Presentation is loading. Please wait.

Presentation is loading. Please wait.

SMECO Demand Response filing

Similar presentations


Presentation on theme: "SMECO Demand Response filing"— Presentation transcript:

1 SMECO Demand Response filing
March 18, 2008

2 SMECO Filing Components
Background Current Load Management Load Management Program with Comverge Customer Participation & Operation Cost/Benefit Review SMECO Cost/Benefit recovery

3 Background EmPower Maryland establishes a goal of 15% statewide reduction in electric usage by 2015 SMECO filed reduction plan on January 11, 2008 outlining energy efficiency, conservation, and demand response efforts Demand Response plan filed March 18, 2008

4 Current Load Management
SMECO current Load Management system employs switches on approximately 61,000 air conditioners and water heaters Legacy program began in 1986 Provides 11 MWs of capacity credit in the PJM ILR program Customers receive incentive payments of $5/month for AC & $2.50/moth for WH

5 Comverge Load Management Program
A Virtual Peaking Capacity (VPC) contract has been executed with Comverge Comverge currently has over 4.5 million devices with over 500 US utility clients; 495 MW of capacity currently contracted

6 Covmerge Load Management Program
New program will give customers the choice of a Smart Thermostat or Digital Control Unit (DCU) air conditioner switch Approach will be to target both existing Load Management customers and new customers Target of 50 MW by 2011 Based on 28% participation rate and 1.25kW/device

7 Comverge Contract

8 Initial Incentive & Cycling Plan
Customers who opt for the Smart Thermostat will receive a $50 annual incentive Those opting for the digital switch will receive a $25 annual incentive Thermostats use 2 degree offset followed by 30% cycling Switches use 50% cycling followed by 30%

9 Ongoing Cycling & Penetration
SMECO and Comverge will work collaboratively to establish control strategies that are best suited to encourage participation among various subgroups SMECO has a history of high penetration rates among residential customers

10 DR Benefit Computation

11 Benefit Computations ILR/DR Revenue calculation
SMECO will receive capacity credit for MWs registered in the PJM Interruptible Load Response Program SMECO will receive capacity credit for MWs offered into the PJM Reliability Pricing Model auctions beginning in Planning Year Total ILR revenue through September 2017 of $7,402,373 (NPV $5,701,828); Total DR Capacity Revenue through September 2017 of $22,031,626 (NPV $12,261,077)

12 Benefit Computations Reduction in Capacity Costs
Demand response capacity will contribute to lower RPM clearing prices Price reduction impacts SMECO’s total capacity obligation (950 MW in 2011) Total reduction in capacity costs: $27,140,215 (NPV $14,851,140) Reduction in Peak Hour Energy Costs Project avoiding 50 MW for 100 peak summer hours Projected energy costs savings of $15,896,251 (NPV $8,926,162)

13 Benefit Computations Reduction in Network Integration Transmission Service (NITS) and Other Supporting Facilities (OSF) Charges Reducing the MW measured during the coincident peak load for summer periods will reduce our NITS and OSF obligations Price savings over the course of the VPC contract total $6,501,587 (NPV $3,777,186)

14 DR Cost Computations

15 Cost Computations SMECO Direct Costs Payment for Legacy Switches
Includes contractual costs of installation and maintenance of switches & thermostats, customer incentive payments, and administrative costs Total: $44,442,577 (NPV $27,523,053) Payment for Legacy Switches SMECO will receive revenue for removal of existing Legacy air conditioner and water heater switches Total: ($1,672,70,6) (NPV $1,341,804)

16 Cost Computations Depreciation of Legacy Switches
Remaining depreciation value of existing Load Management equipment recovered over the course of the current contract Total: $1,996,211 (NPV $1,317,804) Current Incentive Reductions Early phase out of current Legacy program will reduce incentive payments Total: ($9,322,384) (NPV ($6,091,366))

17 Program Cost/Benefit Totals
Total cost to SMECO for implementation of VPC program through 9/17: $35,443,698 Total estimated benefits to SMECO through 9/17: $78,972,051 Benefit to Cost ratio of 2.13 to 1 (using Net Present Value) Other potential benefits not estimated: PJM ancillary costs Peak period forward energy charges

18 Cost/Benefit Graph

19 Participant vs. Nonparticipant Bill Impact

20 Sensitivities (Benefit/Cost ratio)

21 Sensitivities (Benefit/Cost ratio w/out depreciation & incentive reductions)

22 Benefit Recovery PJM Invoice Credits Reduction in RPM price
ILR and RPM Capacity Payments Flows through SOS Allocated based on DR Capacity Reduction in RPM price No direct cost determination Reduced SOS requirement Net SOS impact to all classes

23 DR Cost Recovery Direct Costs – Contact & Administrative Charges
Recovered through DRCRF operating same as DSMCRF Based on estimated costs with annual true-up mechanism One year recovery of expenses Includes depreciation of Legacy switches Includes credit for Legacy payments Incentive Reduction Current incentives to Legacy program customers Will automatically drop off as payments end PPCA factor will automatically adjust

24 DR Revenue Stabilization
Recover Transmission and Distribution revenue requirement Annual estimate of DR program impact Customer charge basis to spread evenly and match costs


Download ppt "SMECO Demand Response filing"

Similar presentations


Ads by Google