Contractor HSE Training
HSE Training Module for Work Managers Released: 03/01/2013
2
Purpose of the Training Module
Work managers have a key role to play in contractor work safety through: – the provision of skilled staff, – the provision of appropriate tools and equipment for work, – organization and direction, – control and intervention, and – responsibility for compliance with HSE policy. Therefore, they should have a comprehensive knowledge of: – personnel, material and organizational conditions of work, – HSE-related statutory provisions, – MOL’s relevant HSE regulations, – workflow coordination, – etc.
3
MOL-side Actors of Construction Works
Branches that order development and maintenance work. Construction works are done off their premises. - Oil exploration and extraction - Production (Refineries and TVK) - Logistics (base sites, road and rail refueling stations) - Retail (filling stations) Branches Development projects MOL/TVK organization organizing and coordinating development projects. MOL-side contract administrator and project manager. Petrolszolg MOL subsidiary organizing, coordinating and partly implementing maintenance works. MOL-side contract administrator and project manager. FF & EBK MOL/TVK’s central HSE organization in charge of laying down HSE regulations, assisting contractors in the interpretation thereof and monitoring compliance.
4
Contractual HSE Requirements
An independent annex that contains MOL’s HSE regulations, including - Legislative requirements, and - MOL regulations (may contain provisions that are even more stringent than legislative ones!) The work manager is required to become thoroughly aware of all requirements set out in the HSE Annex to the contract! General Contractor The General Contractor should attach the HSE Annex with its subcontract agreements! Subconttractor Subcontractor
5
Work Manager’s Responsibilities Following From the Health & Safety Act
The H&S Act makes it the duty of employers to comply with the statutory requirements for safety at work without posing any hazard to human health, in accordance with the employees’ responsibilities (duties). Employers must bear the primary responsibility as they are required to provide all tools and means necessary for creating proper HSE conditions. While managing field work, the on-site management personnel should assume to some extent these responsibilities of the employer.
6
Requirements Set Out In the Health & Safety Plan
Pursuant to Decree No. 4/2002 SzCsM-EüM, a Health & Safety Plan should be prepared for each building and construction project. The plan must be drawn up as early as in the design phase, and then regularly updated with changes that may occur in the subsequent construction phase. As to the content of the plan, the author should take due account of the relevant legislative requirements as well as the following aspects: the course of work processes in time, harmonization of concurrent works keeping their specific rules in mind, identification of the activities that may be performed only one after the other, determination of site and work-specific health & safety requirements in view of the specificities of the building site, and identification of a set of specific measures aimed at eliminating hazards present at the building site. If, according to MOL regulations, a particular job is also subject to the condition that an HSE Plan must be prepared for it, both plans should be included in a common document!
7
Health & Safety Coordinator
Verifies the content of the H&S Plan and ensures compliance with the plan. Coordinates the implementation of the general principles of prevention and safety at work. Pays special attention to identifying concurrent and strictly consecutive work phases. Coordinates the anticipated implementation periods of various work phases or stages. Liaises with employers working on the building site simultaneously or in turns in order to coordinate their activities. In the event two or more contractors are working on a site, the H&S coordinator assumes some of the field work manager’s job tasks related to on-site coordination. It is the General Contractor’s duty and responsibility to appoint and employ a H&S coordinator. 7
8
Tasks and Responsibilities of the Work Manager (1)
- Regularly makes sure that the working conditions comply with the relevant requirements, and the emplyees are familiar with, and observe, the regulations pertaining to them (both legislative provisions and MOL/TVK requirements); - Cooperates with the operator in issuing work permits and ensures full compliance with the special requirements set out in the permits; - Ensures that all work sites, tools and equipment comply with the relevant health & safety and fire protection requirements; - Ensures that employees acquire all work-related skills and knowledge and comply with the relevant regulations; and - Ensures that employees receive and use appropriate work and personal protective equipment that are replaced if necessary.
9
Tasks and Responsibilities of the Work Manager (2)
- Maintains order and discipline in his area; - Responsible for the safety of machinery, equipment and tools, as well as for conducting periodic reviews and the availability of the supporting documentation on the site; - Ensures that Hungarian documents of machinery and equipment, technology descriptions and PPE items are kept available and accessible on the site, and are verifiably used as materials of training that all employees receive; and - Responsible for checking work sites and work processes so as to ensure that they permanently comply with health and safety requirements for work.
10
Tasks and Responsibilities of the Work Manager (3)
- Arranges for the provision of drinking water and warm-up beverages as required and ensures that employees take the mandatory rest periods; - Responsible for the provision of all personal and material conditions for the availability of on-site first aid; and - Ensures that employees cease to work immediately in case of any serious and imminent threat to health and safety and leave for a safe place.
11
The Manner and Cases of Substituting the Work Manager
The work manager may leave the work area only if absolutely necessary and for short periods only. If the work manager is temporarily leaving the working site, he must appoint an appropriate employee to work as a substitute (give him the armband) and make it known to the entire staff. The work manager is obliged to wear a red armband throughout the duration of the working time. 11
12
Liaison With MOL Representatives
The work manager is required to ensure his permanent availability to MOL’s designated contact person. The operator’s area manager, the responsible project manager or the authorizing official issuing the work permit may work as an area contact person. The work manager is required to report to MOL’s contact person if: - MOL’s intervention or assistance is needed, - any danger or disorder is observed during work, - there is any change regarding those described in the work permit, and - any HSE event occurs.
