Presentation is loading. Please wait.

Presentation is loading. Please wait.

Chuck starts the presentation Charles (Chuck) Gullakson, P.E.

Similar presentations


Presentation on theme: "Chuck starts the presentation Charles (Chuck) Gullakson, P.E."— Presentation transcript:

1 Use of Progressive Design-Build to Deliver Infrastructure Upgrades to a Class-1 Freight Corridor
Chuck starts the presentation Charles (Chuck) Gullakson, P.E. CSX Transportation Philip Sheridan, P.E., DBIA Clark Civil, LLC

2 Agenda CSX use of DBIA Best Practices and Progressive Design-Build for Phase 2 of National Gateway Initiative Follows on successful use of P-3 on Phase 1 of National Gateway Initiative Progressive Design-Build initially chosen due to some unique challenges facing the Virginia Avenue Tunnel Project in Washington, DC Based on success with Progressive Design-Build at VAT CSX expanded use for all remaining Phase 2 projects

3 Key Points One of the largest known uses of Progressive Design-Build by the Class 1 Rail Industry Pure Qualification Based Selection process was used to select a Contractor led Design-Build Team PDB was used to deliver projects ranging in size from less than $150,000 to over $250,000,000 PDB was used to leverage the strength of early contractor involvement to optimize the efficiency of the NEPA process and speed of project delivery

4 National Gateway: Critical to meeting future freight demands
61 clearance projects in 6 states and the District of Columbia to achieve 21’0” clearance Construction work varies from minor modifications to complete reconstruction of bridges, tunnels and other infrastructure (including VAT) New/enhanced terminals along the National Gateway corridors utilizing the latest technology Pittsburgh NW Ohio Transfer Yard Chicago New York Florida Boston St. Louis Memphis New Orleans Wilmington Hampton Roads Baltimore Chambersburg Current and Planned Double Stack Routes National Gateway Project

5 Virginia Avenue Tunnel
A single track, low clearance tunnel in Southeast DC 3800 feet long / 112+ years old A major bottleneck to east coast rail operations

6 CSX Virginia Avenue Tunnel History
History of Virginia Avenue Tunnel Original sections built between of rubble stone masonry (7th St. to 11th St., SE) In 1902 an Act of Congress passed that required realignment of most rail traffic in Washington, DC Between balance of tunnel built of brick, cubic stone and unreinforced concrete masonry (2nd St. to 8th St, SE)

7 CSX Virginia Avenue Tunnel History
History of Tunnel Originally contained two tracks Approximately 3,800 feet long By 1930s – was single tracked due to increases railcar sizes, creating a bottleneck on network Insufficient vertical clearance for double stack intermodal freight trains (18’ +/- vs. 21’ needed) Ever increasing maintenance costs as tunnel neared end of its useful life – 350’ section collapsed in 1985

8 CSX Virginia Avenue Tunnel History
1904 Tunnel Construction

9 CSX Virginia Avenue Tunnel History
1904 Tunnel Construction

10 Concerns Driving Need for Replacement
Need to improve overall rail fluidity and efficiencies over the network to better serve CSX’s customers CSX was seeing ever increasing need for: More Frequent Structural Inspections Periodic Track Reconstruction Cleaning of Drainage Structures in Tunnel Replacement of Sump Pump Systems

11 Key Challenges that drove decision to use PDB
Project location in a dense urban environment Close proximity to residences, government offices, businesses and Interstate highway Age, condition and material of existing tunnel Complexity of existing public utilities Need to use construction methodologies that assured ability to maintain active rail traffic

12 Why Use PDB? PDB was selected to leverage the strength of early contractor involvement to optimize the efficiency of the NEPA process and speed of project delivery CSX needed to obtain a Final NEPA determination without schedule risk or need to submit an EIS supplement to align with different methodologies Required Constructability From Beginning

13 PDB Procurement Process
CSX Issued RFQ’s to five pre-selected general contractors using a pure QBS selection process Goals: To find the Contractor led Design-Build Partner that could best work with CSX and their NEPA consultant team to work through the NEPA determination process To select an constructible build alternate to provide double stack, double track clearance through the VAT Project alignment that would not require a supplemental EIS evaluation

14 PDB Evaluation Process
Teams were evaluated on the following criteria: Safety Team Members Experience with Project Type Local Presence and Experience working in DC Knowledge of Local Permitting Processes Capabilities and depth of Available resources Tunnel construction experience Work on/around Class 1 rail corridors MOT in urban environments Each team had a one hour call with CSX procurement team where project goals were explained to the proposers prior to submission of RFQ responses

