Mr. Nolan Alvarado / TSgt Lewis
KEEN EDGE 2009 CPX Logistics Mr. Nolan Alvarado / TSgt Lewis
2
J73 Timeline DEC JAN JAN 18 JAN 25 JAN 28 S T A R E X 05 JAN
SET UP TRANSPORTATION INVENTORY ADP EQUIPMENT TRACK ARRIVALS OF PACOM PERSONNEL DEVELOP PERSONNEL ROSTER 26 JAN Participants Leave (31) 28 JAN Ichigaya Participants, TSgt Lewis/ Nolan Leaves 08 JAN JWFC(6) ARRIVES 25 JAN END EX PPM/AAR TRANSPORT PACOM PERSONNEL TO ICHIGAYA(6) S T A R E X 15 JAN TY ARRIVES 15 DEC ADP EQUIPMENT CONFIRMED YOKOTA 09 Jan PACOM/KBSC STAFF (20) ARRIVES DEC JAN JAN 18 JAN 25 JAN 28 06 Jan TECH TEAM(8) Arrives 23 JAN Col Davis Arrives 27 JAN Build Pallets SHIP OUT FEDEX ADP EQUIPMENT BACK TO PACOM 15 DEC CONFIRM RETURN TRIP ON FEDEX SHIPMENT 25 JAN BEGIN PACK OUT FOR ADP EQUIPMENT IN PREPARATION FOR SHIP OUT DATE 26 Jan COMPLETE PACK OUT STAGE TO PALLETIZE 04 JAN TSgt Lewis Arrive in Country 11 Jan DET 120 Kelly Kirk Arrives (6) 02 JAN Nolan arrive in Country
3
Event Schedule 14 DEC: ADP Equipment received at USFJ
18 DEC: RETURN Shipment confirm on 27 Jan 2009 02 Jan: Nolan arrive in country 04 Jan: TSgt Lewis arrive in country 05 Jan: Set – up transportation Inventory ADP Equipment Track Arrivals of KE participants Set-up arrival Desk for KE USPACOM participants
4
ARRIVALS 06 JAN: TECH Team(8) 08 JAN: JWFC(6)
09 JAN: PACOM/KBSC Staff(20) 11 JAN: DET 120/Kirk/Kelly(6) 15 JAN: Ty Arrives 23 JAN: Col Davis arrives
5
Lodging Tracker
6
TRANSPORTATION POC: TSgt Lewis Base Shuttle ‘Kanto Express” USFJ
2 nine-pax vehicles POC CPL DARAMY OFFICE ROOM DISPATCH GOV Vehicles > 15 pax and 9 pax Able to be given 2 vehicles POC Chief Dispatch TSgt Cohen/SSgt Pittman office Reservations can be made in November 4 Vehicles Drivers TSgt Lewis Nolan Herman Brandon SGM Agustin
7
LODGING Kanto Lodge Final Count for PACOM Personnel at 47
Maj Luyando blocked Rooms POC TSgt Lewis
8
RETURN SHIPMENT OF ADP EQUIPMENT
What ADP Equipment on 7 Pallets 15 Hard drives How FEDEX (TRANSCOM Funded) Entered into TPFFD Current Status Schedule pick up POC: J02HQ2 - SK2 Smith When 27 January 09 Who TSgt Lewis POC Nolan Jeff Little (USFJ) Where Equipment will be staged for re-shipping in USFJ BECG
9
TPFDD / JMD PACOM J7 Government ULNs has been Validated.
TRANSCOM approved funding for airfare under the Commercial Ticket Program for Government Personnel Only. DET 120 funded by USN Contractors are Unit Funded
10
AAR / PPM Participants Transportation Lodging Col Davis Ty Wooldridge
Jerry Giles Herman Ancheta Charlie Snyder Brandon Tokumoto Transportation Participants leave 25 Jan from Yokota AB TSgt Lewis working with USFJ for Transport Lodging Maj Luyando POC Made reservations at the Grand Hills Ichigaya Credit Card Information received 25 – 28 January Col Davis leaves on 27 January
11
KEEN EDGE 2009 CPX Good Afternoon. Questions?
12
KEEN EDGE 2009 CPX Simulations Mr. Larry Tran
13
Requirements Network Infrastructure will be in place and fully operational USFJ J6 TOP COP and subordinate GCCS will be fully functional Phone directories for role players and training audience will be available MDA will provide backup BMD systems for missile injects
14
Sim/C4I Architecture
15
Event Test 3 Review / Validate C4I architecture Primary path
Alternate path JOI feed Review / Validate / Functional JTLS database Testing Day 1,2 Review / Validate / Functional US Forces Day 3,4 Review / Validate / Functional JSO Forces Day 3,4,5 Japanese JTLS OJT training BMD testing Day 1 and Day 2 of ET3 Reinforce Response Cell Operating Procedures
16
BECG Training Products due out: Training material for C2PC and ICSF
Provide simulation Provide COP Provide missile shots
17
Warm Start Process
18
Execution These procedures will be used:
Model controller change procedures Shadow game procedures Checkpoint procedures Simulation Crash procedures Hardware failover procedures COP inject procedures
19
KEEN EDGE 2009 CPX Good Afternoon. Questions?