13
HSE Plan Purpose: To ensure that the general contractor and/or subcontractor(s) in charge of construction reconsider the work processes ahead of them, the technology-specific circumstances and potential hazards for HSE-critical works, and assess resource intensity (work, personal protection and safety equipment) and personal competence requirements of the project. Author: The General Contractor or subcontractor performing work should prepare and submit the HSE Plan before starting their actual work. Approvers: The representative of the operator affected by the project and MOL FF&EBK’s competent expert.
14
Content Elements of the HSE Plan
- Who will do exactly what by when? - What kind of work, protective and safety equipment will they use? - Who will manage work? - What individual steps will be taken to make up work as a whole? - What risks are identified in relation to each work process, and what measures are taken to reduce such risks (JSA)? Identification of the location and the parties involved Identification of work activities Tools and equipment Protective clothing and personal protective equipment Required qualifications (HSE competence) Boundaries of the working area Subcontractors’ management Supervision, controls Waste management Detailed work instruction that renders the entire work process transparent Risk analysis for workflow steps Risk reducing measures The work manager is required to become familiar with the content of the HSE Plan and ensure that all employees are aware of and understand the same!
15
Site Handover Procedure
Participants: Operator’s representative or his/her substitute (authorizing official), Contractor’s site manager or work manager (in charge of construction) General Contractor’s (or Petrolszolg’s) site manager or representative, MOL FF&EBK’s representative, Project representative (for projects), Contractor’s H&S coordinator (where appropriate). Criteria: Availability of the approved HSE Plan (required), Working site prepared (delimited) by the operator, Preliminary walkthrough of the working site. Handover Protocol A written document (with fixed format), Valid when signed by all parties concerned, Also designed to document the return of the site on completion of work and record HSE performance assessment results. The successful site handover procedure itself is not an authorization for starting work (a valid work permit is required).
16
Site Handover Procedure / Operator’s Tasks
Preparation of the work area involved / exploration, elimination and posting of all hazardous energies. Is there any other prescheduled on-site work in addition to the activities related to the site handover procedure? If so, it should always be reported to the contractor by making an entry in the Handover Protocol. Identification of the types of permits required for work and the persons (employee group) who are authorized to issue the permits identified. Information (signals, assembly point, important telephone numbers, etc.) for emergencies. Specification of what other tests and inspections (electrical/mechanical review, pressure test, etc.) must be carried out and documented to restart technology lines/machinery on completion of the job at issue. If, during the site handover procedure, such tests and inspections are specified, the relevant test reports must be available for the return of the site as restarting the technology lines/machinery is subject to the availability of the documentary evidence of tests. It is up to the Operator to specify what tests and inspections to conduct, and the (General) Contractor, implementing the job, is required to perform them. Laying down traffic rules for the site. It should also be specified here where and under what conditions road vehicles and mobile machinery are allowed to stop (be parked) and perform any work. Road closures and the standard procedure for ordering closures should also be recorded in this section. Determination of the locations for the installation of containers by the Contractor with details of the properly documented authorization of installation.
17
Site Handover Procedure / (General) Contractor’s Tasks
Statement as to the preparation and approval of the HSE Plan (when and by whom it was approved). Site handover is not allowed for lack of an approved HSE Plan! Statement on the prospective subcontractors. Statement as to whether the Contractor intends to install containers or mobile toilets on the site taken into its possession, and what purpose the containers are intended for (e.g. for use as warming shelters or stores). Statement with the name of the contact person whom the Operator can liaise with and consult on work-related issues. On completion of work, performance of the tests and inspections required by the Operator (electrical/mechanical reviews, pressure tests, etc.) for the return of the site, recording test and inspection results and handing over the report to the Operator.
18
Content of the Work Order
Key content elements of the Work Order: SAP SM Order No.: relates to one job Order Number: Multiple orders can belong under a given SM number for various works Contractor Data Short name of the work ordered For a job to perform (a Work Permit to apply for), the Contractor must in possession of a valid Work Order
19
”Assignment” Form Statement on: proper staff qualifications,
the suitability of tools and equipment. Authorization: to perform (hazardous) work activities Issued and signed by the employer Brought to the site by the work manager So many employers, so many ”mandates” Required for all types of work Issued for a particular job Sequentially numbered Duplicate List of names and equipment (both can be completed with continuation sheets)
20
Any work on the site is subject to authorization
”Work Permit” Form (1) It is the work manager’s duty to apply for a Work Permit if the following conditions are known and met: Location and content of work Proper staffing level and appropriate tools and equipment Work Order number Completed Assignment form Any work on the site is subject to authorization The Work Permit is issued by MOL/TVK’s area manager: Type of work (normal, involving fire hazards, in confined spaces with entry, drive-in permit) Hazards and risks Relates tasks to perform (initial gas concentration measurement, compartmentation, delimitation, etc.) Precautionary measures, protective equipment (permanent gas concentration measurement, etc.) Valid for a fixed term but can be extended The issuer of the permit and the work manager jointly interpret the content of the Work Permit.
21
”Work Permit” Form (2) The permit issuer may conduct site visits jointly with the work manager whenever he/she deems it necessary to interpret the conditions and requirements set out in the Work Permit. The work manager takes over the Work Permit and proceeds as follows: - Ensures that the conditions and requirements set out in the Work Permit are met, - Interprets the requirements specified in the Work Permit jointly with his/her subordinates (daily toolbox talks), - Expects the employees under his/her command to meet the requirements and monitors proper compliance, - Retains and keeps the Work Permit readily available at the working site, - Presents the Work Permit on request whenever an inspection is conducted. Any work on the site is subject to authorization Not just a piece of paper – never work without it!
