & Layout
9
Location & Layout
10
Mechanical Design Two Roof Mounted 300 Ton Air-cooled Rotary Screw Chillers Four 2000 MBH Sealed Combustion Condensing Boilers Variable Primary Flow 11 Air Handling Units 2 5 4
11
Energy Model
12
Energy Model $0.10 / kWh Electricity $0.80 / Therm Natural Gas
13
Emissions Calculations use factors from the Regional Grid emissions Factors table B-10
14
Emissions 9 Million lbs. of C02e / year 867 acres
15
Comparison
16
Goals Reduce Emissions Reduce Energy Consumption Reduce Operating Cost
17
Proposal Decrease Thermal Loads Through Envelope
Increase Efficiency of Chilled Water Production Become Energy Independent From Grid
18
Depth One Thermal Bridging
19
Depth One Thermal Bridging
20
Depth One Thermal Bridging
Outside Inside Location of thermal break N
21
Depth One Thermal Bridging
22
Depth One Thermal Bridging
23
Depth One Thermal Bridging
24
Depth One Thermal Bridging
25
Depth One Thermal Bridging
8760 hr. study Total: Watts per year Lowest indoor temp = 69 oF Savings: $1, / year [Main gallery] For a simple payback of 5 years Each Thermal Break = $653
26
Depth One Thermal Bridging
27
Depth One Thermal Bridging
28
Depth One Thermal Bridging
29
Depth One Thermal Bridging
30
Two 300 Ton Air Cooled Chillers EER 9.4
Depth Two Heat Rejection Two 300 Ton Air Cooled Chillers EER 9.4 Carrier
31
Depth Two Heat Rejection
Carrier
32
Two 300 Ton Water Cooled Chillers COP 5.9
Depth Two Heat Rejection Two 300 Ton Water Cooled Chillers COP 5.9 EPA
33
Depth Two Heat Rejection
34
Depth Two Heat Rejection
Additional Water: 2, gal Cost : $5, / year Capital: -$42,850
35
Depth Two Heat Rejection
30 Year LCC Existing Air-Cooled System: $4,045,288.09 Alternative 2; Water-Cooled System: $3,861,471.04 Savings: $183,817.05
36
Depth Two Heat Rejection
Supply Return
37
Depth Two Heat Rejection
38
Depth Two Heat Rejection
Cold Water Temp = 0.739*WB
39
Depth Two Heat Rejection
40
Depth Two Heat Rejection
41
Depth Two Heat Rejection
42
Depth Two Heat Rejection
Capital: +$104,255
43
Depth Two Heat Rejection
Simple Payback: years Discount payback : years 30 Year LCC Alternative 2; Cooling Tower System: $3,861,471.04 Alternative 3; River Water System: $3,641,264.61 Savings: $220,206.43
44
Depth Two Heat Rejection
45
Air-Cooled vs. Water-Cooled with River Water
Depth Two Heat Rejection Air-Cooled vs. Water-Cooled with River Water Capital cost increased 10% [$61,400.00] Annual operating cost reduced by 14% [$21,732.00] 30 year LCC reduced 10% [$389,986.00] Simple payback 3 years
46
Depth Three CHP Feasibility
47
Electric Cost: $0.10/kWh = $29.30/MMBTU
Depth Three CHP Feasibility Spark Gap Electric Cost: $0.10/kWh = $29.30/MMBTU Gas Cost: : $0.80/therm = $8.00/MMBTU 1 : 3.7 Ratio , 1 : 4 [rule of thumb]
48
Depth ThreeCHP Feasibility
Thermal-to-Electric Ratio = 0.74 Recommended: 373 kWe Gas Engine
49
Conclusions Depth Three CHP Feasibility Additional Cost $564,000
Generation Cost $0.088 /kWh 1.2 cents less than purchased Total Savings: $140,000 /year Simple Payback: 4.04 Years CO2 reduction of 62%
50
+ + = = Total $160,000 Annually 4 Year Payback 65% Reduction of CO2
Recommendations + + Total $160,000 Annually 4 Year Payback 65% Reduction of CO2 = =
51
Questions?
52
Depth One Thermal Bridging
Member Force Allowable Actual OK? Beam Bending Moment 64.12 ft kips 18.5 ft kips Yes Shear 79.1 kips 3.7 kips Girder 3723 ft kips 686 ft kips 886 kips 40.05 kips Live Load Deflection 3.4” 2.75” Total Deflection 6.85” 6.6” Column Load 355 kips 50 kips Thermal Break 13,400 psi 2.24 psi
Similar presentations
© 2024 SlidePlayer.com Inc.
All rights reserved.