Download presentation
Published byBrandon Morris Modified over 7 years ago
1
Understanding Causes of Structural Failures by Fred Nelson, P. E. , S
Understanding Causes of Structural Failures by Fred Nelson, P.E., S.E., Vice President, Gervasio & Associates, Inc. ASCE/ASHE Conference – Sept. 2016
2
SECTION SUMMARY Lessons Learned from Historic Failures
Design and Agency Errors Defective Construction Material Deficiencies Excessive Loadings Deterioration and Degradation Maintenance and Operation Errors Terrorist Acts Bonus Presentation – Mudslide Deployment in Oso Washington
3
Lessons Learned from Historic Failures: Sources of Information are: (1) ASCE Failure Case Studies in Civil Engineering, c. 2013; and (2) Google Website
4
Leaning Tower of Pisa
5
Background and Lessons Learned from Tower of Pisa
The tower was built in phases: the first four floors were built from 1173 to 1178; the next three floors were built between 1272 and 1778; and the third construction phase for the bell tower was between 1360 and 1370. Foundation failure (resulting in tower rotation) has occurred continuously for over 800 years. The 200 ft. high tower reached a horizontal tilt of 17 ft. by 1993, with an south inclination of almost 5.5 degrees. Despite extensive investigations and analyses over the past 60 years, there is still no consensus on the failure. Finally, after 8 centuries, the tower has been stabilized, via the use of a soil extraction method.
6
1976 Teton Idaho Dam Failure
7
Background and Lessons Learned from Teton Dam Failure
Zone-filled earth dam, 300 ft. high - reservoir filling commenced in November 1975. Dam failed on June 5, 1976, when water level was 30 ft. below crest. Breaching was preceded by a period of two days with increasing quantities of seepage. At 10:30 A.M., the seepage was approximately 15 cfs in a 6 ft. tunnel. By 11:00 A.M. a vortex was observed in the reservoir, and the crest was breached at 11:55 A.M. It was the tallest dam to have failed. The failure helped engineers to learn (1) the need for instrumentation; (2) protective filters to prevent seepage erosion; (3) design of cut-off trenches; (4) the effect of frost action; (5) the importance of adequate compaction control criteria and methods.
8
Tacoma Narrows Bridge - 1940
9
Background and Lessons Learned from Tacoma Narrows Bridge Failure (Evaluated by the “Board of Engineers”) Bridge was well designed and built to safely resist all static forces. Its failure resulted from excessive oscillations made possible by the degree of flexibility of the structure…its deck/span ratio was an unprecented 1:350. During its service, under steady winds of an estimated 25 to 35 mph, the bridge experienced gentle amplitudes of 4 ft. that were considered to be normal and not dangerous. The solid plate girder and deck acted like an “aerofoil”, creating both “drag” and “lift” via the Karmon Vortex effect. The initial failure was the slippage of the cable band on the north side of the bridge, which may have initiated torsional oscillations. After this failure, more studies were needed done on future bridges to (1) consider the aerodynamic effects of wind; and (2) to eliminate the aero-elastic instability that pushed Galloping Girtie to failure.
10
Kansas City Hiatt Regency Failure
11
Failure resulted from a change in a hanger detail that was not fully evaluated by the Engineer of Record…resulted in 4 times the design stresses. In addition, there was no redundancy in hangers
12
Background and Lessons Learned from Hyatt Regency Failure
The technical reason was easy to understand. There is a need for all parties to understand their responsibilities and to perform their assignments properly. The structural engineer is responsible for the overall structural integrity, including the performance of connections was firmly established in this case…the structural engineer did not evaluate the loads on the connections. The failure also reinforced the need for practices such as project peer review and constructability checks.
13
Hartford Civic Center Roof Collapse in 1978
14
Roof Section and Inverted Pyramid Module
15
Three Dimensional Drawing of Roof Space Truss Module
16
Top Chord Bracing Issue…One of Three Conflicting Collapse Theories…the other Two were Torsional Buckling and Inadequate Welding
17
Background and Lessons Learned from Hartford Civic Center Roof Collapse
With clear spans of 210 and 270 ft. between four pylon supports, the “inverted pyramid” space structure was near record size. The roof collapsed before dawn on January 18, 1978 after a snowstorm (15 to 18 psf) and just hours after fans left a well-attended basketball game. Although the design assumed that the compression members were braced at mid-span, they in fact were not…these members buckled. The use of struts without cross bracing did not provide diaphragm action for bracing the top chords. The roof dead loads were also seriously underestimated at 40 psf, when they were actually 53 psf…a 20% reduction. The investigation revealed that excessive deflection occurred during the construction phase…and the engineer of record dismissed this information. This case is a lesson that computer software is a tool, and not a substitute for sound engineering experience and judgment.