22
”Work Permit” Form (3) For normal work For work involving fire hazards
In such cases, the issue of the Work Permit is always preceded by an initial gas concentration measurement by MOL/TVK. The permit may be granted only if the measured gas concentration is below the limit value. For work in confined spaces For driving in
23
Work Permit
24
HSE High Risk Work Activities - List
Work involving fire hazards Work at height Work in confined spaces Detailed rules for these work activities are set forth in relevant legislation, and also form part of MOL’s training program. Critical mechanical lifting Earthwork Opening containers of hazardous substances Chemical cleaning High-pressure (300 bar) cleaning, abrasive blasting
25
Lifting Operations I The lifting equipment operator may only use lifting equipment and lifting accessories that have: OHS compliance certificates, OHS commissioning licenses (issued by the operator), Installation specifications (plans) for installable lifting machinery, Operating instructions in Hungarian, Load diagrams (loadability for boom outreach), Lifting machine logs (kept regularly) as a documentary evidence of regular maintenance, Documented periodic reviews (valid till the completion date of contract work): Shift test (documented by the operator in the lifting machine log), Structural inspection (at regular intervals according to the industrial group number), Overhaul inspection at regular intervals according to the industrial group number), and Safety review (every 5 years). Lifting equipment must be operated only by personnel: authorized to operate this type of equipment by the employer in writing, holding valid statutory hoisting machine operator license (light or heavy machine operator license) and passed a type exam, and found medically fit. 25
26
Prepared by the company performing the lifting!!!!
Lifting Operations II (Lifting Plan) What should be included in the Lifting Plan? Identification of the lifting equipment, Rated loads specified for various boom radiuses and inclination angles (load diagram), Load lifter attachments used, Weight of the load to be lifted, Representation of the load path, Method of using outrigger stabilizers, additional safety measures, Identification of staff members participating in the lifting operation (slinger, signaller), Demarcation of the area of crane operation, method of delineation. When to prepare a Lifting Plan? Multiple cranes operating within each other’s radius of action, Combined lifting using multiple cranes, Use of lifting beam or lifting frame, Lifting of persons during crane operation, The load to be lifted exceeds 65% of the rated load Employees working in the immediate vicinity of the suspended load, Lifting near or above transmission lines or inhabited buildings (structures falling within the crane’s radius of action. Figyelem = Attention! Vége = Over Vigyázz = Look out! Állj = Stop! Fel = Up Le = Down Előre = Forward Hátra = Backward Jobbra = To the right Balra = To the left Vízszintes távolság = Horizontal distance Függőleges távolság = Vertical distance Prepared by the company performing the lifting!!!! 26
27
Lifting Operations III
DO NOT stay within the radius of action of the lifting equipment and DO NOT walk or work under a suspended load while a lifting operation is in progress! The possibility of communication between staff members involved in a lifting operation should be continuously provided throughout the operation. It is the duty and responsibility of the company in charge of the lifting operations to provide appropriate means of communication. Unauthorized access to the working site affected by the lifting operation should be prevented by fencing or personal supervision (it is a task of the company responsible for the lifting operations). Lifting machinery should be installed on firm ground (mobile cranes stabilized by outriggers) against tipping or accidental displacement. The load bearing capacity of the soil should be sufficient to support the combined load made up of the machine’s dead weight and the weight of the suspended load. Each staff member who works as a slinger must have taken a slinger course with an exam that is still valid. If the lifting machine operator does not have clear visibility of the lifting path, a banksman should be appointed. The use of a banksman is absolutely necessary for combined lifting operations using multiple lifting equipment even if the lifting path is clearly visible for the crane operators. Always use lifting machinery with load capacity corresponding to the weight of the load to be lifted. DO NOT overload the lifting equipment during the lifting operation (deviate from boom radius-related load ratings) (if the crane is not equipped with overload protection). The lifting path and the place of landing should be cleared of any obstacles. Accidental or unauthorized use of lifting equipment should be excluded. DO NOT leave the ignition key in an unattended, out-of-use lifting equipment! The presence of a staff of at least 2 is required for a lifting operation. One of them is the lifting machine operator, while the other one may as well be a MOL employee. However, for such a lineup, he must be present in the area of lifting throughout the lifting operation. 27
28
Work In Confined Spaces I
Pre-entry Tasks: Exclusion, elimination and posting of hazardous substances and energies (if possible), Preparation of an HSE Plan (a duty of those responsible for working in the confined space), Site handover procedure, Preliminary atmospheric measurement (where hazardous gases and vapors are expected to appear, or oxygen deficiency may occur), Issue of the Work Permit (the Operator should be authorized to issue entry permits), ”Assignment” for the employees who are responsible for working in a confined space (their employer will issue it for the entry). Any activity that can be done by leaning inside or entering equipment or confined spaces not specifically designed for human habitation is deemed to be a work activity in confined spaces with entry. Such spaces include among others: Tanks, Columns, Elevator shafts, Pits (e.g. water meter pits), Sewers, Boilers, Trenches (from 1.2 m) Confined spaces, etc. 28
29
Work In Confined Spaces II
Staff number needed for the entry To be specified in the HSE Plan and Work Permit in view of the related hazards (CH contamination, type of the activity) and the relevant standard requirements. Specification of the number of staff members who will enter the confined space by access points Specification of the number of watchers by access points. Protective and safety equipment required for entry: Protective clothing (with the protective capabilities specified in the permit), Protective footwear (ankle shoes, boots, high boots), Personal atmospheric meter (if included in the permit), Supplied air respirators in case of the imminent danger of inhaling hazardous substances, Safety devices (harness, signaling rope and lifeline), Aids used to help access to dangerous spaces and work in them (e.g. ladders, scaffold and alpine devices). 29
30
Work In Confined Spaces III
