INFRASTRUCTURE PROGRAMME FOR DCS PRESENTATION TO PORTFOLIO COMMITTEE ON JUSTICE AND CORRECTIONAL SERVICES DATE: 04 AUGUST 2015
2
1. OBJECTIVES OF THE PRESENTATION
To Present to Portfolio Committee the Infrastructure Programme implemented by Department of Public Works on behalf of Department of Correctional Services To provide an update on issues raised during the oversight visit conducted in Limpopo The challenges in delivering the Programme Options being Investigated to correct the situation and prevent future occurrences
3
2. GENERAL PERSPECTIVE Over the past years DPW experienced significant drop in performance in the delivery of infrastructure and this was attributed to various factors, amongst them: Contractor disputes with their subcontractors, General under-performance by contractors, Contractors’ cash flow challenges. Tedious process of liquidation and termination of non-performing contractors and subsequent delays in appointing the new contractors after termination. Delays in decision making from the client’s side. DPW remains responsible to maintain the existing facilities through service contracts under the Repair and Maintenance Programme (RAMP), and the more reactive means referred to as day-to-day maintenance The Users are delegated attend to minor maintenance services to the tune of R100 000 per assignment (maximum).
4
2. GENERAL PERSPECTIVE Cont…
DPW has been implementing a turnaround plan that has resulted in the establishment of Programme Management Office (PMO), the Ministerial Joint Task Team and has seen improved performance on expenditure from the 2014/15 Financial Year. As part of the efficiency enhancement phase (phase 2) of the DPW turnaround plan, we are in the process of separating the Capital Programme and the Facilities Management Programme, as focused business centres to improve planning and accountability.
5
3. DCS CAPITAL PROGRAMME The NDPW implements construction projects and operation of facilities for DCS as per instructions issued and budgeted for. This includes the following: Construction of New Correctional Facilities Upgrading of existing facilities Improvement of Security Measures Improvement of Fire detection services Upgrading and maintenance of Mechanical & Electrical Services Provision of water to facilities outside municipal networks Operate and maintain Waste Water Works, and contribute to recycling for irrigation Operation and maintenance of Boilers Repair and Maintenance of Kitchen Equipment In providing these services DPW utilises the services of Consultants and Contractors appointed through the tender process.
6
4. DCS CAPITAL PROGRAMME – PERFORMANCE MEASURES / REPORT
The Performance Measures the NDPW uses are mainly the following: Expenditure of Allocation (Financial Measures): DCS approves an annual capital allocation following the review process of Progress made in Planning Stages of Projects and Budget Estimates, as informed by Projected Cash Flows for Committed Contracts. Delivery of Completed Projects/ Facilities: Performance in Execution and Completion of construction projects is linked to the Delivery Date as informed by contract period. Each Project has its planned / projected date which Users use to plan their occupation. Maintenance of Services (Facilities Management) : Water Supply; Fire Fighting Equipment; Kitchen Fittings; Waste Water Management; Servicing of Boilers The Financial Performance is discussed starting from 2013/14 – 2014/15
7
5. DCS CAPITAL EXPENDITURE – END MAY 2014 (2013/14)
OFFICE ALLOCATION R’ EXPENDITURE B’ALANCE % EXP CORRECTIONAL SERVICES 47% HEAD OFFICE 44% KAM 0% PROF SERV:TOWN PLANNING 164% SPECIAL & MAJOR PROJECTS 41% REGIONAL OFFICES BLOEMFONTEIN 26% CAPE TOWN 97% DURBAN 48% JOHANNESBURG 63% KIMBERLEY 60% MMABATHO 37% NELSPRUIT 45% POLOKWANE 6% PORT ELIZABETH 18% PRETORIA 82% UMTATA 91 005 4% TOTAL
8
6. DCS CAPITAL EXPENDITURE – END MARCH 2015 (FY 2014/15)
