1 Sanitary Sewer Lift Station Rehabilitation Design Services Pre-Submittal Meeting
September 20, 2016

2 Introductions

3 Purpose of Meeting Provide overview of the Sanitary Sewer Lift Station Rehabilitation Design Services RFP Answer questions regarding the project

4 Agenda Safety Moment Project Background Procurement Process
Evaluation Criteria and Submittal Information Scope of Services Questions

5 Safety Moment Consultant will develop health and safety plans as part of PXP Field safety instructions for site visits and field work (survey, geotechnical, etc.) For consultant and their subconsultants

6 Project Background

7 Project Background City is under a Regional Water Quality Control Board Cease and Desist Order to eliminate sanitary sewer overflows and unauthorized discharges Master plan efforts have identified needed collection system improvements The CWP includes a Biennial Pump Station Upgrade Program, identifying high priority sanitary sewer pump stations for upgrade Condition Assessment identified the following lift stations for high priority rehab: Kelly/Kehoe Laurie Meados Los Prados No. 1 Los Prados No. 2 Los Prados No. 3

8 Project Map

9 Background Documents Integrated Wastewater Master Plan (Draft), Carollo, October 2014 City of San Mateo Pump Stations and Force Mains Condition Assessment, AECOM, June 2016 The Citywide Sanitary Sewer Pump Station Study, Schaaf & Wheeler, November 2010

10 Procurement Process

11 RFP Schedule Milestones What When RFP Available September 11, 2016
Pre-Submission Meeting September 20, 2016 Deadline for inquiries/questions September 30, 2016 SOQs Due at the City October 17, 2016 Consultant Short List October 31, 2016 Consultant Interview November 8 - 9, 2016 Consultant Selection November 11, 2016 Consultant Negotiation – Phase 1 November 14 – December 9, 2016 Council Award January 9, 2017 Notice to Proceed January 30, 2017

12 RFQ Questions and Addenda
Send in writing Include “Sanitary Sewer Lift Station Rehabilitation Design Services” in subject line Deadline for questions: 5:00 PM, September 30, 2016 Direct Inquires to: Robert Wiseman, Contract Manager Responses published to City’s website Addenda: Posted to City website Oral clarifications are non-binding City will not notify respondents of addenda Response must include acknowledgement of addenda

13 Scoring and Selection SOQ Interview Final Scoring and Selection
Scoring based on a maximum of 100 points Scored based on Evaluation Criteria SOQs will be ranked and short-listed Interview Short-listed firms will be interviewed Different evaluation criteria may be used for the interview Respondents will be ranked Failure of Respondent or proposed team members requested by the City to participate in the interview may result in disqualification Final Scoring and Selection Combined SOQ and Interview scores will be used to determine the final ranking Rating forms will not be revealed Written notice of selection will be provided to the selected firm

14 Negotiation and Award Negotiation Award LOE SOW Schedule
Contract terms Negotiations may be discontinued if no terms reached after 3 revisions Award Recommendation to council at conclusion of negotiations Initial contract for Phase 1 only

15 Submittal Information and Evaluation Criteria

16 SOQ Format Submittal: Format: 6 original bound SOQs
1 disc or flash drive with ready-for-print PDF of the SOQ Provide submittal in a box or envelope and include Respondent’s name, contact information and SOQ title and job number on the box or envelope SOQ shall remain effective for 90 days beyond the submittal date Format: Maximum of 30 pages, including cover letter and excluding resumes of key personnel Cover letter requirements Front and back cover and dividers not included in page count Project schedule shall be prepared on 11” x 17” paper Maximum of three 11” x 17” figures Resumes shall not exceed 2 pages Any excess pages beyond limit will be removed and not considered in the evaluation

17 SOQ Evaluation Criteria
Prime and Subconsultant Firms’ Project Experience and Past Performance: 30 points Key Project Personnel: 30 points Project Understanding and Approach: 35 points Project Schedule: 5 points

18 Project Experience and Past Performance
Project experience and past performance for prime consultant and subconsultants For Prime Consultant, minimum of five similar projects Sanitary and sewer lift station rehabilitation/design projects Maintaining sanitary sewer lift stations in service during rehab Validation of rehab requirement and analysis of pump station hydraulics and selection of equipment Odor control analysis and design for sanitary sewer lift stations Rehab/replacement of force mains, mechanical valves and piping, electrical equipment and I&C systems associated with sanitary sewer lift stations Proposed prime and subconsultants working together on similar projects

19 Key Project Personnel Project Manager Design Manager Project Engineer
Other Specific Subject Matter Experts

20 Project Understanding and Approach
Project risks Approach to design and wide range of rehab tasks Maintaining operability during rehab Minimizing changes during construction and impacts to work area surroundings Expanding pumping capacities Team qualifications Management Team strengths

21 Project Schedule Proposed baseline schedule
Identify tasks, subtasks, durations, milestones Identify field investigations and exploratory work Single 11x17 inch page

22 Interviews Interview for short-listed firms, at City’s discretion
Elaborate on SOQ and respond to specific questions Questions may be issued prior to the interview 60 minutes, including questions and answers Identified PM will lead presentation City will notify respondent which key personnel are required to be present during interview

23 Scope of Services

24 Phased Negotiation Phase 1 Phase 2 Phase 3 Task 1 – General Services
Task 2 – Verification of Rehabilitation and Basis of Design Phase 2 Task 3 – 50% Design Task 4 – 90% Design Task 5 – 100% Design and Bid Documents Task 6 – Bid Period Assistance Phase 3 Task 7 – Construction Phase Services

25 Task 1 – General Services
Services performed throughout the project Project Management Risk Management Workshops and Meetings Quality Control Management of Subconsultants Agency Coordination, Public Outreach Support, and City Meeting Support Permitting and Environmental Support Consultant to obtain all permits for the project

26 Task 2 – Verification of Rehabilitation and Basis of Design
Tasks: Gather and review available information and studies Site visits of subject facilities and structures O&M staff coordination and discussions Prepare a Basis of Design Report

27 Task 3 – 50% Design Survey Field and aerial surveys Complete before proceeding to 90% design Geotechnical Investigation, if determined necessary during Phase 1 Field Exploration and Testing Geotechnical Reports (GDR, Geotechnical Design Memorandum) Utility Potholing, if determined necessary during Phase 1 Locate key buried utilities or other structures Completed before proceeding to 90% design 50% Design Development

28 Task 4 – 90% Design 90% Design Submittal 90% Design Drawings
Major design elements well-established and substantially complete Specs substantially complete and include all sections and divisions AACE Class 2 Estimate with basis of estimate narrative and construction sequencing plan 90% Design Drawings

29 Task 5 – 100% Design and Bid Documents
Final (100%) Design Submittal Final Bid Documents

30 Bidding and Construction
Task 6 – Bid Period Assistance Conducted independently for each identified projects Pre-bid meeting, respond to bidder questions, addenda, bid evaluation, conformed documents Task 7 – Construction Phase Services Pre-construction and progress meetings, submittals, RFIs, change orders, record drawings, etc.

31 Questions?