Presentation is loading. Please wait.

Presentation is loading. Please wait.

ELECTRICAL SAFETY TASK GROUP

Similar presentations


Presentation on theme: "ELECTRICAL SAFETY TASK GROUP"— Presentation transcript:

1 ELECTRICAL SAFETY TASK GROUP
Task Group 5 Risk Assessment and Arc Flash Controls for Normal Operations Greg Christensen, INL July 18, 2016

2 PARTICIPANTS Scot Winningham Earl Myott Jennifer Martin Russ Moder
Jerald Kinz Todd Kujawa Craig Shaw Kevin Gurbisz Tommy Martinez Jaqueline Mirabal-Martinez Matthew Giardina Jackie McAlhaney Earl Myott Russ Moder Mike Minard Glen Mirocha Frank Perrotta Glenn Anderson Greg Christensen Robert Fry Ray Joggerst Rick Ramirez Dan Evans Omar Al Atassi

3 BACKGROUND NFPA 70E 2015 Employers are responsible for assessing the risk from the arc hazard for employees that interact with electric equipment

4 BACKGROUND NFPA 70E recognizes arc flash hazards may exist even when equipment is in an enclosed condition. This includes operators whose only interaction is with the equipment in an enclosed condition. There are situations where opening or closing a switch or breaker has been a contributing factor to an arc flash event.

5 GOAL Develop a best practice for:
Risk Assessment and recommendations for verifying proper installation, minimum maintenance requirements and no evidence of impending failure for assigning arc flash controls

6 BEST PRACTICE Elements of Best Practice Risk Assessment
Verifying Proper Installation Minimum inspection, testing and maintenance requirements for overcurrent protection devices (OCPDs) Verifying no evidence of Impending failure Additional considerations i.e. engineering controls, configuration, environment, venting, egress, documentation, etc.

7 Documentation required!
ASSESSING RISK Documentation required! Installed properly Maintained properly Doors closed and secured Covers in place and secured No evidence of impending failure Annex F Risk Assessment has 38 sample questions to ascertain compliance with first two criteria.

8 THRESHOLDS FOR ARC FLASH
≤ 125 KVA at < 240 V and < 1.2 Volts is exempted (assumes calculated in accordance with approved method in accordance with NFPA 70E or IEEE 1584)

9 VERIFY INSTALLATION Electrical Inspection Program – Task Based Risk Assessment 1) Permit - Obtain an Electrical Work Authorization Document or Electrical Installation Permit 2) Engineered - Engineering Design Document that has taken into consideration the environment and application of the equipment to be installed. 3) Inspection or Examination – Inspection performed by a qualified NEC inspector or an AHJ delegated to perform such inspections. 4) Approved or Accepted– The inspection is approved and documented by NEC Inspector or AHJ, & work authorization document or permit is closed. 5) Required Labeling – Visual indication that the installation was performed in accordance with the required by applicable standards. i.e. Stickered

10 VERIFY INSTALLATION Electrical Inspection Program – Task Based Risk Assessment Qualified Person’s Initial Observation of Equipment Installation – Real Time Risk Assessment 1) Covers in place (screws, fasteners are engaged) 2) All penetrations are closed or sealed (is venting in the front?) 3) Conduits, Fittings are secured and complete 4) Handle or Switching mechanism is intact (appears functional) 5) Equipment meets field labeling requirements (reviewed in last 5 yrs) 6) No Suspect/Counterfeit/Recalls 7) Field Modifications have been evaluated

11 VERIFY INSTALLATION Resources:
NFPA 70 Definitions: Approved, Qualified Person, Authority Having Jurisdiction NFPA 70 Article 90.7 & Examination, Identification, Installation and Use of Equipment NFPA 70 Article Approval of Conductors and Equipment NFPA 70 Article Arc Flash Hazard Warning Labels NFPA 70 Article (A) Maximum Available Fault Current Labeling & (B) Modifications NFPA 70E 2015 Article (D) Arc Flash Risk Assessment Equipment Labeling

12 OVERCURRENT PROTECTION
Need to Maintain overcurrent protection

13 Power Breakers 3 – 5 year Cycle Cleaning and inspection Lubrication
Thermal imaging Torqueing connections Mechanical exercise

14 Power Breakers Performance Testing Needed
Secondary or primary current injection Instantaneous test to validate trip mechanism and arc flash calculation Ground fault, short term and long term delay to validate equipment protection

15 Molded Case Circuit Breakers
3 – 5 Year Cycle Cleaning and inspection, torque connections, Thermal Imaging - Energized, with loading greater than 40% of rating with covers removed Torque connections to ensure no hot spots Mechanical exercise

16 Molded Case Circuit Breakers
Performance tests should be performed: Instantaneous testing performed to validate trip time of breaker and arc analysis results. Short Term and Long Term Delay should be performed to validate equipment protection

17 Fuses 3 - 5 Year Cycle Cleaning and inspection
Check fuse clips for tightness

18 Tools Torqueing calibrated tools Document and record values
Torque per manufacturer’s requirements Remote racking equipment

19 Resources and references
NFPA 70E Standard for Electrical Safety in the Workplace 2015 Chapter 2 NFPA 70B Recommended Practice for Electrical Equipment Maintenance IEEE Recommended Practice for the Selection, Field Testing and Life Expectancy of Molded Case Circuit Breakers for Industrial Applications NEMA AB 4 Guidelines for Inspection and Preventative Maintenance of Molded Case Circuit Breakers Used in Commercial and Industrial Applications

20 IMPENDING FAILURE QUESTION:
You can’t see inside or the back of the breaker

21 PRACTICAL CONCERNS 25 cal/cm2 Incident Energy Properly installed
Properly maintained Cover on and secure no evidence of impending failure Risk = high consequence/low probability Consensus of the group some level of PPE is still recommended for this risk. = Serious injury if event occurs.

22 RISK High Probability Low Probability High Consequence Severity
Low Consequence Frequency Upper left quadrant – Beware - here is the problem, the brain is telling you the likelihood (probability) is low so one may take no action to protect from an arc flash (the employee thinks properly installed, properly maintained … hence no PPE required) However if an arc flash does happen the results will be the same as in the upper right quadrant of this table.

23 PPE for OPERATIONS If bounding conditions are NOT met then arc rated clothing and PPE must meet the available incident energy level >40 cal/cm2 remote racking or other engineered control to remove the employee from the hazard zone should be employed Consider Hierarchy of Controls

24 PPE for OPERATIONS If risk assessment indicates the conditions for proper installation, maintenance and no evidence of impending failure are met: Underlayer must be non-melting Minimum for outer layer is non melting Arc rated clothing recommended > 1.2 cal/cm2

25 CONCLUSION Risk assessment to evaluate bounding conditions for proper installation, maintenance and no evidence of impending failure must consider many discreet factors to be effective and provide a high level of safety for breaker operations. See also EFCOG Best Practice #192 “Guide to Incorporating Risk Assessment into ISM for Electrical Safety”

26 POSSIBLE FUTURE GOALS Each site should evaluate implementation of this process Survey workers regarding their questions or concerns Identify lessons learned for implementation Study accident trends associated with breaker operations

27 QUESTIONS?


Download ppt "ELECTRICAL SAFETY TASK GROUP"

Similar presentations


Ads by Google