20
Network / Technical Support
KEEN EDGE 2009 CPX Network / Technical Support Mr. Brandon Tokumoto
21
BECG SET-UP TIMELINE Monday Tuesday Wednesday Thursday Friday Saturday
Sunday 5-Jan 6-Jan 7-Jan 8-Jan 9-Jan 10-Jan 11-Jan TECH / SIM DEPLOY FROM HNL BECG SET-UP ET3 12-Jan 13-Jan 14-Jan 15-Jan 16-Jan 17-Jan 18-Jan BECG Training COMMEX / MINIEX CPX 19-Jan 20-Jan 21-Jan 22-Jan 23-Jan 24-Jan 25-Jan 26-Jan 27-Jan 28-Jan 29-Jan 30-Jan 31-Jan 1-Feb PACKOUT / REDEPLOY AAR ICHIGAYA
22
ADVON Team Jerry Giles (OIC) Brandon Tokumoto (IM/KM) Will Yip (IM/KM)
Add all J73 personnel roles and responsibilities ADVON Team Jerry Giles (OIC) Brandon Tokumoto (IM/KM) Will Yip (IM/KM) Robert Chang (Systems / Network Tech) Ken Winter (COMMS / Tech / C4I) Mike Harraway (Systems Engineer) Larry Tran (Senior Model Control) Joe Lacalamito (COMMS / C4I) TSgt Lewis (BECG Admin) Nolan Alvarado (Logistics)
23
Requirements J73 Logisitics will have equipment available for setup within BECG spaces J73 Logisitics will have access badges available for setup team and access to the facility J73 Logisitics will have Classified hard drives available for setup Per discussions with USFJ J6, support will be provided as needed within normal business hours ( ) and user accounts will be provided by USFJ J6
24
DAY 1 (JAN 7) Validate badging and acquire access to facility
Familiarize setup team with facility Validate equipment Distribute tasking to setup team Begin setup of network infrastructure Setup servers and clients
25
DAY 2 (JAN 8) Network HOT! Setup printers, projectors and peripherals
Create and post signage Test and confirm all IMKM toolsets Test access to IMKM toolsets from external sites
26
DAY 3 (JAN 9) All systems HOT! Finalize any open issues
Assist with any additional requirements for ET#3 Detailed POAM will be provided to all staff members
27
Event Test #3 Support will be provided throughout ET#3
Develop Help Desk SOP Revisit roles and responsibilities and finalize with USFJ J6
28
Training / MiniEx Support will be provided during both venues
Assist with training Assist with user accounts Assist with white cell briefings
29
CPX Support One Network / Tech Support per shift
USFJ J6 will also provide 1 Help Desk staff member IM / KM will also provide support, if needed Network / Tech Support Shifts Mr. Robert Chang (Day Shift) Mr. Kirk Fehn (Night Shift)
30
KEEN EDGE 2009 CPX Good Afternoon. Questions?
31
Information Assurance
KEEN EDGE 2009 CPX Information Assurance Mr. Brandon Tokumoto
32
Security Requirements
C2 for KE09 CPX is CENTRIX-JAPAN Secret releasable network Access to SIPR All SIPR request, must be processed through USFJ J6 and validate by BECG Senior Control IA briefing by USFJ J6 will be given to all participants USFJ J6 is the overseeing authority for all IA issues and concerns
33
Security Guidelines NO Personal Laptops NO Government Laptops NO USB
NO Air Gapping of files NO Cell Phones NO PDAs
34
CENTRIX JAPAN Account USFJ CENTRIX-JAPAN Account Request Form
Instructions available on KE09 APAN and EPIC sites Signed and Completed IA Certificate
35
KEEN EDGE 2009 CPX Good Afternoon. Questions?
36
Information Management
KEEN EDGE 2009 CPX Information Management Mr. Brandon Tokumoto
37
IM Toolsets EPIC CBT Lessons Learned JMSEL Open to all BECG members
User name and password required to access Each BECG cell group will have a dashboard CBT Two views response cell view and senior control view Lessons Learned JMSEL
38
Setup Days 1, 2, 3 Fully engaged with setup
Coordinate with USFJ J6 IM lead to finalize BECG and training audience directories
39
Event Test #3 Support will be provided throughout ET#3
Revisit roles and responsibilities and finalize with USFJ J6
40
Training / MiniEx Support will be provided during both venues
Deliver training EPIC CBT Lessons Learned Assist with user accounts Assist with white cell briefings
41
CPX Support One IM / KM per shift IM / KM Support Shifts
Available to assist Network / Tech as needed IM / KM Support Shifts Mr. Brandon Tokumoto (Day Shift) Mr. William Yip (Night Shift)
42
KEEN EDGE 2009 CPX Life Support / Misc Mr. Tony Mesa
43
Life Support Passport and CAC Military ID and Orders under SOFA
Emergency Contact Will be provided on site Weather Current conditions High 49 degrees F Low 33 degrees F Anticipated January weather COLDER Bring warm clothing
44
Miscellaneous Medication Bills Power of Attorney
Fill all prescriptions prior to departure and make sure they can get through customs Bills Coordinate all financial responsibilities prior to departure Power of Attorney
45
KEEN EDGE 2009 CPX Good Afternoon. Questions?