Personal Criteria Personal criteria for working in confined spaces: Turned 18, Mental and physical fitness for entry into confined spaces, external supervision and rescue work if necessary, Documented periodic medical tests proving fitness for a particular job (e.g. for cleaning tanks), Appropriate professional qualifications and experience for the job (e.g. tank inspector), Participation in the required in-house HSE training course, with successful HSE exam, A staff of at least three (3). Continuous concentration measurements in atmospheric air during work in confined spaces (if specified in the permit) 30
31
Work Involving Fire Hazards I
Any activity that poses ignition hazards (e.g. by ignition temperature, generation of sparks or flames) to substances in the environment and technologies is deemed to involve fire hazards. They include e.g.: Welding Flame cutting Soldering Use of quick cutters and angle grinders (flex), Any work involving open flames, etc. A work permit issued for activities involving fire hazards does not lift the ban on smoking! 31
32
Work Involving Fire Hazards II
Written assignment for a particular job from the responsible workplace manager of the employee/personnel in charge of work involving fire hazards, Meeting personal criteria Turned 18, Mental and physical fitness for the job, Valid medical fitness certificate, Appropriate professional qualifications for the job (e.g. certified welder for welding works), Passed fire safety exam (corresponding to the type of work as provided for by law), Taking an on-site HSE course that covers a particular plant area, Preliminary concentration measurements in atmospheric air (only in areas with CH contamination), Availability of personal gas detector for continuous atmospheric measurements (in case of activities involving fire hazards, continuous gas concentration measurements are required only on premises working with CHs – the measured values may not exceed the suspension limit), A staff of at least 2 (hazardous work that may not be performed alone – a watcher is required who can intervene if necessary and help in rescue operations), An HSE Plan for concurrent parallel activities involving fire hazards, which contains a risk analysis for the activities, At least 1 fire extinguisher in good repair verified by regular inspections (the number and type of fire extinguishers should be determined in view of the intensity and features of potential fires assumed to break out at the work area as a result of on-site work activities). 32
33
Work Involving Fire Hazards III
Only properly authorized officials have the right to issue permits (for work activities involving fire hazards). All combustible materials must be removed from the physical proximity (within a radius of 10 m) of the work activities involving fire hazards. When working in a CH area, every sewer opening and shaft manhole on the site and within a radius of plus 20 m should be covered with a gastight cover (10 cm layer of sand and canvas). Work should be discontinued if the flammable gas concentration exceeds 20% of the lower explosion limit (LEL) in open spaces and buildings for human habitation or 5% LEL in confined spaces, i.e. tanks or shafts. In the event of doing any work at height involving fire hazards (e.g. with spark generation), special attention should be paid to the premises and working areas situated below. Immediately before starting hot works with open flames and exposed arc (welding, flame cutting, etc.), smoke, flame or heat detectors installed within the area of action of such work (in rooms and structures) can be switched off to avoid false alarms for the duration of the work activities at issue with the permission of the area operator. On completion of the work activity, the permit issuer must ensure that the protection system (smoke, flame or heat detectors) is switched back again once it has been deenergized.. 33
34
Collective protection should be preferred over individual one!
Work At Height I Any activity where the working level is located at least 2 meters or more above ground, and there is no fixed protection against fall from height (e.g. at building sites, at least a toeboard, a center board and a handrail or an equivalent solution must be provided) is deemed to be work at height. Collective protection should be preferred over individual one! 34
35
Work At Height II When working at height, access to the place of work and work itself can be difficult and dangerous, so the following requirements must be strictly observed: As far as possible, the job is to be performed from a fixed platform (installed work station) where the employee is protected from falling down by an at least 1 m high double-row railing. For lack of an installed work station, the following options are available: Construction of a standard scaffold (standard walking surface and double-row handrail with toeboard) where both the access path to the work area and the place of work are safe for climbing and working, Use of ladders to access the working level and perform short-duration routine tasks (using simple and light tools, e.g. screwdriver) up to a height of 2m, and Use of personal fall protection equipment. When opting for the use of individual protective equipment, full body harnesses should always be worn as mandatory equipment. The method of connecting the harness to the anchor point is to be chosen according to the type of work. This can be done using a positioning Y rope lanyard or a fall arrest fastened to an overhead anchor point or ropeway. In selecting the personal protective equipment for working at height, the typical features of the place of work should always be taken into account. DO NOT use work safety belt as fall protection equipment! 35
36
Work At Height III In the event where working from an elevated place over 2m is only possible by tearing down safety structures (handrails) or by bending over them, the use of fall protection equipment (full body harness and Y rope lanyard or fall arrest equipment) is an absolute must. The anchor point should be selected so as to ensure that its rated load bearing capacity is at least 1000 kg, and is located over the employee. It is the task of the person directly supervising work to select the anchorage points by providing information to, and in consultation with, the operator. In selecting the proper fall arrest equipment, attention should be paid to the height of the working level and the point of anchorage as compared to the ground level (or the position of the structures below it) in order to ensure that the arrest can stop employee’s fall before reaching the ground, with no injury to him. Only standard ropes (e.g. Y rope lanyards) can be used to fasten the full body harness attachment point (front or rear) to the anchor point above it. DO NOT use non-certified ropes for this purpose. Working at height is considered a dangerous activity and, therefore, should be carried out by at least 2 people. They must be medically fit (for working at height) and properly trained in the use of the protective equipment. DO NOT use protective equipment when damaged or not subjected to periodic inspections! 36
37