OFFICE ALLOCATION R’ EXPENDITURE BALANCE % EXP CORRECTIONAL SERVICES 81% HEAD OFFICE 51% PROF SERV:TOWN PLANNING 0% SPECIAL & MAJOR PROJECTS 54% REGIONAL OFFICE 83% BLOEMFONTEIN 52% CAPE TOWN 55% DURBAN JOHANNESBURG 46% KIMBERLEY 88% MMABATHO 77% NELSPRUIT 145% POLOKWANE 21% PORT ELIZABETH 144% PRETORIA 34% UMTATA TOTAL
9
7. DCS CAPITAL EXPENDITURE – END JUNE 2015 (FY 2015/16)
OFFICE ALLOCATION R’ EXPENDITURE % EXPENDITURE SPECIAL & MAJOR (HO) 0% BLOEMFONTEIN 8% CAPE TOWN 116% DURBAN 11% JOHANNESBURG 6% KIMBERLEY MMABATHO 23% NELSPRUIT 41% POLOKWANE 2 214 PORT ELIZABETH 86% PRETORIA 20% UMTATA 83 434 TOTAL 30%
10
8. CONTRIBUTING FACTOR TO UNDER EXPENDITURE/ PERFORMANCE IN THE PAST TWO PERFORMANCE YEARS
Withdrawal of Security Projects from tender stage due to unhappiness expressed by DCS over dominance of the sector by one supplier. Generally poor workmanship and inability to schedule the sequence of Work on Site properly by contractors leading to spending lower than the projections. Six Prison Contracts (Ceres, Vanrhynsdorp, Kgoši Mampuru, Escort, North End, and Tzaneen) contractor experienced cash flow problems leading to liquidation and contract cancellations. Shortage of Prison Window Supplies in the Market, implying that building works cannot continue without windows due to the installation method. Because the Cash Flow Expenditure is linked to monthly work progress and acquisition of capital fittings (mechanical, Electrical), if this is not realised on site, Budget is not spent.
11
9. TZANEEN CORRECTIONAL CENTRE
The Contractor for this project has been liquidated. The Liquidators identified new service provider (replacing contractor) to complete remaining portion of work. However the challenge with the proposal requires that the department have a direct contract with the identified service provider. The legal opinion has been received, which indicates that another contractor can complete the works, however the original contractor will still be held accountable as per the conditions of the contract. The DPW had successful engagements with the liquidator and started discussions with the guarantor. The guarantor will conclude negotiations with the new contractor on the 31st August The negotiations will include the new date for the new contractor to be on site. Assessment to recover any additional costs emanating from the delays, where applicable will be done once the project has reached final completion.
12
10. PARYS CORRECTIONAL CENTRE
The project was advertised; however bids received were higher than the actual estimate. The DPW negotiated with CIDB to waive 6 month cooling period and re-advertisement is scheduled for 31 July We anticipate award by 31 October 2015.
13
11. KGOŠI MAMPURU – C-MAX CORRECTIONAL CENTRE
The contract was terminated due to poor performance and this termination was done at 70% completion. However this contractor was subsequently liquidated. Consultants were appointed to conduct assessment and finalise the Final account. The processes to appoint the new contractor have commenced and the anticipated award date is mid-November 2015. This project was visited jointly by DPW and DCS on the 15/07/205 as part of close monitoring and weekly report will be provided by the project manager and professional team. Assessment to recover any additional costs emanating from the delays, where applicable will be done once the project has reached final completion.
14
KGOŠI MAMPURU – C-MAX 1 Concrete Works Completed Prior To Termination of Contract 2 Concrete Walkways 3 Concrete & Structural Work Completed Prior Cancellation Of Contract
15
12. VANRHYNSDORP CORRECTIONAL CENTRE
The initial contractor was liquidated. The guarantor started in February 2015 to complete the remaining works and the project is anticipated to be completed by October Progress to date is 99% on the work completed by the original contractor and currently finalising electrical compliance matters. Assessment to recover any additional costs emanating from the delays, where applicable will be done once the project has reached final completion.