18
Boston’s Big Dig Ted Williams Tunnel Ceiling Collapse
19
Background and Lessons Learned from Boston’s Big Dig Ceiling Collapse
The ceiling collapse occurred on July 10, 2006 when a concrete panel and debris weighing 26 tons and measuring 20 ft. by 40 ft. collapsed. The failure began with the simultaneous creep-type failure of several anchors embedded in epoxy in the tunnel’s roof slab…this became a progressive collapse. Not only were the bolts too short, but the epoxy was not of the type that could sustain continuous tension loads. The “Powers Fasteners” epoxy used to hold the bolts in place cost $1, The cost of repair was $54 million.
20
The I-35 Bridge Mississippi River Collapse
21
Background and Lessons Learned from I-35 Bridge Collapse
The bridge was built in 1967 and collapsed on August 1, 2007, resulting in 13 fatalities and 145 injuries. At the time of the failure, loads on the bridge, including added loads during service (thicker road beds) and construction loads (staged sand and gravel for making concrete and equipment) exceeded design loads. The failure was determined to be at 24 gusset plates that were ½ the required thickness for the original design…consistent with tears in the gussets observed in the collapse debris. The bridge was poorly rated and had been on MnDOT’s radar for many years. The “design error” escaped discovery during numerous inspections and repair operations over the years, including the last “in depth” inspection in June 2006. The failure was formally evaluated by NTSB and Wiss Janney Elstner and Lichtenstein & Associates.
22
A “Blue Ribbon” Committee and Dedicated Contractor Combined to Construct a New Bridge and win the Public’s Confidence, which opened on September
23
Design and Agency Errors from G&A Files
24
Two Design Failures of MSE (Mecanically Stabilized Earth) Walls
25
MSE Wall Failure at Overpass
31
MSE Wall Failure after Water Leak
38
Flyash Tank Design and Material Failure: Engineer’s Assumptions resulted in design for only one half of the actual hoop stresses, and fabricator used undocumented foreign bolts of less strength than specified by engineer
39
Flyash Tank Failure
42
Failed Bolt Taken from Debris
43
Bolt Failed by Laboratory Torsion
Bolt Failed by Laboratory Shear
44
Dairy Tank Failure…Due to Failed Pipe Delivering Sulfuric Acid
47
Design Failure: Engineer did not Account for Thermal Concrete Shrinkage Stresses in Large (20 Million Gallon) Reservoir. After initial Filling in December with CAP water, Tank Lost 1 ft. of Water (1 million Gallons) of Water Daily for Seven Days before Problem was Realized. Simpson Gumpertz and Hager Study verified 1/32 inch cracks would pass water more than that which was lost.
48
Large Underground Water Storage Tank Leakage
49
Partial Floor Plan of 20 million Gallon Concrete Water Tank (20 ft
Partial Floor Plan of 20 million Gallon Concrete Water Tank (20 ft. High)
50
No Joint between Columns
Footing Restrains Slab Movement
53
Agency Error: Mill Avenue (Construction) Bridge Collapse under a flood of 125,000 to 140,000 cfs, when the Agency required it to be designed for only 30,000 cfs
64
Severe Wind Damage to Poorly Supported Glass Masonry
69
Field Notes showing Missing Glass Masonry
70
Underdesigned Concrete Wastewater Tank
73
Defective Construction (From G&A Files)
74
Grain Dryer Collapses: Caused by (1) Lack of Design; and (2) Defective Construction
80
Empty Grain Bin Failure during Strong Winds
81
Contractor Drilled Through Concrete Pipe while Installing Sheet Piling
83
Boring into Existing Water Main
85
HARDESTY, ALBERTA, CANADA RAIL TERMINAL COLLAPSE DURING WIND STORM
93
Maintenance and Operation Errors From G&A Files
94
Concrete Formwork Failure
95
Concrete Formwork Failure
96
Material Deficiencies From G&A Files
97
Truss Failure During Reroofing
99
Airplane Speared by Debris from Failed Canopy During Wind Storm (defective column base plate welds)
102
Overload Failures from G&A Files
103
Two Case Studies in Overload Failures, involving Concrete trucks and Bridges
104
Concrete Truck Overloaded Old Bridge
107
Out-of-Control Concrete Truck Impacts Bridge
113
Roof Collapse due to Ponding from Inadequate Drainage
115
Deterioration and Degradation Examples from G&A Files
116
1925 Water Tank Evaluation and Repairs
121
Repair Drawing of 1925 Water Tank
122
Finished Tank now an Attractive Part of Gilbert AZ Landscape
123
Precast Concrete Cylinder Pipe Failure
128
Arizona Dam Spillway Repairs
Recipient of the ICRI Award of Excellence for Outstanding Concrete Repair Projects 2003
132
The engineer……… just hanging around!
