Project Organization and Communication

Similar presentations


Presentation on theme: "Project Organization and Communication"— Presentation transcript:

1 Project Organization and Communication
Roadmap for today’s class Project organization organization roles tasks and work products schedule – Gantt chart, PERT chart Communication

2 Some Questions Related to Project Organization and Communication
Who is responsible for which part of the system Which part of the system is due by when Who should be contacted when a problem with a specific version of a component is discovered In which form should new requirements be communicated to developers Who should be informed of new requirements Who is responsible for talking to the client

3 Basic Elements of a Project
Work Product Schedule Task Participant Project Work Product: This is any item produced by the project Schedule: This specifies when work on the project should be accomplished Participant: This is any person participating in a project Task. This is the work to be performed by a project participant to create a work product.

4 Team-based Organization
* Team * Participant

5 A Simple Project Organization
Managerment Team Database Team Control Team UserInterface Team Member1 Member2

6 Relationships between Participants
Organizations can have many different types of associations between participants The three most important associations for project organizations are: Reporting, decision making and communicating Reporting association: Used for reporting status information Decision association Used for propagating decisions Communication association Used for exchanging information needed for decisions (e.g., requirements, design models, issues).

7 An Organization with a Reporting and Decision Structure
The developers make local decisions and reports them via a status report to the leader (team leader, project manager) The team leader, who has a local overview of the subsystem, can override these decisions. She reports them to the project manager. The project manager, who has a global view of the project, can virtually override any decision.

8 Hierarchical Organization
Often also called centralized organization. Examples: Military, church, traditional businesses. Key property: The organization has a tree structure. Decisions are made at the root and communicated to the leaf nodes. The decision association is also used for reporting and communication. Advantages: Centralized control over project selection One set of management and reporting procedures for all project participants across all projects Established working relationships among people Clearly established lines of authority to set priorities and resolved conflicts Authority to pressure people to honor their action items Clearly defined career path

9 Hierarchical Project Organization
Control Flow Information Flow Chief Executive First Level Manager (“Front-Line Manager”) Project Members A B A wants to talk to B: Complicated Information Flow B wants to make sure A does a certain change: Complicated Controlflow Basis of organization: Complicated information and control flow across hierarchical boundaries

10 Liaison Based Project Organization
UserInterface :Team role Alice :Develolper John Mary Chris Sam Team leader API engineer Documentation liaison implementator Management: Team communicates Architecture: Documentation: Testing:

11 Definition: Role A role is a set of responsibilities
A role is instantiated during a project and assigned to one or more persons. Instances of roles are often also called players („who are the key players?“) or stakeholders

12 Different types of roles
Developer Liaison Manager Consultant API Engineer Document Editor Configuration manager Tester Project Manager Tam Leader Application Domain Specialist Solution Client End User

13 Key Roles in Organizations
Project Manager: The person ultimately responsible for the successful completion of the project Project Team Member: Participants who are responsible for performing individual activities and tasks (in a project organization) Functional Manager: The team member‘s supervisor in the department (in a functional organization) Upper management: People in charge of the departments or projects

14 Responsibilities of the Project Manager
Determine objectives, schedule and resource budgets Design a software project management plan (SPMP) Create and sustain focused and motivated teams Determine the team‘s work procedures, reporting systems and communication infrastructure. Accomplish project objective within time and budget Monitor performance against the plan Resolve technical conflicts and interpersonal conflicts Control changes in the project Report on project activities to upper management Keep the client informed and committed Contribute to the team members performance approval

15 General Responsibilities of Team Members
Technical responsibilities: Perform assigned tasks within time and budget Acquire technical skills and knowledge needed to perform the work People responsibilities Identify situations and problems that might affect your team members‘s tasks Keep your team members informed of your progress and problems you encounter

16 Tasks and Work Products
A task is a well-defined work assignment of a role Gruops of related tasks are called activities A work product is a tangible item that results from a task