16
VANRHYNSDORP CORRECTIONAL CENTRE
1 Main Entrance to the Facility 2 Dining Hall 3 Laundry Facility 4 Visitors Facilities
17
13. CERES CORRECTIONAL CENTRE
The initial contractor for this project was liquidated and the guarantor appointed a new contractor and the new contractor completed the project in April Final delivery taken in July There is no need to recover costs as there were no additional costs incurred.
18
CERES CORRECTIONAL CENTRE
1 Main Entrance to the Facility 2 Kitchen Facilities 3 Laundry Facility 4 Training Facility
19
14. ESTCOURT CORRECTIONAL CENTRE
The initial contractor for this project was liquidated and the guarantor has appointed the new contractor to complete the remaining work. Work progress on site is at 43%, however delays have been experienced due to lack of consistent supply of specialised (manganese) windows and door frames. Upon assessment, the realistic completion date is January 2017 given the above mentioned delays and weather inclination extension of time claims under consideration.
20
ESTCOURT CORRECTIONAL CENTRE
21
15. NORTH END CORRECTIONAL CENTRE
Repair & Renovations of the Facility. The initial contractor for this project was liquidated and the guarantor appointed the new contractor in August 2014 to complete the remaining work. Progress is about 48% complete. The completion date as per contract is end of March 2016.
22
North End CORRECTIONAL CONTRE
Visitor Receiving Centre Newly Constructed Dining Hall Male Juvenile Toilet Generator Fencing
23
15. MATATSHE (THOHOYANDOU) CORRECTIONAL CENTRE
First contract was terminated due to non-performance. The new contractor is already appointed and was handed over site on the 12th June Site establishment will be completed end of July Construction period is for 24 months, including maintenance.
24
16. GLENCOE CORRECTIONAL CENTRE
The prison was burnt down in May An assessment was conducted and different options were proposed, including demolition and rebuilding of affected areas with brick and mortar and ensure that the existing corrugated facility is fire compliant. The proposal has been submitted to DCS for consideration.
25
Glencoe Correctional Centre
26
17. PERFORMANCE REPORT ON DCS FOR 2015/16
The Capital budget allocation for DCS for 2015/16 is R Expenditure as per end of June 2015 is R (representing 30% of budget allocated vs 25% time lapsed) The programme has a total of 246 projects, with an allocation/budget of R for the 2015/16 financial year. 108 Projects are in planning and 138 projects are committed (status 5b-9) with a budget of R 563
27
18. CHALLENGES Construction of New Correctional Facilities is very complex and requires a longer sustained cash flow. We have realised that Contractors experienced cash flow problems when they are at about 60% of the contract because of the following: At this stage of project most mechanical and electrical installations are required on Site and Suppliers require higher deposits to confirm orders. These components in most cases are under-priced by contractors far below the Retail Costs, and contractors have to somehow source cross-subsidise the purchases from other projects, which leads to collapse of cash management. Repetition of works due to correction of defective works Idling resources or Labour on sites because of improper work scheduling which increases labour costs Failure to pay Supplier / Creditors on time leads to applications for Administration or Liquidation Specification for Security Contracts and Supplier Monopoly
28
19. OPTIONS INVESTIGATED TO PREVENT THE RECURRENCE OF CHALLENGES
CURRENT CONTROLS OPTIONS BEING IMPLEMENTED/ UNDER REVIEW Appointment of Competent Contractors Current Controls are based on SCM Policies linked to Points for Competitive Price & Preference, and Risk Assessment The SCM evaluation method now include Functionality Replacement of Defaulting Contractors The Department still follows the open tender approach, which is far time consuming Internal Policy development in consultation with National Treasury to allow for Nomination of Capable Contractors to submit bids to complete the remaining works Poor Programming of Works Contractors submit Programme of Works Improve the condition of tender to include Appointment of Professional Construction Managers for specific value threshold of contracts
29
THANK YOU