133
Wall pier with huge delamination.
136
Rope access to identify delaminated concrete.
137
Chipping on delaminated concrete to verify extent of damage
138
Rigging access to bottom of the spillway slab
140
Investigation of bottom of the spillway slab
Investigation of bottom of the spillway slab. An extremely difficult place to access.
141
Preparations during the repairs for shotcrete.
142
Dry shotcrete repair process.
143
for Outstanding Concrete Repair Projects
Sports Stadium Recipient of the ICRI Award of Merit for Outstanding Concrete Repair Projects 2007
144
Steel floor beam below. Project started with trip and fall concerns on the concourse floors.
145
Heavily corroded steel floor beams.
146
As much as one half of top flange thickness was lost
As much as one half of top flange thickness was lost. Over 5/8” in some cases.
147
Shoring from structure above.
Concourse floor beam repairs.
148
Carbon Fiber Rod Reinforcement
149
Prestress tendons completely corroded away
150
Hollow core concrete plank repair
Prestress tendons
151
Cable Roof Structure Repair
153
Lost Tension in Roof Cable
155
Old Swimming Pool Floatation Failure
159
Dome Failure
161
What evidence do we look for at the scene?
The mechanical equipment Cable damages Damage to fabric Foundations Damage to small doors Damage to overhead doors at vehicle entry Fabric quality Wind damage to outside equipment
162
Does the mechanical equipment work properly?
163
The cables were slack, but there was no failures or damage.
164
A lot of perimeter tears
165
This drawing shows the major fabric tears.
166
Major tears occurred at the towers.
167
No damage to foundation.
168
Small doors overturned.
169
One door did not overturn, but had moderate base damage.
170
At the vehicle entry, the outside door was upside down.
171
The upside down door became the focus of the investigation.
172
The six panels had bend outward at the middle and came off tracks.
173
A protocol for testing the door was established and lab testing was done to determine the failure pressure.
174
The company that furnished the air inflated dome, came to the scene, and repaired the damages, reinserted the perimeter into the foundation and reinflated the dome…at night. They were from Canada and could not endure our Arizona heat.
177
Terrorist Acts FEMA Urban Search and Rescue Deployments
178
Murrah Building Bombing: April 19, 1995
179
Large Explosion - Crater & E Q
Next 1.1-9c
180
Exterior Explosion Loading
over pressure over pressure spherical shock wave reflected pressure Explain: Spherical shock wave Initial reflected pressure Over pressure Drag forces drag over pressure stand-off 1v 1s
181
Exterior Explosion Loading
Exterior walls, columns & windows A Roof & Floor slabs B Successive Loading of structure - in milliseconds Also mild EQ Frame C Ground shock 1s
182
Note that the Murrah Building was designed in 1970
Note that the Murrah Building was designed in The beams were designed with positive (bottom) reinforcing steel between columns and negative (top) reinforcing steel over the columns.
185
World Trade Center: September 11, 2011
187
The Pentagon was also attacked in coordinated attacks by our enemies on September 11, 2011
188
September 11, :43 am.
190
“E” RING LEAN-TO COLLAPSE, SMOLDERING
191
Bonus Presentation – March/April 2014
Oso, Washington Mudslide Presentation
192
OSO WASHINGTON (ROUTE 530) MUDSLIDE
202
SUMMARY COMMENTS All of us represent more than just ourselves.
Each person has special talents. Develop them and appreciate other’s talents. When we do “1” and “2” very well, we have an aura about ourselves, which others notice and which motivates others to do good. This whole business of Performing Forensic Engineering is a Process, not an Event. What we learn takes time and experience.
Similar presentations
© 2025 SlidePlayer.com Inc.
All rights reserved.