Work At Height IV When working at height, tools, parts and machinery must be placed (secured for machines) so that they do not pose additional risk by falling down to the work area below. Walking or driving under the elevated work area should be restricted by work organization measures or completely prohibited in such case. If machinery or equipment are installed below the working level, they must be protected from falling objects. It is the duty and responsibility of the company that performs work to select appropriate personal protective equipment for working at height, make them available to the employees, carry out their periodic inspections and conduct documented training in their proper use. Certification documents of the protective equipment as well as documents proving the implementation of periodic inspections should be kept readily available for any inspection at the place of work. In the event of using ladders, always maintain 3 points of contact when climbing up and down. DO NOT carry tools or materials in your hands when climbing a ladder. Instead, use for this purpose a tool bag or a special case. Erect scaffolds and ladders on a firm and level plane, and secure them against tipping if necessary. 37
38
Scaffold Erection I Construction scaffoldings should be designed, erected and inspected, as well as HSE commissioning activities concerning scaffolds performed in full conformity with the provisions of Decree No. 4/2002 SzCsM-EüM and other related legislation, also in view of the requirements set out in the applicable Hungarian standards. Every scaffold should be properly designed, erected and maintained so as to prevent collapse or accidental displacement when properly used. The working platforms, gangways and stairways of scaffolds should be of such dimensions and so constructed and guarded as to protect employees and others within the range of work operations against falling or being endangered by falling objects. All working levels, passageways and gangways above 2m height should be equipped with guardrails (1m high triple rails with less than 0.3m spacing, toeboard, center board and handrail, or other equivalent solution). Dimensions, shape and arrangement of scaffolds must correspond to the type of work to do, should comply with the design load (max. load capacity should be posted), and must allow employees to work and move in safety. 38
39
Scaffold Erection II A Scaffold Plan should be prepared for every scaffold with a load capacity in excess of 2000 N/m2 or height over 6m. For smaller scaffolds, structural outline drawings are required. For the issue of permits for working on installed scaffolds, the scaffold plan, structural outline drawings and the written documentation of the preliminary inspection should always be made available to the permit issuer (operator) for inspection. The issue of a work permit is strictly subject to the availability of the above-mentioned documents. Before putting into use, mobile scaffoldings (running on wheels) should be secured against displacement (with brake). When moving a mobile scaffold, pay attention to the following aspects: DO NOT move the scaffold with employees on board of it! The planned route of scaffold movement should be secured in advance (in terms of height, any overhead electrical line, etc.). If necessary, reduce the height of the scaffold. Check the path of scaffold movement for any overhead line hanging in, technology component and the smoothness of the path. For custom-built scaffolds, every second story should be anchored to a fixed technology point against tipping. Only mechanisms rated for both tensile and compressive strains should be used for anchorage. DO NOT use soft iron wire for anchoring a scaffold. Scaffold platforms and decking may not be less than 0.6m in width. Platform width should be adapted to the spread width corresponding to scaffold frame. Scaffolds are to be stiffened in two planes perpendicular to one another (by incorporating cross members, i.e. Andrew’s crosses). To climb up and down the scaffold, use special access ladders or stairs that must be firmly secured against falling down. Do not use the stiffeners to access the working level on the scaffold. Scaffold erection requires a staff of at least 2. 39
40
Scaffold Erection III An inspection should check scaffolding for:
– Compliance with scaffold plans, – Stability of structural components (e.g. foundation, extensions, stiffening reinforcement and anchorage), and – Safety equipment (e.g. gangways, handrails, toeboards, load capacity, other labeling, fire protection, lightning protection, lighting). Scaffolding must be inspected by a competent person (an authorized employee of the company erecting the scaffold): Before it is put into use, After any structural alterations or withdrawal from use, After bad weather (storm), earthquake, etc., A written report must be prepared to document the inspection and its results. The report should also contain the requirements the scaffold has been tested to and a statement as to the scaffold’s compliance with relevant standard requirements and fitness for use, After any accident or other event likely to have affected its structural strength or stability, After extended periods of interruption in use (after 1 week, a repeated inspection and documentation is required). 40
41
Earthworks I Earthworks are manual or motorized activities intended to disturb and expose land surfaces on a scale from shallow manual digging to major complex excavations, using machinery, for buildings and large structures. Large-scale earthworks can pose significant risks (e.g. landslides, cave-in accidents or submersion in swampy areas, falling down, dangerous trench work, etc.). 41
42
Min. staffing requirement
Earthworks II The contractor should maintain the following minimum staffing level while performing earthworks: An HSE Plan should be prepared for each trench excavation of 1.2m or deeper during earthworks (manual or mechanical) on MOL premises, and the work area made available, within the framework of a site handover procedure, to the contractor in a documented manner before starting work. For trenches deeper than 1.2m, requirements for entry into confined spaces should also be taken into account. In the preparation of an HSE Plan, the following issues should also be addressed: method of excavating the trench (manual/mechanical), means of propping and shoring, staffing requirements, protective and safety equipment, routing of utility and other lines in the area (electricity, products, etc.) and requirements for their elimination. All employees concerned should be made familiar with the content of the HSE Plan in a documented manner. Activity Min. staffing requirement Manual earthworks down to a depth of 1.2m 2 Manual earthworks below 1.2m depth 3 Mechanical earthworks for any depth 42
43
Earthworks III Earthworks in progress:
For open trench depths ranging between 0.25 and 1.25m, a warning tape (employing a two-tone pattern of alternating red-white or yellow-black stripes) should be affixed at 1m height to warn those approaching to the trench of the possible hazard. For an open trench deeper than 1.25m, guardrails (min. 1 m high fixed guards e.g. of wooden plank structure designed to physically prevent falls into the trench) should be erected around the trench, at a distance of 1m from its edges. A Construction Log should be maintained while earthworks are in progress. The earthwork contractor is responsible for keeping the log. A Work Permit for earthworks may be issued only if: the HSE Plan is completed and approved (for 1.2m or deeper trenches), the site is handed over to the contractor (for 1.2m or deeper trenches), the staff is available for the earthworks in the required number, hazardous energy source locations (underground pipelines, power lines and control cables) on the area affected by earthworks are mapped and isolated if necessary, the conditions of entry into confined spaces are met (exclusively for 1.2m or deeper manual excavations), and calibrated instruments are available for the mandatory continuous measurement of atmospheric concentrations (continuous atmospheric measurements are not required in the only case where combustible gases are definitely not present on the site, and are not even expected to appear, e.g. for greenfield projects). 43