17 Tasks and Work Products
A task is a well-defined work assignment of a role Gruops of related tasks are called activities A work product is a tangible item that results from a task Task name Assigned role Task description Input Output Database subsystem Requirements elicitation System architect Elicits requirements.. Team liaisons Database subsystem API Database subsystem design Object designer Designs the database … Subsystem API Database subsystem design (UML diagram) Schedule the tasks

18 How to develop an Initial Project Schedule
Identify all your activities (reuse a template if possible) Identify intermediate and final dates that must be met Assign milestones to these dates Identify all activities and milestones outside your project that may affect your project’s schedule Identify “depends on” relationships between all these identified activities Draw a dependency diagram for all identified activities and relationships Analyze the diagram to determine critical paths and slack times of noncritical paths. Example: Establish a schedule for system integration testing

19 PERT Chart Critical path

20 Gantt Chart A Gantt chart is a compact way to represent the schedule of a software project along the time axis. It is a bar graph on which the horizontal axis represents time and the vertical axis lists the different tasks to be done. Tasks are represented as bars whose length corresponds to the planned duration of the task.

21 Gantt Chart Easy to read Activity 1 Activity 2 Activity 3 Activity 4
1 2 3 4 5 6 7 Time (in weeks after start) Easy to read

22 Gantt Chart with milestones Good for reviews. Project Start Activity 1
Design Review Activity 4 Activity 5 Project Finish 1 2 3 4 5 6 7 Time (in weeks after start) Good for reviews.

23 Two Types of Gantt Charts
Person-Centered View To determine people‘s load Activity-Centered View To identify teams working together on the same tasks Joe A1 A2 A3 A1 Joe, Toby Mary A2 Joe Toby A1 A3 A3 Clara, Toby, Joe Clara A3 Time Time Choose one view, stay with it. Usually base the view on the WBS structure Managing Experienced Teams: Person-centered view Managing Beginners: Activity oriented view

24 Review All These Concepts
Work out An Example Together Class Project of CSC 4350/6350 Organization Chart Tasks and roles table Schedule Chart – Gantt chart

25 A Communication Example
"Two missile electrical boxes manufactured by different contractors were joined together by a pair of wires. Box 1 Pair of Wires Box 2

26 A Communication Example (continued)
Thanks to a particular thorough preflight check, it was discovered that the wires had been reversed." Box 1 Box 2

27 After the Crash... ... "The postflight analysis revealed that the contractors had indeed corrected the reversed wires as instructed."

28 “In fact, both of them had.”
Box 1 Box 2

29 Communication is important
In large system development efforts, you will spend more time communicating than coding A software engineer needs to learn the so-called soft skills: technical writing, reading documentation, communication, collaboration, management, presentations. In this course, we ask each of you to (acquire and) demonstrate the following skills: Management: Run a team meeting Presentation: Present an major aspect of STARS during its development phase. Collaboration: Negotiate requirements with the client and with members from your team and other teams. Technical writing: Write part of the documentation of STARS

30 Definitions Communication event
Type of information exchange that has defined objectives and scope Scheduled: Planned communication (e.g., review, meeting) Unscheduled:Event-driven communication (e.g., request for change, issue clarification, problem report) Communication mechanism Tool or procedure that can be used to transmit information Synchronous: Sender and receiver are available at the same time Asynchronous: Sender and Receiver are not communicating at the same time.

31 Classification of Communication
Event is supported by Communication Mechanism * * Planned Event Unplanned Event Synchronous Mechanism Asynchronous Mechanism

32 Planned Communication Events
Problem Definition Objective: Present goals, requirements and constraints Example: Client Presentation Usually scheduled at the beginning of a project. Project Review: Focus on system model Objective: Assess status and review system model, system decomposition, and subsystem interfaces Examples: Analysis Review, System Design Review Scheduled around project milestones and deliverables Client Review: Focus on requirements Objective: Brief client, agree on requirements changes Client Review Usually scheduled after analysis phase

