T-76.115 Project Review X-tremeIT I1 Iteration 02.12.2003.

Similar presentations


Presentation on theme: "T-76.115 Project Review X-tremeIT I1 Iteration 02.12.2003."— Presentation transcript:

1 T Project Review X-tremeIT I1 Iteration

2 Valeria, Konstantin, Roman, Olesia, Vladislav, Seppo, Aleksandr
Agenda Project status (7 min) achieving the goals of the iteration project metrics Used work practices (5 min) Completed work (30 min) presenting the iteration’s results demo Plans for the next iteration (3 min) X-TremeIT Valeria, Konstantin, Roman, Olesia, Vladislav, Seppo, Aleksandr

3 Status of planned goals of the iteration
Ratification of the requirements Designing core architecture of the system Writing specifications Implementing important modules 3 Use cases Module testing Requirements ratification Writing specs Architecture design Modules implementation Use cases implementation Testing X-TremeIT Valeria, Konstantin, Roman, Olesia, Vladislav, Seppo, Aleksandr

4 Status of planned deliverables of the iteration
Implemented core architectural parts: Engine, GUI, Communications Use cases implementation: Case UC-01: Creating new process diagram Case UC-02: Add new object Case UC-03: Add dependency between 2 objects Main Documents: updated project plan updated requirements document tech. specification on a general level test case specifications X-TremeIT Valeria, Konstantin, Roman, Olesia, Vladislav, Seppo, Aleksandr

5 Realization of the tasks
Deviations Personal assignment Architectural design meetings X-TremeIT Valeria, Konstantin, Roman, Olesia, Vladislav, Seppo, Aleksandr

6 Working hours by person
Realized hours in this iteration Real Plan Diff Valeria 62,5 51,3 11,2 Aleksandr 52,5 45,3 7,2 Vladislav 55 9,7 Konstantin 56 48,3 7,7 Olesia 50,5 5,2 Roman 64,5 19,2 Seppo 40,1 -5,2 Total 361 326,1 PP I1 Subtotal I2 I3 DE Total Valeria 62 62,5 124,5 30 25 22 202 Aleksandr 56 52,5 108,5 40 19 198 Vladislav 53 55, 108 32 20 200 Konstantin 54 110 18 Olesia 41 50,5 91,5 44 196 Roman 50 64,5 114,5 35 210 Seppo 46 40,1 86,1 39 185 361 722 270 235 139 1366 X-TremeIT Valeria, Konstantin, Roman, Olesia, Vladislav, Seppo, Aleksandr

7 Valeria, Konstantin, Roman, Olesia, Vladislav, Seppo, Aleksandr
Quality metrics Bug metrics I1 I2 I3 DE Total Reported Closed Small bugs were found while compiling the code Insignificant logical bugs eliminated right on the programming sessions All conducted tests are passed Functional area Coverage Quality Comments Communications 3 J No defects GUI L Not started Engine 2 No defects, not all functions checked yet X-TremeIT Valeria, Konstantin, Roman, Olesia, Vladislav, Seppo, Aleksandr

8 Software size in Lines of Code (LOC)
Module LOC Classes GUI 857 5 Engine 612 6 Communications 606 4 Total 2075 X-TremeIT Valeria, Konstantin, Roman, Olesia, Vladislav, Seppo, Aleksandr

9 Valeria, Konstantin, Roman, Olesia, Vladislav, Seppo, Aleksandr
Risks Risk management risks evaluation forms Risks analysis (Red , Yellow, Green) New risks “Not enough time to complete required tasks” Risks becoming more important to the project (utility losses) or probability of the risk is increasing? X-TremeIT Valeria, Konstantin, Roman, Olesia, Vladislav, Seppo, Aleksandr

10 Valeria, Konstantin, Roman, Olesia, Vladislav, Seppo, Aleksandr
Work practices Configuration management Requirements elicitation and analysis Architecture design Pair programming Project progress tracking and control (Earned value calculations) X-TremeIT Valeria, Konstantin, Roman, Olesia, Vladislav, Seppo, Aleksandr

11 Results of the iteration
New documents Technical specifications Test cases specifications Test report Progress report UML class diagram Other testing related documents test log Test Cases Matrix Updated documents Project plan Requirements document X-TremeIT Valeria, Konstantin, Roman, Olesia, Vladislav, Seppo, Aleksandr

12 Architecture design & technical specifications
UML class diagram X-TremeIT Valeria, Konstantin, Roman, Olesia, Vladislav, Seppo, Aleksandr

13 Valeria, Konstantin, Roman, Olesia, Vladislav, Seppo, Aleksandr
Software demo GUI Communications Engine X-TremeIT Valeria, Konstantin, Roman, Olesia, Vladislav, Seppo, Aleksandr

14 Plan for the next iteration
Goals: Test cases and testing of GUI Integrate system modules Implement more use cases Creating objects – to be updated with more object types Add text box to objects Removing objects Removing dependencies Saving process diagram Saving process diagram to XML database Removing process diagram Viewing process diagram Printing process diagram Testing User manual X-TremeIT Valeria, Konstantin, Roman, Olesia, Vladislav, Seppo, Aleksandr

15 Plan for the next iteration
Deliveries: Implemented software Updated: project plan requirements document technical specification Test cases Test report User’s manual Progress report X-TremeIT Valeria, Konstantin, Roman, Olesia, Vladislav, Seppo, Aleksandr

16 Plan for the next iteration
X-TremeIT Valeria, Konstantin, Roman, Olesia, Vladislav, Seppo, Aleksandr

17 Valeria, Konstantin, Roman, Olesia, Vladislav, Seppo, Aleksandr
Schedule Week 52 iD GUI test cases and testing report Vlad & Roman Integration session (group meeting) All iDL Modules integration Integration test cases Olesia & Lera iDL Draft version of user manual Seppo & Roma Week 2, 2004 Group meeting Week 3 Deliver system to customer for possible feedback  All Week 5 iD: Use cases implemented Week 6 iDL : Testing of implemented use cases ALL User manual, final version for I2 phase Seppo DL: I2 documentation delivery Week 7 Project review All  X-TremeIT Valeria, Konstantin, Roman, Olesia, Vladislav, Seppo, Aleksandr

18 Valeria, Konstantin, Roman, Olesia, Vladislav, Seppo, Aleksandr
Thank you! Questions, comments? X-TremeIT Valeria, Konstantin, Roman, Olesia, Vladislav, Seppo, Aleksandr