44
Earthworks (Mechanical) IV
It is prohibited to stay within the radius of operation of the earthmover or in the trench under excavation while mechanical earthworks are in progress. Accordingly, the following warning notice should be posted to both sides of the machine: ‘Danger!’ ‘Keep Away!’ When mechanical excavation works are under way, the earthmover is not allowed to come too close to the edge of the trench being dug so that no trench slides or collapses occur and not to expose itself to the risk of falling into the trench. This distance can be reduced if trench shoring is designed to support the additional load exerted by the machine. It is not allowed to install equipment and store heavy materials on the eroded banks of a trench. The edge of a pit (trench) may be loaded within its eroded banks only if the trench shoring structure is designed and rated to support the additional load. Once parked, an earthmover should be secured against accidental displacement before leaving it unattended. It must also be ensured that no unauthorized person can restart it (e.g. by taking the key out of the ignition). No person other than the driver of the earthmover can be carried on board of the machine unless it has a standard seat therefor, which is properly fixed, and can provide adequate protection for the person sitting on it against falling off or down. 44
45
Earthworks (Mechanical) V
If, in the area affected by earthworks, any hazardous energy is expected to be present (e.g. power lines, control cables, product pipelines, etc.), they must be explored and mapped in advance and, if possible, eliminated. No earthwork machine (including any of their accessories, e.g. shovel) may drive closer than 0.5 m to a crude oil or product pipeline. In such cases, exploration work should be continued by manual digging. An overhead electrical line can be approached by an earthmover or any of its accessories (e.g. boom) only by ensuring that the following safety clearances are always kept: If the safety clearances specified above cannot be maintained, the operator is required to take immediate measures in order to avoid the risk of electric shock. Such measures may include deenergization, line rerouting or work area demarcation. Rated Voltage Safety Clearance Up to 1000 V 1 kV to 110 kV 110 kV to 220 kV 220 kV to 380 kV Unknown voltages
46
Earthworks (Manual) VI
During manual earthworks, trenches should be constructed so that the excavated soil is prevented from running back into the trench (by forming 0.5m wide berms), trench sidewalls are secured against collapse and caving in (using appropriate shoring or sloping techniques), trench workers can, in emergency, escape from the trench in safety under any circumstances (mostly using a ladder, which should remain in place throughout the trenching work). The safety features applicable in trenching work (sloping angles, shoring, stepwise sidewalls) should be specified in view of the mechanical features of the soil. For 0.8 m or deeper trenches, their use is obligatory. Strutted trench deepening of the trench should be followed with strutting as required by soil quality (at every 1m in cledgy soils and every 0.5m in fitchery soils), The bottom width may not be less than 0.8m. Use accommodation ladders, properly secured against displacement, for climbing down to/up from trenches to a depth of max. 5m. For trenches deeper than 5m, stairs should be constructed. An accommodation ladder mounted in a trench should be of sufficient length to extend above ground level by min. 1m, ensuring safety for climbing up and down. 46
47
Earthwork (Manual) VII
For work trenches and pits, passageways should be constructed at every 200 meters as a minimum. The passageways should be at least 0.6 m in width. Passageways constructed over work trenches deeper than 1 m must be equipped with double-row handrails on both sides. Work pits located next to existing building foundations should be dug only to a depth that does not adversely affect the stability of the existing building or structure. 47
48
Providing Adequate Labor (Qualifications & Staff Number)
Appropriate staff number / planning Proper identification of job-related work processes Health and medical fitness Taking account of work loads, according to the relevant legislation, that require prohibition as being potentially harmful for the health of vulnerable groups (juveniles, women, etc.). Availability of activity-related special medical certificates (e.g. if an employee is fit for wearing respirator). Labor demand assigned to work processes Identification of qualifications, skills, capabilities and experience for work Mandatory fire safety exam Mandatory mine safety exam Basic and site-specific training for contractors with validity on MOL Group premises Work manager training with validity on MOL Group premises The key role of risk analyses Identification of hazardous activities Jobs that may not be performed alone Difficult & extraordinary conditions Provision of supervision for e.g. work in confined spaces Provision of rest times The work manager is responsible for ensuring that each and every work activity is done by a person qualified and authorized to do it.
49
Provision of Machinery & Equipment In Proper Quantity and Quality (1)
Decree No. 16/2008 (VIII. 30.) NFGM on Safety Requirements For and Compliance Certification of Machinery Proper identification of job-related work processes Transportation and handling Warehousing, storage and preservation Transformation of materials: processing machinery Energy conversion: machines and power engines Transformation of information: PCs, control & management systems The key role of risk analyses Obligatory compliance with legislative requirements for the safe use of machinery! EC declaration of conformity for machinery EC type examination certificates EC conformity marking Essential health and safety requirements Commissioning of hazardous work equipment Periodic safety reviews Technology specifications, work instructions and activity rules Hungarian operational documentation for the safe use of machinery
50
Provision of Machinery & Equipment In Proper Quantity and Quality (2)
Keeping machinery and work equipment in appropriate technical condition Technical condition and periodic reviews of hazardous machinery and equipment Inspection of electrical equipment for shock protection Control inspections of low-voltage and power current electrical equipment for protection against indirect contact (shock protection), checks of equipment by fitters, review of compliance with standards (protection switches, power tools and other electrical equipment) Making sure that a crane book is available for the lifting machines and is kept on a shift basis Periodic review of lifting equipment Use of explosion-proof equipment if appropriate ”Before using a machine or equipment made available to an employee, he/she is required to make sure that it is suitable for performing the work and does not pose any potential hazard.”