15 PDB Selection Process Qualification Proposals were evaluated by a cross disciplinary group at CSX including: Construction, Engineering, Environmental, Legal, Operations and Procurement Following ranking of Proposals each team was required to make an Oral Presentation to the Evaluation Committee followed by Q&A Final award was made following Oral Presentations Selected Design-Build Team was working with NEPA team within two weeks of award

16 Selection Timeline Recap
June 28, Calls to Contractors July 22, RFQ’s Distributed August 23, Qualifications Received August 31, Oral Interviews September 8, Selection Made September 14, st Public Scoping Session October 3, Step 1 Negotiations Complete

17 Invited Contractor 1st Steps
Upon receipt of first contact by CSX the contractor had to work rapidly to select a lead design partner and assemble a core team of highly qualified individuals who would lead the team in development of RFQ response and oral presentation Chuck hands off to Phil

18 Defining Win Themes Quickly identified several key themes necessary to be successful proposer Knowledge of construction in the Project market Past track record of successfully obtaining NEPA approvals Local presence with appreciation of working closely with district agencies and the community (our backyard) Strong understanding of Design-Build Best Practices and Progressive Design Build delivery method Highly collaborative project leaders truly committed to a single Team approach Ability to self perform critical aspects of the work as part of risk management approach Phil

19 Working Together Upon selection, CSX Team quickly developed a 2 Step approach to the contract Step 1 - Professional Services style contract that required Design- Builder to provide technical support to CSX and their EIS Prep Team Step 2 - GMP Design-Build contract to construct the preferred alternative from the Record of Decision

20 Step 1 Scope of Work Alternative concept development
Preliminary scheduling and budgeting Geotechnical and environmental field sampling Extensive existing condition surveys Preparation of numerous technical studies and reports such as traffic analysis, SOE schemes, environmental impact mitigation measures, etc. Providing subject matter expertise support at public hearings and meetings with FHWA & DDOT

21 VAT NEPA Timeline Extensive community engagement began in mid-2000s
Over 200 meetings with the public, government agencies, elected officials Federal NEPA process began in Summer 2011 “Federal action” triggered by use of federal air-rights, I-695 ramp impacts Lead federal agency – FHWA Lead local agency – District-of-Columbia DOT Started as an EA in Fall 2011, was changed to EIS in Summer 2012 11 initial concepts with 4 retained in the EIS (including “no-build”) Draft EIS – Published July 2013 Final EIS with Preferred Alternative – Published June 2014 Record-of-Decision (ROD) – Published November 2014 Construction NTP Issued in May 2015 153 NEPA mitigation commitments in total

22 Step 2 GMP Negotiations During preparation of Final EIS document CSX and Design-Builder successfully negotiated the Step 2 GMP contract This assured the team would be able to start final design immediately should a build alternative be selected This approach was necessary to help in expediting delivery of the project, while efficiently addressing NEPA commitments and local construction permitting processes

23 Step 2 GMP Negotiations Step 2 GMP contract utilized DBIA’s Standard Documents 530 Standard form of Agreement 535 Standard form of General Conditions Key features Shared savings clause Portion of DB fee is earned via incentive payments awarded based on a quarterly evaluation of Design-Builder’s performance on key metrics

24 Execution of New CSX Virginia Avenue Tunnel
Selected Alternative was one of three “on-line” concepts that called for construction of a new tunnel adjacent to the existing one Tunnel reconstruction is followed by complete reconstruction of the surface roadways including significant betterments required as part of the mitigation commitments

25 Sequence of Construction

26 Sequence of Construction
To Richmond / East coast Ports To Pittsburgh / Chicago / Baltimore 2nd New Tunnel I-695 Columns I-695 Piers and Straddle-Bents Original 1870 / 1904 Tunnel 1st New Tunnel

27 CSX Virginia Avenue Tunnel
Evaluated 11 preliminary concepts In-depth analysis of 3 build alternatives for EIS leading to selection of a preferred build alternative Able to start construction within 6 months of Record of Decision

28 Coordination with agencies and outside parties
DDOT DCRA DCSHPO DGS DPR DOEE DSLBD ANC’s NAVFAC / Marines NCPC Garfield park Southeast BID Barracks row UFA Nationals ballpark Architect of the capitol DC Water Washington Gas Pepco Verizon Comcast DC Street light and signal Zayo Adjacent construction projects Adjacent property owners

