1 ORIO Project Plan Procurement Bas Schilperoort Opening slide

2 ORIO procurement ODA money Untied aid
Goods and services for the project should be purchased in a transparent and efficient manner in accordance with legislation in the Applicant's country, the OECD Good Procurement Practices for Official Development Assistance, CSR compliance form: OECD Guidelines for Multinational Enterprises (edition 2011). IFC Performance Standards Conventions of the International Labour Organisation

3 Procurement plan Procurement guidelines:
Describe the procurement method and approach for each of the phases for goods and services, including the partners' division of roles. What type of tender procedure (International Competitive Bidding, Limited International Bidding, National Competitive Bidding) will be used or, in case of direct negotiations, how will the firm be selected? Explain how the procurement method complies with local procurement rules, OECD Good Procurement Practices for Official Development Assistance

4 Procurement plan # Name of package
Original price of package in Grant Arrangement Method of ' selection Contractors' selection time Contract impl. time Sources of finance Type of contract EUR local currency 1 ICB/NCB/ Direct app. Q. Year… # months ORIO/CA donor/ loan works, goods services 2 3 4 5 Total - Procurement plan

5 Procurement plan (example)
No. Name of package Budget Method of contractors' selection and bidding methods Contractors' selection time Contract implementation time Sources of finance % Type of contract 1 Project coordination and supervision ICB Q3 2015 48 months ORIO (35%) + MioB (65%) Services 2 Construction Works Section A (Dalb-Gdal) Q2 2016 22 months Works 3 Construction Works Section B (Chag-Gestamova) 33 months 4 Construction Works Section C (Duurtuu-Daga) 5 Operation & Maintenance ( All 3 Packages) NCB Q4 2016 Total EUR 1= SEN 65.48

6 No objection process ORIO “no objection” needed for next step in procurement process: The complete draft set of tender/bidding documents including: media for notice, draft contracts and proposed independent engineer or employers representative Tender evaluation report Final draft contract prior to signing

7 Type of contract Reflects the structure of the project;
Affects the procurement process; Reflects the organisation of the imlementation of the project and the rights and obligations of the client and the contractor. Use internationally accepted standards.

8 Supervision Works contracts > EUR 2.5 million
Contracted before start tender procedure works contract Employed by client, but acts in the interest of the project Main responsibility: Supervise implementation of the contract. Additional: CSR Preparation of progress and monitoring reports for CA / ORIO