51
Provision of Machinery & Equipment In Proper Quantity and Quality (3)
General Rules Thorough knowledge of how to use and operate machines and work equipment according to type-specific instruction manuals, their safe handling and inherent hazards. Before using a machine or equipment made available to an employee, he/she is required to make sure that it is suitable for performing the work and does not pose any potential hazard. Before starting to work with an electrical equipment, always check the integrity of the housing and cables. If, during work, an employee observes any abnormal operating condition, or the machine or work equipment he/she uses becomes in any manner defective or damaged, he/she should immediately STOP working with the machine or equipment! Work should be suspended until the risk of accident is eliminated, and the defect must be notified to the competent executive on the site (or the manager in charge of the work). On completion of the work, all electrical machines and equipment should be powered down.
52
Checking Compliance & Adequacy of Labor and Machinery
Employee adequacy ”At least 18, healthy, medically fit and professionally competent person” Good health as well as medical and (if necessary) psychological fitness Appropriate skills and qualifications Small machine operator, Lifting equipment operator, Slinger, Crane operator, Fire safety exam, Welder certificate, Mine safety exam ADR, etc. Compliance of machinery According to the list of work equipment classified as hazardous pursuant to Decree No. 5/1993 MüM, identification of the scope of work activities that may not be performed alone. Validity of the inspections of machinery and work equipment. Shock protection review of electrical equipment. Control inspections of low-voltage and power current electrical equipment for protection against indirect contact (shock protection), checks of equipment by fitters, review of compliance with standards.
53
Gas Concentration Measurement (1)
Hazards of gases and vapors: - Potentially explosive, combustible gases (Ex): - Oxygen (Ox): Danger of suffocation in the absence of oxygen. Increased risk of ignition/auto-ignition in atmospheres rich in oxygen (pre- conditions of fire: oxygen, combustible materials and ignition spark) - Toxic gases (Tox): Without appropriate aids, no one can timely detect the presence of hazardous gases and their high concentrations. Personal monitoring: Usually, the personal gas concentration meter is stuck to the working clothes. It must be of rugged design, and should emit various alarm signals in case of emergency (tone, visual signal and vibration). Area monitoring: Here, the task is to check an area where several employees are working simultaneously. The gas concentration meter(s) should be installed at a well-thought-out central location. It is very important to ensure that the meter provides meaningful alerts (visual and tone) to capture attention. Work in confined spaces: Before commencing the work, check the space with a so-called preliminary measurement, and only then start working. Of course, personal monitoring measurements should also be maintain here, as well. Leak test: Leaks can occur everywhere where gases or liquids are stored/transported. Their earliest possible detection, identification and elimination is a task of utmost importance. Integrated pump devices can quickly detect any change in the atmospheric concentration of gases and, thereby, help to quickly locate leaks. When an alert is triggered (tone, visual, vibration), all activities should be stopped and the danger zone left.
54
Gas Concentration Measurement (2)
The contractor may either own or rent it*. BUMP test: Testing the meter for the measurement of gas concentrations corresponding to an etalon gas and the proper condition of its sensors. The test must be conducted every day! Use only appropriate test equipment for the test. At the end of the test, the test equipment should print out a certificate as to the condition of the meter (FAIL or PASS): Weight: 220 g Dimensions: 47 x 129 x 31 mm XXS sensor inputs Visual alarm Catalytic sensor Horn > 90 dB Segment indicator Okon – button Press to confirm alarms +M- - button Navigation in the menu *At certain MOL sites only
55
Provision of First Aid The contractor must ensure that the staff includes: qualified first aid providers at least 1 in each team, with both practical and theoretical knowledge (obtained in in-plant first aid training), the test certificate must be kept on site. First aid kit with content as per Standard MSZ 1355: Type I: Staff of 1 to 30 Type II: Staff of 31 to 50 Type III: Staff of 51 to 100 Type IV: Staff of 101 to 200 For a staff over 50: first aid station Stretcher should fit through the door Must be properly marked
56
Provision of Sanitary Premises
When protective clothing or working clothes must be worn: - Changing room In the case of working with carcinogens: - Separate changing rooms for clean and dirty zones Where employees’ safety or health requires: - Resting places, warm-up premises When a staff of 10 or more works simultaneously for a period of over 2 weeks: - Washing facilities 1 wall-mounted basin for every 5 workers, 1 shower with hot and cold running water for every 20 workers For a staff of over 15 working at a building site - Toilet and handwash facilities in separate rooms, next to workplaces, resting rooms, lockers and showers
57
Aspects of the Interior Layout of Sanitary Containers
Ease of access After installation, shock protection (SP) test by professional Proper ventilation, lighting and heating (min. 21 °C) Provision of windbreak fittings At least 2.2 m headroom Window that opens Do not smoke in the container! Sufficient total elbowroom for changing clothes (min. 6 m2 floor area) At least 0,5 m2 free space for each locker to change clothes The changing should be equipped with seating facilities (benches or chairs)
58
Documents To Be Kept On Site (1)
Written Work Order or contract Written Assignment from the Contractor’s employer HSE Manual (basic, site-specific and work manager HSE training) Certificates proving required qualifications Mine Safety exam, Fire Safety exam, Qualified first aid provider, Machine operator, Slinger, etc. Job-related medical fitness opinion Activity-related Operational or Technology Instructions, e.g. for tank cleaning, scaffolding, pressure testing or welding Construction Log List of identifiable on-site tools, machinery and equipment, including typical ID data (e.g. manufacturer/brand, power rating, type)
59
Documents To Be Kept On Site (2)
Statement on the proper technical condition of the tools, machinery and equipment on the list, and to the effect that all required control inspections, H&S commissioning and periodic H&S reviews have been conducted. Manufacturers’ test certificates and inspection documentations of lifting devices, slinging & rigging equipment, gas contamination meters and hand power tools used for work (e.g. shock protection reports) Supplier risk analysis (VEM, HSE Plan) Safety data sheets (MSDS) for the hazardous substances and preparations used Personal protective equipment (EC Certificates of Conformity) Gas contamination meter ‘Bump Test’ report WORK PERMIT Up-to-date Waste Register The work manager must ensure that documents are stored on the working site or within reach.