29 Key Features of New Tunnel
21’-3” Vertical clearance & 9’ horizontal clearance Structure designed for AASHTO HS-25 Drilled piles for SOE and secant pile walls Intermediate access points from surface with cross passages in tunnel Improved drainage systems, full waterproof wrap Safety inspection walkway/power &comm. duct bank LED lighting/ventilation fans/backup generators PTC communication compatible Extensive security measures

30 Project Features and Challenges
Tiber Creek Sewer – spandrel arch bridge 6th Street siphon Utility relocation and support in place Marine chiller underpinning Six cross street bridges & multiple MOT changes Phase 1 Tunnel demolition under live traffic Remnants of abandoned 1872 tunnel Working in a very dense urban environment Working in the public space - DDOT

31 Phase 1 Tunnel Demolition

32 Work Adjacent to Active Tracks

33 “Four-level” Crossing at Tiber Creek
(I-695 above 2nd Street) 14’ 6”

34 Phase 1 Trench Through Neighborhood

35 Concrete Wall Form Traveler

36 Phase 2 Demolition

37 Phase 2 Demolition

38 Schedule Overview As of March, 2017 Phase 1 Milestone of first tunnel running double stacks cars was reached 1 month early on December 23, 2016

39 Keys to Success to date Commitment to Safety Strong collaboration Ongoing value engineering Don’t let issues linger, elevate timely Prompt owner decision making Co-location (contractor/designer/owner) Work as a single team focused on delivering BEST VALUE which we have defined as follows: The proper balance of cost, schedule, risk and certainty of outcome for all parties

40 CSX National Gateway Initiative Phase 2
CSX modified previous Two Step Progressive Design-Build contract format to have a master contract for 11 initial clearance projects with each project being performed under a task order that spelled out the specific contract conditions for delivery Ultimately used to clear 17 sites to date Work varied from minor modifications to complete reconstructions The task order contract format allowed CSX to add new tasks (projects) rapidly without needing to go through individual contract negotiations

41 CSX National Gateway Initiative Phase 2
Contractor led Design-Build team working with two different lead designers progressed each project through initial design development and permitting under the Step 1 Professional Service style Agreement portion of the contract At a mutually agreed point between CSX and Design-Builder a Step 2 task order was executed to deliver final design and construction services

42 CSX National Gateway Initiative Phase 2
Each task order had provisions for the final method of delivery and contract format: Lump Sum Design-Build GMP Design-Build Construction Manager at Risk Method selected generally varied on the risk sharing approach and the amount of self perform work being done by the Design-Builder

43 CSX National Gateway Initiative Phase 2
17 locations cleared in VA, WV, MD and DC 3 abandoned bridge removals 3 remove/replace overhead highway bridges 6 track lowering's beneath bridges 2 bridge raises (1 highway/1 railroad) 1 mountain tunnel crown raise 2 mountain tunnel invert lowering's All Projects were completed on schedule or early All Projects were completed within the agreed budgets

44 Progressive Design-Build Benefits
Flexibility to deliver projects ranging in size from less than $150,000 to over $250,000,000 Leverages the strength of early contractor involvement to optimize the efficiency of the NEPA process Appropriately balances project risks and speed of project delivery

45 Progressive Design-Build Benefits
Success of PDB requires highly collaborative Project Teams which are committed to shared risks and rewards Success of PDB requires open and clear lines of communication at all Project Levels Success of PDB requires regular evaluation and feedback of Team performance both ways

46 Baltimore Clearance Improvement Program
Achieve Double Stack Vertical Clearance through Baltimore City Howard Street Tunnel 8,703 Ft. Long Build Primarily in Ten (10) Other Obstructions between HST and Seagirt Terminal Three (3) Bridge Modifications Seven (7) Track Lowering Sites Seeking Public Funding for Construction Start

47 Baltimore Clearance Improvement Program
Howard Street Tunnel Bridge Modifications North Ave. Guilford Rd. Harford Rd. Track Lowering Sites Mt. Royal Station MTA Bridge Sisson St. Huntington Ave. Charles St. St. Paul/Calvert St. Barclay St.

48 First Double Stack Train through New Tunnel December 23, 2016
QUESTIONS First Double Stack Train through New Tunnel December 23, 2016


Download ppt "Chuck starts the presentation Charles (Chuck) Gullakson, P.E."

Similar presentations


Ads by Google