33 Planned Communication Events (continued)
Walkthrough (Informal) Objective: Increase quality of subsystem Example: Developer presents subsystem to team members, informal, peer-to-peer To be scheduled by each team Inspection (Formal) Objective: Compliance with requirements Example: Client acceptance test (Demonstration of final system to customer) To be scheduled by project management

34 Planned Communication Events (continued)
Status Review Objective: Find deviations from schedule and correct them or identify new issues Example: Status section in regular weekly team meeting Scheduled every week Brainstorming Objective: Generate and evaluate large number of solutions for a problem Example: Discussion section in regular weekly team meeting

35 Planned Communication Events (continued)
Release Objective: Baseline the result of each software development activity Software Project Management Plan (SPMP) Requirements Analysis Document (RAD) System Design Document (SDD) Object Design Document (ODD) Test Manual (TM) User Manual (UM) Usually scheduled after each phase Postmortem Review Objective: Describe Lessons Learned Scheduled at the end of the project

36 Unplanned Communication Events
Request for clarification The bulk of communication among developers, clients and users. Example: A developer may request a clarification about an ambiguous sentence in the problem statement. Request for change A participant reports a problem and proposes a solution Change requests are often formalized when the project size is substantial. Example: A participant reports of a problem the air conditioner in the lecture room and suggests a change. Issue resolution Selects a single solution to a problem for which several solutions have been proposed. Uses issue base to collect problems and proposals

37 Example of Request for Clarification
From: Alice Newsgroups: cs413.architecture.discuss Subject: SDD Date: Thu, 10 Oct 23:12: Message-ID: MimeVersion: 1.0 Content-Type: text/plain; charset=us-ascii When exactly would you like the System Design Document? There is some confusion over the actual deadline: the schedule claims it to be October 22, while the template says we have until November 7. Thanks, Alice

38 Example of a Change Request
Report number: 1291 Date: 5/3 Author: Dave Synopsis: The STARS client crashes when empty forms are submitted. Subsystem: User interface Version: 3.4.1 Classification: missing/incorrect functionality, convention violation, bug, documentation error Severity: severe, moderate, annoying Description: <<Description of the problem>> Rationale: <<Why the change should be done>> Proposed solution: <<Description of desired change>>

39 Example of Issue Base

40 Synchronous Communication Mechanisms
Smoke signals Supports: ?, Pros: ?, Cons: ? Hallway conversation (face-to-face) Supports: Unplanned conversations, Request for clarification, request for change Pro: Cheap and effective for resolving simple problems Con: Important information can be lost, misunderstandings can occur when conversation is relayed to others. Meeting (face-to-face, telephone, video conference) Supports: Planned conversations, client review, project review, status review, brainstorming, issue resolution Pro: Effective mechanism for resolution of isssues, and building consensus Con: High cost (people, resources); difficulty of managing them and getting effective results

41 Meeting Roles Primary facilitator Minute taker Time keeper
Responsible for organizing the meeting and guiding the execution. Writes the agenda describing objective and scope of meeting. Distribute the agenda to the meeting participants Minute taker Responsible for recording the meeting. Identifies action items and issues Release them to the participants Time keeper Responsible for keeping track of time

42 Structure of a Meeting Agenda

43 Asynchronous Communication Mechanisms
Supports: Release, change request, brainstorming Pro: Ideal for planned communication events and announcements. Con: taken out of context can be easily misunderstood, sent to the wrong person, lost or not read by the receiver. Newsgroups Pro: Suited for notification and discussion among people who share a common interest; cheap (shareware available) Con: Primitive access control (often, you are either in or out) World Wide Web Supports: Release, change request, inspections Pro: Provide the user with a hypertext metaphor: Documents contain links to other documents. Con: Does not easily support rapidly evolving documents

44 Summary Communication Events Communication Mechanisms
Planned (stipulated by the schedule) Unplanned (driven by unexpected events) Communication Mechanisms Asynchronous communication mechanisms Synchronous communication mechanisms Important events and mechanisms Weekly meeting Project reviews Online communication (discussion forum, , web)