60
Construction Log The construction log should be kept up to date from the very beginning till the completion of on-site construction work, and made available to the developer’s technical supervisor for inspection and entry whenever so requested. The construction log is a tool (documentary evidence) of communication between/among participants of a construction project. The log is maintained by Contractor Subcontractor Parties entitled to make entries in the construction log: a) Developer, organizer of the project, b) Construction supervisor and design engineer’s site supervisor, c) Contractor and its subcontractor(s), d) Site manager, and e) In specific cases provided for by law, the building authority and other administrative body authorized to inspect and make entries in the construction log, and f) H&E coordinator. Frequency of entries The contractor/subcontractor is required to keep the log on a daily basis, while the construction supervisor (contractor vis-à-vis subcontractor) as required. A construction log must be kept for every activity subject to permission from the building authority (notifiable activities). Government Decree No. 191/2009 (IX. 15.) provides for how to keep construction logs.
61
Consider the following before work:
HSE Meetings Prior to Daily Operations - Toolbox Meeting Consider the following before work:
62
Leaving the Work Area Notification to the area manager
Stopping and securing machinery against accidental restart Power down of electrical equipment Storage of combustible materials and gas cylinders at designated places Implements and structural components are stabilized and secured for storm or other natural incident Fencing of excavations Prevention of unauthorized access to the site Fire safety-oriented site inspection Maintaining order on the site
63
Rules Applicable To Official Inspections (1)
The work manager is required to cooperate with the authorities during official on-site inspections. The health & safety authority is entitled to take measures as provided for by law and proceed against those whose responsibility is established. Severe Safety Hazards: Failure to perform H&S commissioning or periodic safety reviews Lack of risk assessment Inoperable or missing personal protective equipment Failure to meet coordination obligation Failure to perform job fitness checks The amount H&S fine ranges between HUF 50,000 and 10,000,000. 63
64
Rules Applicable To Official Inspections (2)
Supervisor of the H&S authority is entitled to: conduct inspections, call upon the employer to meet occupational health & safety requirements, obligate the employer to eliminate deficiencies, ban an employee from a job if his/her work is objectionable, order the use of a work equipment, personal protective equipment or hazardous substance/preparation to be suspended ask any information he/she deems necessary for the inspection from any person on the working site, and verify the identity of such person, and turn to the Police if he/she is prevented from conducting the inspection. 64
65
H&S Inspections and Consequences
HSE-oriented check of contractor’s work: - performed by MOL representatives, - contractor is represented by the work manager, focused on the safety of work as well as the adequacy and suitability of personnel, machinery and documents. Delivery of requirements: - Annex to the Contract - HSE consultations - HSE trainings Site handover HSE Plan Work Permit Ban of a company from MOL/TVK sites for a specified period of time Ban of a work manager from MOL/TVK sites for a specified period of time Ban of an employee from MOL/TVK sites for a specified period of time Imposing HSE penalty on the general contractor (even in case of subcontractor’s failure) Withdrawal of the Work Permit, repeated permit procedure Repeated HSE training Checking requirements: Ongoing monitoring by the operator Inspection of the Project/Petrolszolg HSE audit/visit
66
Reporting HSE Incidents To MOL
Notifiable incidents: Near misses Personal injuries (cases requiring first aid, lost time, no lost time and fatal injuries) Traffic injuries (on MOL premises) Fires/explosions Spills Incidents causing property damage _______________________________________ - When in doubt, it is better if you report the incident. It is the contractor’s duty to report accidents at work to the competent authorities as provided for by law) Primary intervention (first aid, intervention, securing the area, Ambulance, Fire Brigades, etc.) Reporting the incident to MOL Person involved in the incident or eye witness Work manager MOL/TVK contact person Failure to report an incident is subject to sanctions.
67
Investigation of HSE Incidents
MOL will investigate all notifiable contractor incidents (as required by its internal policies) using its own methodology The contractor is required to cooperate in the above-mentioned investigation procedure as follows: The contractor should allow - people involved in an incident to be interrogated, - equipment and materials involved to be inspected, and the MOL representative to have access to contractor’s regulations. Incident Investigation Identification of corrective measures Purpose: Identification of the root causes and implementation of corrective measures to prevent reoccurrence. Implementation of corrective measures If, pursuant to the relevant legislation, the contractor is obliged, as an employer, to investigate an incident, it should involve MOL in the procedure.