Presentation is loading. Please wait.

Presentation is loading. Please wait.

MATERIAL Requirements planning MRP

Similar presentations


Presentation on theme: "MATERIAL Requirements planning MRP"— Presentation transcript:

1 MATERIAL Requirements planning MRP

2 PLANNING AND CONTROL ACTIVITIES IN MANUFACTURING ENTERPRISE
Strategic plan Sales&Operation Plan (Aggregated Production Plan) Master Production Schedule (MPS) Material Req. Planning (MRP) Purchasing Control Production Control Input /Output Control Detailed Capacity Req. Planning Rough-cut Capacity Plannig Resource Planning Plan Execution Demand Demand Forecasts Customers Orders Resources

3 Materials Requirements Planning MRP
MRP system Production and inventory management system in dependent demand inventory environment . System was developed by Orlicky in the early seventies of last century MRP determines the items orders quantities and the time periods (time „buckets”) in which those orders must be placed to meet MPS needs. Backgraund of MRP Distinction of independent demand and dependent demand inventory Availability of relatively powerful, reliable and cost-efective computers

4 Independent and Dependent Demand
INDEPENDENT DEMAND - the demand for item is independent on the demand for others item.. The typical dependency is only on external customer demand. Final products and spare parts inventory. DEPENDENT DEMAND - demand for item is dependent upon the demand for some other item (parent item). Components and raw materials Bill of Materials CAR WEEL TIRE

5 Stock Consumption and Demand Inventory Reorder Point System used in dependent inventory case
Independent demand Car Dependent demand Weel RP Product STOCK CONSUMPTION Demand STOCK DEMAND Tire Discontinuous Steady and Continuous Time Time Assembly Time Time Component Time Time

6 Materials Requirements Planning Inputs/Outputs
MRP inputs Master Production Schedule Bill of Materials Inventory Status Lot size (lot sizing method) Lead Times MRP outputs Planned manufacturing order releases Planned purchasing order releases

7 Basic Structure of MRP system
MASTER PRODUCTION SCHEDULE (MPS) MATERIAL REQUIREMENTS PLANNING (MRP) Gross Requirements Net Requirements 3. Lot sizing 4. Offsetting. Backward scheduling Inventory status On hand inventory Scheduled receipts of openned orders Bill of Materials Master Items File Lot size, Lead time Planned Purchasing Order Releases Planned Manufacturing Order Releases

8 MRP explosion BOM MRP explosion in time X B C D F E (2) (3) (4) (1) 1
Level 1 2 3 4 6 5 Week p – production z - purchasing Ez Dp Bp Ez Xp X MPS Ez Cp Fz Product structure X - Bill of Material (BOM) Total (cumulated) lead time of Product X

9 Projected available t - 1 Safety stock paramiter
MRP Logic Gross requirements calculation (MPS + Bill of Materials) Net requirements calculation (NRt = GRt – SRt – PAIt-1 + SS) Lot Sizing – order quantity calculation using proper lot sizing method Backward scheduling (Timing) – placing a planned order in the appropriate time period Net req-ments t Gross req-ments t Scheduled receipts t Projected available t - 1 Safety stock paramiter = - - + Item: B Period t (week) 1 2 3 4 5 6 7 Lead time: 1 Gross requirements 30 60 50 Safety stock: 0 Scheduled receipts Lot sizing method: LFL Available inventory Net reqirements Planned receipts Planned order releaces Rekord MRP item B

10 Lot Sizing ? Part C Periods (weeks) 1 2 3 4 5 7 8 6 Net requirements
Planned order release 20 ? LOT SIZING ALGORITHMS 1. Lot for Lot - LFL 2. Fixed Order Quantity - FOQ 3. Economic Order Quantity - EOQ 4. Fixed Period Requirements -- FPR 5. Period Order Quantity - POQ 6. Least Unit Cost - LUC 7. Least Total Cost - LTC 8. Part-Period Balancing - PPB 9. Wagner-Whitin Algoritm - WW

11 Algorithm 1 – Lot 4 Lot Lot size = net requirements
Example Planning horizon = 9 weeks Period = 1 week Holding cost H = 1 $/unit/week Order cost (set up cost) S = 100 $/order Week 1 2 3 4 5 6 7 8 9 Total Net requirements 35 10 40 20 5 10 30 150 Lot size 35 10 40 20 5 10 30 150 Inventory Holding costs TH = 0 Setup costs TS = 700 Total costs TC = 700

12 Algorithms 2 - 3 Assumption: Lot size is fixed, order period is variable Algorithm 2 – lot size is set up. Algorithm 3 – lot size is calculated using EOQ model Example: Algorithm 2 (lot size is fixed FQ = 60 units) Week 1 2 3 4 5 6 7 8 9 Total Net requirements 35 10 40 20 5 10 30 150 Lot size 60 60 60 180 Inventory 25 15 15 35 35 15 10 30 180 Holding costs TH = 180 Setup costs TS = 300 Total costs TC = 480

13 Algorithms 4 - 5 Assumption: Order period is fixed
Algoritm 4 – order period is set up. Algoritm 5 – lot size is calculated using EOQ model Example: Algoritm 4 (order period is fixed FP = 3 weeks) Week 1 2 3 4 5 6 7 8 9 Total Net requirements 35 10 40 20 5 10 30 150 Lot size 45 60 45 150 Inventory 10 20 20 40 30 120 Holding costs TH = 120 Setup costs TS = 300 Total costs TC = 420

14 Algorithms 6 - 9 Assumption: Lot size is variable, order period is variable Example: Algoritm 9 (Wagner’s Whitin’s algorithm) Week 1 2 3 4 5 6 7 8 9 Total Net requirements 35 10 40 20 5 10 30 150 Lot size 45 65 40 150 Inventory 10 25 25 5 30 95 Holding costs TH = 95 Setup costs TS = 300 Total costs TC = 395

15 Master Production Schedule
Week t 1 2 3 4 5 6 7 (MPS) Product X 15 30 25 Master item: X Week t 1 2 3 4 5 6 7 Lead time: 1 Gross requirements 30 25 Safety stock: 0 Scheduled receipts Lot size: LFL Projected available Net requirements Planned receipts 15 Planned orders release 15 15 15 Item: C (2) Week t 1 2 3 4 5 6 7 Lead time: 2 Gross requirements 60 50 Safety stock: 0 Scheduled receipts Lot size: FQ 50 Projected available 20 10 Net requirements 40 Planned receipts Planned orders release x2 x2 x2 x2 30 30 50

16 One week later Item: C (2) Week t 2 3 4 5 6 7 8 Lead time: 2
Gross requirements 60 50 40 Safety stock: 0 Scheduled receipts Lead time: FQ 50 Projected available 30 20 10 Net requirements Planned receipts Planned orders release 50 Order released in week 1

17 MRP versus Order-Point Systems

18 Benefits of MRPII/ERP system implementation in an organisation
Reduced Inventory with fewer (none) shortages Improved Customer Service Improved Direct Labour Productivity Reduced Purchasing Cost Reduced Obsolescence Reduced Overtime Plan for future capacity needs


Download ppt "MATERIAL Requirements planning MRP"

Similar presentations


Ads by Google